XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Apex Rigging and Crane ?

Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

None yet.

Source: missed_date, missed_date_doc

Pay applications

No subcontract set up yet.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

No delays logged on these activities.

Source: delay

Activities

ActivityTradePlannedActual finish%
EN050 Lift plans: press section, dryers, gears, rollsRIG 2026-05-21 → 2026-06-012026-06-01 100
PR050 Machine room crane inspection and load testRIG 2026-06-02 → 2026-06-032026-06-03 100
RM010 Remove Voith press section: rolls and felt runRIG 2027-01-12 → 2027-01-14 0
RM020 Remove press section frames and sole platesRIG 2027-01-15 → 2027-01-16 0
IN010 Set new press frames and sole platesRIG 2027-01-23 → 2027-01-25 0
IN020 Install press rolls, suction roll and felt runRIG 2027-01-29 → 2027-02-01 0
Source: activity