XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Paper Machine 3 Press and Dryer Section Rebuild ?

Demo Paper Mill · Pulp and paper outage rebuild · Demo Mill, PM3 · 2026-05-04 to 2027-03-31

Preconstruction 2026-05-04 → 2026-06-05 5 / 5 gates Engineering and Procurement 2026-06-05 → 2026-12-19 2 / 4 gates Construction 2026-12-19 → 2027-02-09 0 / 5 gates Commissioning and Startup 2027-02-09 → 2027-02-21 0 / 4 gates Turnover and Closeout 2027-02-21 → 2027-03-31 0 / 5 gates

Is this page current? Some feeds are late

CM look-ahead NEVER never written · expected every 24 h
Contractor daily logs NEVER never written · expected every 24 h
Cost report OK 0 min ago · expected every 7 d
Doc control drawings NEVER never written · expected every 24 h
Meeting records NEVER never written · expected every 7 d
Procurement register OK 0 min ago · expected every 7 d
Schedule (P6 export) OK 0 min ago · expected every 24 h
Watch list register NEVER never written · expected every 24 h
0 recordables
TRIR MISSING calc · supervision trained MISSING
Source: safety_observation, safety_pretask, safety_toolbox, safety_inspection, safety_permit, safety_action, safety_stop_work, safety_incident, daily_log, training_attempt, safety_card
Activities complete
28 / 165
Source: activity
Late activities
0
Source: activity
Budget
$32,365,300
Source: cost_account
Forecast at completion
$33,143,800
Source: cost_account
Cost performance (CPI) calculated
0.89
Source: cost_account, activity · earned value / actual cost, trades with a cost source
$32,365,300
approved changes $0 · 0 pending ($0) · value returned $0
Source: cost_account, change_order, backcharge
0
of 8 PO lines · 0 with no promise date
Source: material_item, activity

Schedule and budget by trade

TradeTrade leadActivitiesCompleteLate% completeBudgetEarnedActualForecastCPI
Millwrights Dale Whitaker 1012 0 2% $3,250,200$511,900$542,600$3,250,200 0.94
Rigging and Heavy Lift R. Okafor 62 0 33% $1,150,100$619,300$656,400$1,150,100 0.94
Piping Marcus Lee 52 0 40% $1,320,100$1,077,600$1,142,200$1,320,100 0.94
Electrical and Instrumentation Priya Raman 42 0 50% $1,380,000$1,226,700$1,300,300$1,380,000 0.94
Scaffolding Tony Alvarez 31 0 33% $609,900$435,700$461,800$609,900 0.94
Insulation Beth Carver 10 0 0% $340,000$0$0$340,000 MISSING
Concrete Luis Ortega 10 0 0% $150,000$0$0$150,000 MISSING
Survey and Layout Hannah Price 52 0 40% $124,900$72,900$77,300$124,900 0.94
Welding and QA/QC Grant Fowler 62 0 33% $210,100$85,600$90,700$210,100 0.94
Commissioning Nina Brooks 50 0 0% $600,000$0$0$600,000 MISSING
Line Boring and Machining Wes Turner 61 0 17% $460,000$189,400$200,800$460,000 0.94
Project Management and Procurement Jordan Pike 2214 0 67% $22,770,000$18,943,540$21,646,000$23,548,500 0.88
Source: activity, cost_account · schedule and cost join on WBS, area and trade · nothing is estimated

Live from the boards updates by itself

  • 16:38 · Survey and Layout · Hannah Price added a field log entry
  • 16:20 · Dale Whitaker updated schedule progress
  • 16:05 · Line Boring and Machining · Wes Turner added a turnover
  • 15:48 · R. Okafor updated a lift plan
  • 15:30 · Rigging and Heavy Lift · R. Okafor added a watch item
  • 15:15 · Millwrights · Dale Whitaker added a field log entry
Source: live_event · every saved change on the project

Trades needing attention

BoardOverdue itemsBlockedNeeds a decision
Millwrights 0 0 None
Rigging and Heavy Lift 0 0 None
Piping 0 0 None
Electrical and Instrumentation 0 0 None
Scaffolding 0 0 None
Insulation 0 0 None
Concrete 0 0 None
Survey and Layout 0 0 None
Welding and QA/QC 0 0 None
Commissioning 0 0 None
Line Boring and Machining 0 0 None
Project Management and Procurement 0 0 None
Source: watch_item (same as the CM roll-up)

Next milestones

2027-01-10 Machine down: last paper off the reel PMGT

2027-02-14 Paper on the reel COMM

2027-03-14 Project turned over PMGT

Source: activity

Schedule delays

0 delays logged.

Client delay report Contractors Delay log

Source: delay, schedule_slip · each delay counted once; overlapping delays are not added into one project delay

Meetings

No meetings recorded.

Source: meeting, meeting_item