Rigging and lift plans
Every lift by equipment tag: the item weight and where it came from, the rigging by tag, the crane and set-up, and the people running it. The platform adds the rigging and hook block to the item weight, reads the load chart at the planned radius, and checks every sling and shackle against what it will carry. Over 75% of chart, a tandem pick or a load over people makes it a critical lift. These numbers are a cross-check; the crane chart, rigging ratings and the qualified lift director's sign-off govern the lift.
Lift register
| Lift | Item tag | What | Activity and date | Crane and set-up | Item lb | Rigging + block lb | Gross lb | % of chart | Sling load / leg | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| RM010-1 | PR-SPU | Remove suction pick-up roll to the laydown From the drawing |
RM010 12-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 74 ft radius |
38,400 | 11,050 | 49,450 | 19,200 2 legs at 90° |
APPROVED | |
| RM010-2 | PR-1T | Remove 1st press top roll to the laydown From the drawing |
RM010 12-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 80 ft radius |
52,600 | 11,050 | 63,650 | 26,300 2 legs at 90° |
APPROVED | |
| RM010-3 | PR-SP | Remove suction press roll to the laydown From the drawing |
RM010 12-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 92 ft radius |
61,200 | 11,050 | 72,250 | 30,600 2 legs at 90° |
APPROVED CRITICAL LIFT | |
| RM010-4 | PR-2T | Remove 2nd press top roll to the laydown From the drawing |
RM010 12-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 82 ft radius |
47,900 | 11,050 | 58,950 | 23,950 2 legs at 90° |
APPROVED | |
| RM010-5 | PR-2B | Remove 2nd press bottom roll to the laydown From the drawing |
RM010 12-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 86 ft radius |
44,300 | 11,050 | 55,350 | 22,150 2 legs at 90° |
APPROVED | |
| RG01-1 | BG-01 | Remove bull gear BG-01 From the drawing |
RG01 13-Jan-27 | Gear case hoist (10t) | 6,897 | 360 | 7,257 | 3,982 2 legs at 60° |
APPROVED | |
| RG01-2 | IG-01 | Remove idler gear IG-01 From the drawing |
RG01 13-Jan-27 | Gear case hoist (10t) | 1,531 | 360 | 1,891 | 884 2 legs at 60° |
APPROVED | |
| RG01-3 | IG-02 | Remove idler gear IG-02 From the drawing |
RG01 13-Jan-27 | Gear case hoist (10t) | 1,662 | 360 | 2,022 | 960 2 legs at 60° |
APPROVED | |
| RG02-1 | BG-02 | Remove bull gear BG-02 From the drawing |
RG02 13-Jan-27 | Gear case hoist (10t) | 6,994 | 360 | 7,354 | 4,038 2 legs at 60° |
APPROVED | |
| RG02-2 | IG-03 | Remove idler gear IG-03 From the drawing |
RG02 13-Jan-27 | Gear case hoist (10t) | 1,793 | 360 | 2,153 | 1,035 2 legs at 60° |
APPROVED | |
| RG02-3 | IG-04 | Remove idler gear IG-04 From the drawing |
RG02 13-Jan-27 | Gear case hoist (10t) | 1,924 | 360 | 2,284 | 1,111 2 legs at 60° |
APPROVED | |
| RB01-1 | BB-1 | Remove blow box BB-1 From the drawing |
RB01 14-Jan-27 CP | Machine room crane (60t) | 2,740 | 2,522 | 5,262 | 1,582 2 legs at 60° |
APPROVED | |
| RB02-1 | BB-2 | Remove blow box BB-2 From the drawing |
RB02 14-Jan-27 | Machine room crane (60t) | 2,880 | 2,522 | 5,402 | 1,663 2 legs at 60° |
