XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Procurement Document control Current revisions Safety center

Procurement ?

Every PO line the job is waiting on, checked against the date the work needs it. Need-by comes from the planned start of the activity that uses the item unless someone enters one. Status is worked out from the dates.

Is this page current? All feeds OK

Procurement register OK 0 min ago · expected every 7 d
Schedule (P6 export) OK 0 min ago · expected every 24 h
Late
0
Source: material_item, activity
At Risk
0
Source: material_item, activity
No Promise
0
Source: material_item, activity
On Track
8
Source: material_item, activity
Delivered
0
Source: material_item, activity

Material register

PO lineItemTradeSupplierNeeded forNeed-byPromisedDeliveredMargin calcStatus
PO-7715-01 Idler bearing bore sleeves IB-1 to IB-5 PMGT Midstate Bearing Supply LB01
Line bore and sleeve idler bearing bore IB-1
2027-01-15
activity planned start
2026-10-26 81 d ON TRACK
Update
PO-7710-01 New press section, complete (OEM) PMGT Demo Press OEM IN010
Set new press frames and sole plates
2027-01-23
activity planned start
2026-12-28 26 d ON TRACK
Update
PO-7711-01 Dryer cans D-01 to D-14 PMGT Lakeshore Dryer Works ID01
Set new dryer D-01 (top tier)
2027-01-23
activity planned start
2026-12-14 40 d ON TRACK
Update
PO-7715-02 Dryer and gear bearings, housings and seals PMGT Midstate Bearing Supply ID01
Set new dryer D-01 (top tier)
2027-01-23
activity planned start
2026-11-02 82 d ON TRACK
Update
PO-7712-01 Bull gears BG-01 to BG-14 PMGT Ridgeline Gear Co IG01
Install bull gear BG-01 and idler gears IG-01, IG-02
2027-01-24
activity planned start
2026-11-30 55 d ON TRACK
Update
PO-7712-02 Idler gears IG-01 to IG-27 PMGT Ridgeline Gear Co IG01
Install bull gear BG-01 and idler gears IG-01, IG-02
2027-01-24
activity planned start
2026-11-23 62 d ON TRACK
Update
PO-7713-01 Felt rolls FR-01 to FR-13, balanced PMGT Crestview Roll Co IF01
Install felt roll FR-01 (top felt)
2027-01-24
activity planned start
2026-11-16 69 d ON TRACK
Update
PO-7714-01 Blow boxes BB-1 to BB-6 PMGT AirFlow Process Equipment IB01
Install blow box BB-1
2027-01-24
activity planned start
2026-11-09 76 d ON TRACK
Update
Source: material_item, activity · margin = need-by minus promised (or delivered) date; negative means it arrives after the work needs it; a passed promise counts from today

Add a material line