XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Summit Scaffold ?

Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

None yet.

Source: missed_date, missed_date_doc

Pay applications

No subcontract set up yet.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

No delays logged on these activities.

Source: delay

Activities

ActivityTradePlannedActual finish%
PR020 Scaffold design and pre-build of outage scaffoldsSCAF 2026-06-02 → 2026-06-112026-06-11 100
OT030 Erect outage scaffolding, tending and drive sidesSCAF 2027-01-12 → 2027-01-13 0
SY080 Strike outage scaffoldingSCAF 2027-02-07 → 2027-02-08 0
Source: activity