APPROVED | |
| RB03-1 | BB-3 | Remove blow box BB-3 From the drawing |
RB03 14-Jan-27 | Machine room crane (60t) | 3,020 | 2,522 | 5,542 | 1,744 2 legs at 60° |
APPROVED | |
| RB04-1 | BB-4 | Remove blow box BB-4 From the drawing |
RB04 14-Jan-27 | Machine room crane (60t) | 3,160 | 2,522 | 5,682 | 1,824 2 legs at 60° |
APPROVED | |
| RB05-1 | BB-5 | Remove blow box BB-5 From the drawing |
RB05 14-Jan-27 | Machine room crane (60t) | 3,300 | 2,522 | 5,822 | 1,905 2 legs at 60° |
APPROVED | |
| RB06-1 | BB-6 | Remove blow box BB-6 From the drawing |
RB06 14-Jan-27 | Machine room crane (60t) | 3,440 | 2,522 | 5,962 | 1,986 2 legs at 60° |
APPROVED | |
| RF01-1 | FR-01 | Remove felt roll FR-01 (top felt) From the drawing |
RF01 14-Jan-27 CP | Machine room crane (60t) | 10,173 | 3,668 | 13,841 | 5,873 2 legs at 60° |
APPROVED | |
| RF02-1 | FR-02 | Remove felt roll FR-02 (top felt) From the drawing |
RF02 14-Jan-27 CP | Machine room crane (60t) | 10,546 | 3,668 | 14,214 | 6,089 2 legs at 60° |
APPROVED | |
| RF03-1 | FR-03 | Remove felt roll FR-03 (top felt) From the drawing |
RF03 14-Jan-27 | Machine room crane (60t) | 10,919 | 3,668 | 14,587 | 6,304 2 legs at 60° |
APPROVED | |
| RF04-1 | FR-04 | Remove felt roll FR-04 (top felt) From the drawing |
RF04 14-Jan-27 | Machine room crane (60t) | 11,292 | 3,668 | 14,960 | 6,519 2 legs at 60° |
APPROVED | |
| RF05-1 | FR-05 | Remove felt roll FR-05 (top felt) From the drawing |
RF05 14-Jan-27 | Machine room crane (60t) | 11,665 | 3,668 | 15,333 | 6,735 2 legs at 60° |
APPROVED | |
| RF06-1 | FR-06 | Remove felt roll FR-06 (top felt) From the drawing |
RF06 14-Jan-27 | Machine room crane (60t) | 12,038 | 3,668 | 15,706 | 6,950 2 legs at 60° |
APPROVED | |
| RF07-1 | FR-07 | Remove felt roll FR-07 (top felt) From the drawing |
RF07 14-Jan-27 | Machine room crane (60t) | 12,411 | 3,668 | 16,079 | 13,218 2 legs at 28° |
DRAFT 1 FAIL | |
| RF08-1 | FR-08 | Remove felt roll FR-08 (bottom felt) From the drawing |
RF08 14-Jan-27 | Machine room crane (60t) | 12,784 | 3,668 | 16,452 | 7,381 2 legs at 60° |
APPROVED | |
| RF09-1 | FR-09 | Remove felt roll FR-09 (bottom felt) From the drawing |
RF09 14-Jan-27 | Machine room crane (60t) | 13,157 | 3,668 | 16,825 | 7,596 2 legs at 60° |
APPROVED | |
| RF10-1 | FR-10 | Remove felt roll FR-10 (bottom felt) From the drawing |
RF10 14-Jan-27 | Machine room crane (60t) | 13,530 | 3,668 | 17,198 | 7,812 2 legs at 60° |
APPROVED | |
| RF11-1 | FR-11 | Remove felt roll FR-11 (bottom felt) From the drawing |
RF11 14-Jan-27 | Machine room crane (60t) | 13,903 | 3,668 | 17,571 | 8,027 2 legs at 60° |
APPROVED | |
| RF12-1 | FR-12 | Remove felt roll FR-12 (bottom felt) From the drawing |
RF12 14-Jan-27 | Machine room crane (60t) | 14,276 | 3,668 | 17,944 | 8,242 2 legs at 60° |
APPROVED | |
| RF13-1 | FR-13 | Remove felt roll FR-13 (bottom felt) From the drawing |
RF13 14-Jan-27 | Machine room crane (60t) | 9,849 | 3,668 | 13,517 | 5,686 2 legs at 60° |
APPROVED | |
| RG03-1 | BG-03 | Remove bull gear BG-03 From the drawing |
RG03 14-Jan-27 | Gear case hoist (10t) | 7,091 | 360 | 7,451 | 4,094 2 legs at 60° |
