Portfolio
Every project on one page. Each row reads the same figures as that project's master and PM boards.
Projects
3
Source: project
Budget, projects with cost
$34,218,300
Source: cost_account
Forecast, projects with cost
$35,077,800
Source: cost_account
Delays logged
3
Source: delay
Missed dates awaiting contractors
10
Source: missed_date
| Project | Safety | Phase | Complete | Late | Budget | Forecast | CPI calc | SPI calc | Delays | Needs attention | Next milestone |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Demo Plant Expansion DEMO-01 · Demo Client · 4 boards |
TRIR 0.00 calc 1 work stopped 1 permit expired 1 action overdue trained 50% |
Construction | 1 / 14 | 3 | $1,003,000 | $1,054,000 | 0.81 | 0.84 | 3 client days MISSING |
Feeds late
|
2026-11-02 Mechanical completion Process Building |
| Demo Water Treatment Plant DEMO-02 · Demo Utility · 4 boards |
TRIR MISSING calc trained MISSING |
Construction | 1 / 6 | 2 | $850,000 | $880,000 | 0.93 | 0.77 | 0 |
Feeds late
|
2026-11-20 Clarifier 1 ready for equipment |
| Paper Machine 3 Press and Dryer Section Rebuild PM3-REBUILD · Demo Paper Mill · 12 boards |
TRIR MISSING calc trained MISSING |
Engineering and Procurement | 28 / 165 | 0 | $32,365,300 | $33,143,800 | 0.89 | 1.00 | 0 |
Feeds late
|
2027-01-10 Machine down: last paper off the reel |
Source: project, activity, cost_account, delay, missed_date, meeting_item · totals add only projects that have a cost report