| Trade | Activities | Complete | Behind plan | % complete |
|---|---|---|---|---|
| Millwrights | 101 | 99 | 0 | 98% |
| Rigging and Heavy Lift | 6 | 6 | 0 | 100% |
| Piping | 5 | 4 | 0 | 87% |
| Electrical and Instrumentation | 4 | 4 | 0 | 100% |
| Scaffolding | 3 | 2 | 0 | 67% |
| Insulation | 1 | 0 | 0 | 5% |
| Concrete | 1 | 1 | 0 | 100% |
| Survey and Layout | 5 | 4 | 0 | 80% |
| Welding and QA/QC | 6 | 4 | 0 | 67% |
| Commissioning | 5 | 0 | 0 | 0% |
| Line Boring and Machining | 6 | 6 | 0 | 100% |
| Project Management and Procurement | 22 | 18 | 0 | 82% |
2026-09-08 Paper on the reel
2026-10-06 Project turned over
| Ref | Delay | Cause | Responsible | Dates | Days | Status |
|---|---|---|---|---|---|---|
| D-001 | New press section fabrication late at the OEM | Material delivery | Third party | 2026-06-05 to 2026-06-14 |
9 | AGREED |
| D-002 | Press frame anchor bolts seized at removal Daily log: Apex Rigging and Crane 2026-08-09; Photo: IMG_press_frame_anchor_bolts.jpg |
Site condition | Client | 2026-08-09 to 2026-08-10 |
1 | AGREED |
| D-003 | Idler bore IB-2 out of round deeper than surveyed Other: Line bore report IB-2, pass 3 |
Site condition | Client | 2026-08-11 to 2026-08-12 |
1 | AGREED |
| D-005 | New press frame sole plate shims re-cut Daily log: Apex Rigging and Crane 2026-08-19 |
Subcontractor performance | Subcontractor | 2026-08-19 to 2026-08-20 |
1 | AGREED |
| D-004 | Blow box BB-2 supply duct flange does not match Drawing: M-3140-02 rev B; Other: PO-7730-01 delivery ticket |
Design, drawing or RFI | Third party | 2026-08-20 to 2026-08-26 |
3 | AGREED |
| D-006 | Felt roll FR-02 bearing housing bore undersize at receipt Other: Receiving inspection FR-02 |
Material delivery | Third party | 2026-08-22 to 2026-08-24 |
0 | AGREED |
Days are counted for each delay on its own. Delays can run at the same time, so they are not added into one project delay.