APPROVED | |
| RG03-2 | IG-05 | Remove idler gear IG-05 From the drawing |
RG03 14-Jan-27 | Gear case hoist (10t) | 2,055 | 360 | 2,415 | 1,186 2 legs at 60° |
APPROVED | |
| RG03-3 | IG-06 | Remove idler gear IG-06 From the drawing |
RG03 14-Jan-27 | Gear case hoist (10t) | 2,186 | 360 | 2,546 | 1,262 2 legs at 60° |
APPROVED | |
| RG04-1 | BG-04 | Remove bull gear BG-04 From the drawing |
RG04 14-Jan-27 | Gear case hoist (10t) | 7,188 | 360 | 7,548 | 4,150 2 legs at 60° |
APPROVED | |
| RG04-2 | IG-07 | Remove idler gear IG-07 From the drawing |
RG04 14-Jan-27 | Gear case hoist (10t) | 2,317 | 360 | 2,677 | 1,338 2 legs at 60° |
APPROVED | |
| RG04-3 | IG-08 | Remove idler gear IG-08 From the drawing |
RG04 14-Jan-27 | Gear case hoist (10t) | 2,448 | 360 | 2,808 | 1,413 2 legs at 60° |
APPROVED | |
| RD01-1 | D-01 | Remove dryer D-01 (top tier) From the drawing |
RD01 15-Jan-27 CP | Machine room crane (60t) | 66,389 | 6,310 | 72,699 | 33,194 2 legs at 90° |
APPROVED | |
| RD02-1 | D-02 | Remove dryer D-02 (bottom tier) From the drawing |
RD02 15-Jan-27 CP | Machine room crane (60t) | 66,778 | 6,310 | 73,088 | 33,389 2 legs at 90° |
APPROVED | |
| RG05-1 | BG-05 | Remove bull gear BG-05 From the drawing |
RG05 15-Jan-27 | Gear case hoist (10t) | 7,285 | 360 | 7,645 | 4,206 2 legs at 60° |
APPROVED | |
| RG05-2 | IG-09 | Remove idler gear IG-09 From the drawing |
RG05 15-Jan-27 | Gear case hoist (10t) | 2,579 | 360 | 2,939 | 1,489 2 legs at 60° |
APPROVED | |
| RG05-3 | IG-10 | Remove idler gear IG-10 From the drawing |
RG05 15-Jan-27 | Gear case hoist (10t) | 2,710 | 360 | 3,070 | 1,565 2 legs at 60° |
APPROVED | |
| RG06-1 | BG-06 | Remove bull gear BG-06 From the drawing |
RG06 15-Jan-27 | Gear case hoist (10t) | 7,382 | 360 | 7,742 | 4,262 2 legs at 60° |
APPROVED | |
| RG06-2 | IG-11 | Remove idler gear IG-11 From the drawing |
RG06 15-Jan-27 | Gear case hoist (10t) | 2,841 | 360 | 3,201 | 1,640 2 legs at 60° |
APPROVED | |
| RG06-3 | IG-12 | Remove idler gear IG-12 From the drawing |
RG06 15-Jan-27 | Gear case hoist (10t) | 1,472 | 360 | 1,832 | 850 2 legs at 60° |
APPROVED | |
| RM020-1 | PF-TS | Remove tending-side press frame From the drawing |
RM020 15-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 78 ft radius |
28,700 | 5,300 | 34,000 | 16,570 2 legs at 60° |
APPROVED | |
| RM020-2 | PF-DS | Remove drive-side press frame From the drawing |
RM020 15-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 84 ft radius |
31,400 | 5,300 | 36,700 | 18,129 2 legs at 60° |
APPROVED | |
| RD03-1 | D-03 | Remove dryer D-03 (top tier) From the drawing |
RD03 16-Jan-27 CP | Machine room crane (60t) | 67,167 | 6,310 | 73,477 | 33,584 2 legs at 90° |
APPROVED | |
| RD04-1 | D-04 | Remove dryer D-04 (bottom tier) From the drawing |
RD04 16-Jan-27 CP | Machine room crane (60t) | 67,556 | 6,310 | 73,866 | 33,778 2 legs at 90° |
APPROVED | |
| RG07-1 | BG-07 | Remove bull gear BG-07 From the drawing |
RG07 16-Jan-27 | Gear case hoist (10t) | 7,479 | 360 | 7,839 | 4,318 2 legs at 60° |
APPROVED | |
| RG07-2 | IG-13 | Remove idler gear IG-13 From the drawing |
