Survey and Layout
Trade lead: Hannah Price, Benchmark Alignment Survey · Everything saved here shows live on the PM and CM screens.
Owner: Survey Lead · Readers: Construction Manager, Project Manager · Trades: SURV · Foreman view · Enter on this board
Is this page current? Some feeds are late
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $124,900 · approved changes $0 · revised $124,900 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
Nothing from meetings for this trade.
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
| No prints loaded for this trade yet. | |||||
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
No milestones for this trade.
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| SURV-2.1-A20 | 2.1 · A20 | $41,700 | $41,700 | $44,200 | $41,700 |
| SURV-4.3-A20 | 4.3 · A20 | $31,200 | $31,200 | $33,100 | $31,200 |
| SURV-6.1-A20 | 6.1 · A20 | $10,400 | $0 | $0 | $10,400 |
| SURV-7.1-A10 | 7.1 · A10 | $20,800 | $0 | $0 | $20,800 |
| SURV-8.3-A20 | 8.3 · A20 | $20,800 | $0 | $0 | $20,800 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|---|---|---|---|
| 2026-10-21 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-20 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-19 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-18 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-17 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-16 | Benchmark Alignment Survey | not received | MISSING | MISSING |
| 2026-10-15 | Benchmark Alignment Survey | not received | MISSING | MISSING |
Shift turnover
No turnovers.
Field log
No entries.
Safety observations
None recorded.
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.
Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation
Forms and sign-off cards
- Layout check record
- As-built survey