Apex Rigging and Crane
Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors
Missed dates needing your explanation (0)
Nothing outstanding. Every missed date has an explanation on record.
Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads
Explanations on record
None yet.
Source: missed_date, missed_date_doc
Pay applications
No subcontract set up yet.
Source: subcontract, pay_app
Back-charges for errors on this scope
When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.
No back-charges on this scope.
Source: backcharge, backcharge_doc
Delays covering this scope
No delays logged on these activities.
Source: delay
Activities
| Activity | Trade | Planned | Actual finish | % |
|---|---|---|---|---|
EN050 Lift plans: press section, dryers, gears, rolls | RIG | 2026-05-21 → 2026-06-01 | 2026-06-01 | 100 |
PR050 Machine room crane inspection and load test | RIG | 2026-06-02 → 2026-06-03 | 2026-06-03 | 100 |
RM010 Remove Voith press section: rolls and felt run | RIG | 2027-01-12 → 2027-01-14 | 0 | |
RM020 Remove press section frames and sole plates | RIG | 2027-01-15 → 2027-01-16 | 0 | |
IN010 Set new press frames and sole plates | RIG | 2027-01-23 → 2027-01-25 | 0 | |
IN020 Install press rolls, suction roll and felt run | RIG | 2027-01-29 → 2027-02-01 | 0 |
Source: activity
Until sign-in by role is built, anyone with the link can submit here; every submission records the name given and the time.