RG07 16-Jan-27 | Gear case hoist (10t) | 1,603 | 360 | 1,963 | 925 2 legs at 60° |
APPROVED | |
| RG07-3 | IG-14 | Remove idler gear IG-14 From the drawing |
RG07 16-Jan-27 | Gear case hoist (10t) | 1,734 | 360 | 2,094 | 1,001 2 legs at 60° |
APPROVED | |
| RG08-1 | BG-08 | Remove bull gear BG-08 From the drawing |
RG08 16-Jan-27 | Gear case hoist (10t) | 7,576 | 360 | 7,936 | 4,374 2 legs at 60° |
APPROVED | |
| RG08-2 | IG-15 | Remove idler gear IG-15 From the drawing |
RG08 16-Jan-27 | Gear case hoist (10t) | 1,865 | 360 | 2,225 | 1,077 2 legs at 60° |
APPROVED | |
| RG08-3 | IG-16 | Remove idler gear IG-16 From the drawing |
RG08 16-Jan-27 | Gear case hoist (10t) | 1,996 | 360 | 2,356 | 1,152 2 legs at 60° |
APPROVED | |
| RD05-1 | D-05 | Remove dryer D-05 (top tier) From the drawing |
RD05 17-Jan-27 CP | Machine room crane (60t) | 67,945 | 6,310 | 74,255 | 33,972 2 legs at 90° |
APPROVED | |
| RD06-1 | D-06 | Remove dryer D-06 (bottom tier) From the drawing |
RD06 17-Jan-27 CP | Machine room crane (60t) | 68,334 | 6,310 | 74,644 | 34,167 2 legs at 90° |
APPROVED | |
| RG09-1 | BG-09 | Remove bull gear BG-09 From the drawing |
RG09 17-Jan-27 | Gear case hoist (10t) | 7,673 | 360 | 8,033 | 4,430 2 legs at 60° |
APPROVED | |
| RG09-2 | IG-17 | Remove idler gear IG-17 From the drawing |
RG09 17-Jan-27 | Gear case hoist (10t) | 2,127 | 360 | 2,487 | 1,228 2 legs at 60° |
APPROVED | |
| RG09-3 | IG-18 | Remove idler gear IG-18 From the drawing |
RG09 17-Jan-27 | Gear case hoist (10t) | 2,258 | 360 | 2,618 | 1,304 2 legs at 60° |
APPROVED | |
| RG10-1 | BG-10 | Remove bull gear BG-10 From the drawing |
RG10 17-Jan-27 | Gear case hoist (10t) | 7,770 | 360 | 8,130 | 4,486 2 legs at 60° |
APPROVED | |
| RG10-2 | IG-19 | Remove idler gear IG-19 From the drawing |
RG10 17-Jan-27 | Gear case hoist (10t) | 2,389 | 360 | 2,749 | 1,379 2 legs at 60° |
APPROVED | |
| RG10-3 | IG-20 | Remove idler gear IG-20 From the drawing |
RG10 17-Jan-27 | Gear case hoist (10t) | 2,520 | 360 | 2,880 | 1,455 2 legs at 60° |
APPROVED | |
| RD07-1 | D-07 | Remove dryer D-07 (top tier) From the drawing |
RD07 18-Jan-27 CP | Machine room crane (60t) | 68,723 | 6,310 | 75,033 | 34,362 2 legs at 90° |
APPROVED | |
| RD08-1 | D-08 | Remove dryer D-08 (bottom tier) From the drawing |
RD08 18-Jan-27 CP | Machine room crane (60t) | 69,112 | 6,310 | 75,422 | 34,556 2 legs at 90° |
APPROVED | |
| RG11-1 | BG-11 | Remove bull gear BG-11 From the drawing |
RG11 18-Jan-27 | Gear case hoist (10t) | 7,867 | 360 | 8,227 | 4,542 2 legs at 60° |
APPROVED | |
| RG11-2 | IG-21 | Remove idler gear IG-21 From the drawing |
RG11 18-Jan-27 | Gear case hoist (10t) | 2,651 | 360 | 3,011 | 1,531 2 legs at 60° |
APPROVED | |
| RG11-3 | IG-22 | Remove idler gear IG-22 From the drawing |
RG11 18-Jan-27 | Gear case hoist (10t) | 2,782 | 360 | 3,142 | 1,606 2 legs at 60° |
APPROVED | |
| RG12-1 | BG-12 | Remove bull gear BG-12 From the drawing |
RG12 18-Jan-27 | Gear case hoist (10t) | 7,964 | 360 | 8,324 | 4,598 2 legs at 60° |
APPROVED | |
| RG12-2 | IG-23 | Remove idler gear IG-23 From the drawing |
RG12 18-Jan-27 | Gear case hoist (10t) | 1,413 | 360 | 1,773 | 816 2 legs at 60° |
