Lift plan RD01-1: D-01 Remove dryer D-01 (top tier) ?

APPROVED Prepared by R. Okafor, Apex Rigging lift planner 2026-09-30 · approved by Jordan Pike, PM 2026-10-07

Item weight
66,389 lb
From the drawing
Source: lift_plan
Gross load calc
72,699 lb
item + 3,810 rigging + 2,500 hook block
Source: lift_plan, rigging_gear, lift_crane
Capacity at radius calc
120,000 lb
Machine room crane (60t)
Source: lift_chart, lift_crane
% of chart calc
60.6%
critical over 75%, not allowed over 90%
Source: lift_plan, lift_chart
Sling load per leg calc
33,194 lb
2 of 2 legs carrying at 90°
Source: lift_plan

Load and rigging

ItemQtyWLL lbWeight lb
D-01 Remove dryer D-01 (top tier)166,389
SH-01 Bolt-type shackle, 35 t270,000190
SL-05 1-1/2 in wire rope sling, 16 ft, choked on journal242,000420
SP-01 Dryer spreader beam, 40 t, 14 ft180,0003,200
Hook block, Machine room crane (60t)12,500
Gross load72,699

Crane, path and people

Crane
Machine room crane (60t) (Overhead bridge crane, rated 120,000 lb, inspected 2026-06-23)
Set-up
n/a
Pick
Dryer D-01 journals, both sides · EL 132
Set
Dryer saddles, tending aisle · EL 100
Exclusion zone
Machine room tending-side aisle barricaded from the dryer to the laydown, basement below closed
Wind limit
n/a
Lift director
M. Alvarez, Apex Rigging lift director
Operator
Demo Mill crane operator
Rigger
K. Brandt, Northfield Millwright rigger
Signal person
S. Whitfield, Apex Rigging signal person
Schedule
RD01 Remove dryer D-01 (top tier), 15-Jan-27 to 15-Jan-27

Checks

PASSCrane capacity72,699 lb gross is 60.6% of 120,000 lb. Limit 90%; over 75% is a critical lift.
PASSSling angle90° from horizontal; under 45° raises sling tension sharply and under 30° is not allowed.
PASSSH-01 shackleWLL 70,000 lb against 33,194 lb per leg (2 legs carrying at 90°)
PASSSL-05 slingWLL 42,000 lb against 33,194 lb per leg (2 legs carrying at 90°)
PASSSP-01 spreader or lifting beamWLL 80,000 lb against 66,389 lb
PASSPeople namedLift director, operator, rigger and signal person named.
PASSExclusion zoneMachine room tending-side aisle barricaded from the dryer to the laydown, basement below closed

A cross-check for the lift team. The crane manufacturer's chart, the rigging ratings and the qualified lift director's sign-off govern the lift.

Lift made

Cancel

Change the plan

Load
Crane
Rigging
People and area