XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Lifecycle

Preconstruction to closeout. Tick a gate item when it is done; the name you enter is recorded with the date.

Preconstruction 2026-05-04 → 2026-06-05 5 / 5 gates Engineering and Procurement 2026-06-05 → 2026-12-19 2 / 4 gates Construction 2026-12-19 → 2027-02-09 0 / 5 gates Commissioning and Startup 2027-02-09 → 2027-02-21 0 / 4 gates Turnover and Closeout 2027-02-21 → 2027-03-31 0 / 5 gates

Preconstruction COMPLETE

2026-05-04 → 2026-06-05 · 5 of 5 done

  • Contract and scope of work signedDone 2026-06-13 by Jordan Pike, PM
  • Baseline schedule approvedDone 2026-06-13 by Jordan Pike, PM
  • Budget and cost codes set upDone 2026-06-13 by Jordan Pike, PM
  • Site safety plan approvedDone 2026-06-13 by Jordan Pike, PM
  • Trade contractors awardedDone 2026-06-13 by Jordan Pike, PM
Source: gate_item

Engineering and Procurement CURRENT

2026-06-05 → 2026-12-19 · 2 of 4 done

  • Issued for construction drawings receivedDone 2026-06-13 by Jordan Pike, PM
  • Long-lead equipment orderedDone 2026-06-13 by Jordan Pike, PM
  • Material delivery schedule agreed
  • Inspection and test plans approved
Source: gate_item

Construction UPCOMING

2026-12-19 → 2027-02-09 · 0 of 5 done

  • Mobilization complete
  • Foundations complete
  • Equipment set
  • Piping and E&I installed
  • Mechanical completion walkdown
Source: gate_item

Commissioning and Startup UPCOMING

2027-02-09 → 2027-02-21 · 0 of 4 done

  • Pre-commissioning checks complete
  • Loop checks complete
  • Systems energized
  • Performance tests passed
Source: gate_item

Turnover and Closeout UPCOMING

2027-02-21 → 2027-03-31 · 0 of 5 done

  • Punch list closed
  • Turnover packages accepted
  • As-built drawings delivered
  • Final cost report issued
  • Lessons learned recorded
Source: gate_item