APPROVED | |
| RG12-3 | IG-24 | Remove idler gear IG-24 From the drawing |
RG12 18-Jan-27 | Gear case hoist (10t) | 1,544 | 360 | 1,904 | 891 2 legs at 60° |
APPROVED | |
| RD09-1 | D-09 | Remove dryer D-09 (top tier) From the drawing |
RD09 19-Jan-27 CP | Machine room crane (60t) | 69,501 | 6,310 | 75,811 | 34,750 2 legs at 90° |
APPROVED | |
| RD10-1 | D-10 | Remove dryer D-10 (bottom tier) From the drawing |
RD10 19-Jan-27 CP | Machine room crane (60t) | 69,890 | 6,310 | 76,200 | 34,945 2 legs at 90° |
APPROVED | |
| RG13-1 | BG-13 | Remove bull gear BG-13 From the drawing |
RG13 19-Jan-27 | Gear case hoist (10t) | 8,061 | 360 | 8,421 | 4,654 2 legs at 60° |
APPROVED | |
| RG13-2 | IG-25 | Remove idler gear IG-25 From the drawing |
RG13 19-Jan-27 | Gear case hoist (10t) | 1,675 | 360 | 2,035 | 967 2 legs at 60° |
APPROVED | |
| RG13-3 | IG-26 | Remove idler gear IG-26 From the drawing |
RG13 19-Jan-27 | Gear case hoist (10t) | 1,806 | 360 | 2,166 | 1,043 2 legs at 60° |
APPROVED | |
| RG14-1 | BG-14 | Remove bull gear BG-14 From the drawing |
RG14 19-Jan-27 | Gear case hoist (10t) | 8,158 | 360 | 8,518 | 4,710 2 legs at 60° |
APPROVED | |
| RG14-2 | IG-27 | Remove idler gear IG-27 From the drawing |
RG14 19-Jan-27 | Gear case hoist (10t) | 1,937 | 360 | 2,297 | 1,118 2 legs at 60° |
APPROVED | |
| RD11-1 | D-11 | Remove dryer D-11 (top tier) From the drawing |
RD11 20-Jan-27 CP | Machine room crane (60t) | 70,279 | 6,310 | 76,589 | 35,140 2 legs at 90° |
APPROVED | |
| RD12-1 | D-12 | Remove dryer D-12 (bottom tier) From the drawing |
RD12 20-Jan-27 CP | Machine room crane (60t) | 70,668 | 6,310 | 76,978 | 35,334 2 legs at 90° |
APPROVED | |
| RD13-1 | D-13 | Remove dryer D-13 (top tier) From the drawing |
RD13 21-Jan-27 CP | Machine room crane (60t) | 71,057 | 6,310 | 77,367 | 35,528 2 legs at 90° |
APPROVED | |
| RD14-1 | D-14 | Remove dryer D-14 (bottom tier) From the drawing |
RD14 21-Jan-27 CP | Machine room crane (60t) | 71,446 | 6,310 | 77,756 | 35,723 2 legs at 90° |
APPROVED | |
| ID01-1 | D-01N | Set new dryer D-01 (top tier) Certified (scale or OEM certificate) |
ID01 23-Jan-27 CP | Machine room crane (60t) | 67,089 | 6,310 | 73,399 | 33,544 2 legs at 90° |
APPROVED | |
| ID02-1 | D-02N | Set new dryer D-02 (bottom tier) Certified (scale or OEM certificate) |
ID02 23-Jan-27 CP | Machine room crane (60t) | 67,478 | 6,310 | 73,788 | 33,739 2 legs at 90° |
APPROVED | |
| IN010-1 | NPF-TS | Set new tending-side press frame Estimated (+10% planned) |
IN010 23-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 78 ft radius |
30,500 | 5,300 | 38,850 | 19,370 2 legs at 60° |
DRAFT | |
| IN010-2 | NPF-DS | Set new drive-side press frame Estimated (+10% planned) |
IN010 23-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 84 ft radius |
33,800 | 5,300 | 42,480 | 21,466 2 legs at 60° |
DRAFT | |
| IB01-1 | BB-1N | Install new blow box BB-1 Certified (scale or OEM certificate) |
IB01 24-Jan-27 | Machine room crane (60t) | 2,840 | 2,522 | 5,362 | 1,640 2 legs at 60° |
DRAFT | |
| ID03-1 | D-03N | Set new dryer D-03 (top tier) Certified (scale or OEM certificate) |
