Project Management and Procurement
Trade lead: Jordan Pike, Project Management · Everything saved here shows live on the PM and CM screens.
Owner: Project Management and Procurement Lead · Readers: Construction Manager, Project Manager · Trades: PMGT · Foreman view · Enter on this board
Is this page current? Some feeds are late
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $22,770,000 · approved changes $0 · revised $22,770,000 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
Nothing from meetings for this trade.
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|---|---|---|---|
FB010 Fabricate new press section (OEM) |
A80 | None | 2026-06-20 → 2026-12-02 | 77 |
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
| No prints loaded for this trade yet. | |||||
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
2026-05-04 Purchase order received
2027-01-10 Machine down: last paper off the reel
2027-03-14 Project turned over
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| PMGT-1.1-A90 | 1.1 · A90 | $500,400 | $500,400 | $530,400 | $500,400 |
| PMGT-1.2-A90 | 1.2 · A90 | $472,600 | $472,600 | $501,000 | $472,600 |
| PMGT-10.2-A90 | 10.2 · A90 | $1,000,900 | $0 | $0 | $1,000,900 |
| PMGT-2.1-A90 | 2.1 · A90 | $1,251,100 | $1,251,100 | $1,326,200 | $1,251,100 |
| PMGT-3.1-A80 | 3.1 · A80 | $4,504,000 | $1,734,040 | $3,403,900 | $4,684,200 |
| PMGT-3.2-A80 | 3.2 · A80 | $3,836,700 | $3,836,700 | $4,066,900 | $3,990,200 |
| PMGT-3.3-A80 | 3.3 · A80 | $5,282,400 | $5,282,400 | $5,599,300 | $5,493,700 |
| PMGT-3.4-A80 | 3.4 · A80 | $5,838,500 | $5,838,500 | $6,188,800 | $6,072,000 |
| PMGT-4.1-A90 | 4.1 · A90 | $55,600 | $27,800 | $29,500 | $55,600 |
| PMGT-5.1-A20 | 5.1 · A20 | $27,800 | $0 | $0 | $27,800 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|
Shift turnover
No turnovers.
Field log
No entries.
Safety observations
None recorded.
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.