XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Delta Electric and Controls ?

Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

None yet.

Source: missed_date, missed_date_doc

Pay applications

No subcontract set up yet.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

No delays logged on these activities.

Source: delay

Activities

ActivityTradePlannedActual finish%
EN070 Drive, controls and instrument designEI 2026-05-11 → 2026-05-302026-05-30 100
PR040 Pull new drive and instrument cables to the MCCEI 2026-05-31 → 2026-06-112026-06-11 100
OT050 Disconnect drives and instrumentsEI 2027-01-11 → 2027-01-11 0
SY040 Reconnect drives and instruments, loop checkEI 2027-01-30 → 2027-02-01 0
Source: activity

Until sign-in by role is built, anyone with the link can submit here; every submission records the name given and the time.