ID03 24-Jan-27 CP | Machine room crane (60t) | 67,867 | 6,310 | 74,177 | 33,934 2 legs at 90° |
APPROVED | |
| ID04-1 | D-04N | Set new dryer D-04 (bottom tier) Certified (scale or OEM certificate) |
ID04 24-Jan-27 CP | Machine room crane (60t) | 68,256 | 6,310 | 74,566 | 34,128 2 legs at 90° |
APPROVED | |
| IF01-1 | FR-01N | Install new felt roll FR-01 Certified (scale or OEM certificate) |
IF01 24-Jan-27 | Machine room crane (60t) | 10,393 | 3,668 | 14,061 | 6,000 2 legs at 60° |
DRAFT | |
| IG01-1 | BG-01N | Install new bull gear BG-01 Certified (scale or OEM certificate) |
IG01 24-Jan-27 | Gear case hoist (10t) | 7,047 | 360 | 7,407 | 4,069 2 legs at 60° |
DRAFT | |
| IG01-2 | IG-01N | Install new idler gear IG-01 Certified (scale or OEM certificate) |
IG01 24-Jan-27 | Gear case hoist (10t) | 1,591 | 360 | 1,951 | 919 2 legs at 60° |
DRAFT | |
| IG01-3 | IG-02N | Install new idler gear IG-02 Certified (scale or OEM certificate) |
IG01 24-Jan-27 | Gear case hoist (10t) | 1,722 | 360 | 2,082 | 994 2 legs at 60° |
DRAFT | |
| IG02-1 | BG-02N | Install new bull gear BG-02 Certified (scale or OEM certificate) |
IG02 24-Jan-27 | Gear case hoist (10t) | 7,144 | 360 | 7,504 | 4,125 2 legs at 60° |
DRAFT | |
| IG02-2 | IG-03N | Install new idler gear IG-03 Certified (scale or OEM certificate) |
IG02 24-Jan-27 | Gear case hoist (10t) | 1,853 | 360 | 2,213 | 1,070 2 legs at 60° |
DRAFT | |
| IG02-3 | IG-04N | Install new idler gear IG-04 Certified (scale or OEM certificate) |
IG02 24-Jan-27 | Gear case hoist (10t) | 1,984 | 360 | 2,344 | 1,145 2 legs at 60° |
DRAFT | |
| IB02-1 | BB-2N | Install new blow box BB-2 Certified (scale or OEM certificate) |
IB02 25-Jan-27 | Machine room crane (60t) | 2,980 | 2,522 | 5,502 | 1,721 2 legs at 60° |
DRAFT | |
| ID05-1 | D-05N | Set new dryer D-05 (top tier) Certified (scale or OEM certificate) |
ID05 25-Jan-27 CP | Machine room crane (60t) | 68,645 | 6,310 | 74,955 | 34,322 2 legs at 90° |
DRAFT | |
| ID06-1 | D-06N | Set new dryer D-06 (bottom tier) Certified (scale or OEM certificate) |
ID06 25-Jan-27 CP | Machine room crane (60t) | 69,034 | 6,310 | 75,344 | 34,517 2 legs at 90° |
DRAFT | |
| IF02-1 | FR-02N | Install new felt roll FR-02 Certified (scale or OEM certificate) |
IF02 25-Jan-27 | Machine room crane (60t) | 10,766 | 3,668 | 14,434 | 6,216 2 legs at 60° |
DRAFT | |
| IG03-1 | BG-03N | Install new bull gear BG-03 Certified (scale or OEM certificate) |
IG03 25-Jan-27 | Gear case hoist (10t) | 7,241 | 360 | 7,601 | 4,181 2 legs at 60° |
DRAFT | |
| IG03-2 | IG-05N | Install new idler gear IG-05 Certified (scale or OEM certificate) |
IG03 25-Jan-27 | Gear case hoist (10t) | 2,115 | 360 | 2,475 | 1,221 2 legs at 60° |
DRAFT | |
| IG03-3 | IG-06N | Install new idler gear IG-06 Certified (scale or OEM certificate) |
IG03 25-Jan-27 | Gear case hoist (10t) | 2,246 | 360 | 2,606 | 1,297 2 legs at 60° |
DRAFT | |
| IG04-1 | BG-04N | Install new bull gear BG-04 Certified (scale or OEM certificate) |
IG04 25-Jan-27 | Gear case hoist (10t) | 7,338 | 360 | 7,698 | 4,237 2 legs at 60° |
DRAFT | |
| IG04-2 | IG-07N | Install new idler gear IG-07 Certified (scale or OEM certificate) |
