Every PO line the job is waiting on, checked against the date the work needs it. Need-by comes from the planned start of the activity that uses the item unless someone enters one. Status is worked out from the dates.
Is this page current? All feeds OK
Procurement register
OK
0 min ago · expected every 7 d
Schedule (P6 export)
OK
0 min ago · expected every 24 h
Late
0
Source: material_item, activity
At Risk
0
Source: material_item, activity
No Promise
0
Source: material_item, activity
On Track
8
Source: material_item, activity
Delivered
0
Source: material_item, activity
Material register
| PO line | Item | Trade | Supplier | Needed for | Need-by | Promised | Delivered | Margin calc | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| PO-7715-01 | Idler bearing bore sleeves IB-1 to IB-5 | PMGT | Midstate Bearing Supply | LB01 Line bore and sleeve idler bearing bore IB-1 |
2027-01-15 activity planned start |
2026-10-26 | 81 d | ON TRACK |
Update |
|
| PO-7710-01 | New press section, complete (OEM) | PMGT | Demo Press OEM | IN010 Set new press frames and sole plates |
2027-01-23 activity planned start |
2026-12-28 | 26 d | ON TRACK |
Update |
|
| PO-7711-01 | Dryer cans D-01 to D-14 | PMGT | Lakeshore Dryer Works | ID01 Set new dryer D-01 (top tier) |
2027-01-23 activity planned start |
2026-12-14 | 40 d | ON TRACK |
Update |
|
| PO-7715-02 | Dryer and gear bearings, housings and seals | PMGT | Midstate Bearing Supply | ID01 Set new dryer D-01 (top tier) |
2027-01-23 activity planned start |
2026-11-02 | 82 d | ON TRACK |
Update |
|
| PO-7712-01 | Bull gears BG-01 to BG-14 | PMGT | Ridgeline Gear Co | IG01 Install bull gear BG-01 and idler gears IG-01, IG-02 |
2027-01-24 activity planned start |
2026-11-30 | 55 d | ON TRACK |
Update |
|
| PO-7712-02 | Idler gears IG-01 to IG-27 | PMGT | Ridgeline Gear Co | IG01 Install bull gear BG-01 and idler gears IG-01, IG-02 |
2027-01-24 activity planned start |
2026-11-23 | 62 d | ON TRACK |
Update |
|
| PO-7713-01 | Felt rolls FR-01 to FR-13, balanced | PMGT | Crestview Roll Co | IF01 Install felt roll FR-01 (top felt) |
2027-01-24 activity planned start |
2026-11-16 | 69 d | ON TRACK |
Update |
|
| PO-7714-01 | Blow boxes BB-1 to BB-6 | PMGT | AirFlow Process Equipment | IB01 Install blow box BB-1 |
2027-01-24 activity planned start |
2026-11-09 | 76 d | ON TRACK |
Update |
Source: material_item, activity · margin = need-by minus promised (or delivered) date; negative means it arrives after the work needs it; a passed promise counts from today