IG04 25-Jan-27 | Gear case hoist (10t) | 2,377 | 360 | 2,737 | 1,372 2 legs at 60° |
DRAFT | |
| IG04-3 | IG-08N | Install new idler gear IG-08 Certified (scale or OEM certificate) |
IG04 25-Jan-27 | Gear case hoist (10t) | 2,508 | 360 | 2,868 | 1,448 2 legs at 60° |
DRAFT | |
| IB03-1 | BB-3N | Install new blow box BB-3 Certified (scale or OEM certificate) |
IB03 26-Jan-27 | Machine room crane (60t) | 3,120 | 2,522 | 5,642 | 1,801 2 legs at 60° |
DRAFT | |
| ID07-1 | D-07N | Set new dryer D-07 (top tier) Certified (scale or OEM certificate) |
ID07 26-Jan-27 CP | Machine room crane (60t) | 69,423 | 6,310 | 75,733 | 34,712 2 legs at 90° |
DRAFT | |
| ID08-1 | D-08N | Set new dryer D-08 (bottom tier) Certified (scale or OEM certificate) |
ID08 26-Jan-27 CP | Machine room crane (60t) | 69,812 | 6,310 | 76,122 | 34,906 2 legs at 90° |
DRAFT | |
| IF03-1 | FR-03N | Install new felt roll FR-03 Certified (scale or OEM certificate) |
IF03 26-Jan-27 | Machine room crane (60t) | 11,139 | 3,668 | 14,807 | 6,431 2 legs at 60° |
DRAFT | |
| IG05-1 | BG-05N | Install new bull gear BG-05 Certified (scale or OEM certificate) |
IG05 26-Jan-27 | Gear case hoist (10t) | 7,435 | 360 | 7,795 | 4,293 2 legs at 60° |
DRAFT | |
| IG05-2 | IG-09N | Install new idler gear IG-09 Certified (scale or OEM certificate) |
IG05 26-Jan-27 | Gear case hoist (10t) | 2,639 | 360 | 2,999 | 1,524 2 legs at 60° |
DRAFT | |
| IG05-3 | IG-10N | Install new idler gear IG-10 Certified (scale or OEM certificate) |
IG05 26-Jan-27 | Gear case hoist (10t) | 2,770 | 360 | 3,130 | 1,599 2 legs at 60° |
DRAFT | |
| IG06-1 | BG-06N | Install new bull gear BG-06 Certified (scale or OEM certificate) |
IG06 26-Jan-27 | Gear case hoist (10t) | 7,532 | 360 | 7,892 | 4,349 2 legs at 60° |
DRAFT | |
| IG06-2 | IG-11N | Install new idler gear IG-11 Certified (scale or OEM certificate) |
IG06 26-Jan-27 | Gear case hoist (10t) | 2,901 | 360 | 3,261 | 1,675 2 legs at 60° |
DRAFT | |
| IG06-3 | IG-12N | Install new idler gear IG-12 Certified (scale or OEM certificate) |
IG06 26-Jan-27 | Gear case hoist (10t) | 1,532 | 360 | 1,892 | 885 2 legs at 60° |
DRAFT | |
| IB04-1 | BB-4N | Install new blow box BB-4 Certified (scale or OEM certificate) |
IB04 27-Jan-27 | Machine room crane (60t) | 3,260 | 2,522 | 5,782 | 1,882 2 legs at 60° |
DRAFT | |
| ID09-1 | D-09N | Set new dryer D-09 (top tier) Certified (scale or OEM certificate) |
ID09 27-Jan-27 CP | Machine room crane (60t) | 70,201 | 6,310 | 76,511 | 35,100 2 legs at 90° |
DRAFT | |
| ID10-1 | D-10N | Set new dryer D-10 (bottom tier) Certified (scale or OEM certificate) |
ID10 27-Jan-27 CP | Machine room crane (60t) | 70,590 | 6,310 | 76,900 | 35,295 2 legs at 90° |
DRAFT | |
| IF04-1 | FR-04N | Install new felt roll FR-04 Certified (scale or OEM certificate) |
IF04 27-Jan-27 | Machine room crane (60t) | 11,512 | 3,668 | 15,180 | 6,646 2 legs at 60° |
DRAFT | |
| IG07-1 | BG-07N | Install new bull gear BG-07 Certified (scale or OEM certificate) |
IG07 27-Jan-27 | Gear case hoist (10t) | 7,629 | 360 | 7,989 | 4,405 2 legs at 60° |
DRAFT | |
| IG07-2 | IG-13N | Install new idler gear IG-13 Certified (scale or OEM certificate) |
IG07 27-Jan-27 | Gear case hoist (10t) | 1,663 | 360 | 2,023 | 960 2 legs at 60° |
DRAFT | |
| IG07-3 | IG-14N | Install new idler gear IG-14 Certified (scale or OEM certificate) |
IG07 27-Jan-27 | Gear case hoist (10t) | 1,794 | 360 | 2,154 | 1,036 2 legs at 60° |
DRAFT | |
| IG08-1 | BG-08N | Install new bull gear BG-08 Certified (scale or OEM certificate) |
IG08 27-Jan-27 | Gear case hoist (10t) | 7,726 | 360 | 8,086 | 4,461 2 legs at 60° |
DRAFT | |
| IG08-2 | IG-15N | Install new idler gear IG-15 Certified (scale or OEM certificate) |
IG08 27-Jan-27 | Gear case hoist (10t) | 1,925 | 360 | 2,285 | 1,111 2 legs at 60° |
DRAFT | |
| IG08-3 | IG-16N | Install new idler gear IG-16 Certified (scale or OEM certificate) |
IG08 27-Jan-27 | Gear case hoist (10t) | 2,056 | 360 | 2,416 | 1,187 2 legs at 60° |
DRAFT | |
| IB05-1 | BB-5N | Install new blow box BB-5 Certified (scale or OEM certificate) |
IB05 28-Jan-27 | Machine room crane (60t) | 3,400 | 2,522 | 5,922 | 1,963 2 legs at 60° |
DRAFT | |
| ID11-1 | D-11N | Set new dryer D-11 (top tier) Certified (scale or OEM certificate) |
ID11 28-Jan-27 CP | Machine room crane (60t) | 70,979 | 6,310 | 77,289 | 35,490 2 legs at 90° |
DRAFT | |
| ID12-1 | D-12N | Set new dryer D-12 (bottom tier) Certified (scale or OEM certificate) |
ID12 28-Jan-27 CP | Machine room crane (60t) | 71,368 | 6,310 | 77,678 | 35,684 2 legs at 90° |
DRAFT | |
| IF05-1 | FR-05N | Install new felt roll FR-05 Certified (scale or OEM certificate) |
IF05 28-Jan-27 | Machine room crane (60t) | 11,885 | 3,668 | 15,553 | 6,862 2 legs at 60° |
DRAFT | |
| IF08-1 | FR-08N | Install new felt roll FR-08 Certified (scale or OEM certificate) |
IF08 28-Jan-27 | Machine room crane (60t) | 13,004 | 3,668 | 16,672 | 7,508 2 legs at 60° |
DRAFT | |
| IG09-1 | BG-09N | Install new bull gear BG-09 Certified (scale or OEM certificate) |
IG09 28-Jan-27 | Gear case hoist (10t) | 7,823 | 360 | 8,183 | 4,517 2 legs at 60° |
DRAFT | |
| IG09-2 | IG-17N | Install new idler gear IG-17 Certified (scale or OEM certificate) |
IG09 28-Jan-27 | Gear case hoist (10t) | 2,187 | 360 | 2,547 | 1,263 2 legs at 60° |
DRAFT | |
| IG09-3 | IG-18N | Install new idler gear IG-18 Certified (scale or OEM certificate) |
IG09 28-Jan-27 | Gear case hoist (10t) | 2,318 | 360 | 2,678 | 1,338 2 legs at 60° |
DRAFT | |
| IG10-1 | BG-10N | Install new bull gear BG-10 Certified (scale or OEM certificate) |
IG10 28-Jan-27 | Gear case hoist (10t) | 7,920 | 360 | 8,280 | 4,573 2 legs at 60° |
DRAFT | |
| IG10-2 | IG-19N | Install new idler gear IG-19 Certified (scale or OEM certificate) |
IG10 28-Jan-27 | Gear case hoist (10t) | 2,449 | 360 | 2,809 | 1,414 2 legs at 60° |
DRAFT | |
| IG10-3 | IG-20N | Install new idler gear IG-20 Certified (scale or OEM certificate) |
IG10 28-Jan-27 | Gear case hoist (10t) | 2,580 | 360 | 2,940 | 1,490 2 legs at 60° |
DRAFT | |
| IB06-1 | BB-6N | Install new blow box BB-6 Certified (scale or OEM certificate) |
IB06 29-Jan-27 | Machine room crane (60t) | 3,540 | 2,522 | 6,062 | 2,044 2 legs at 60° |
DRAFT | |
| ID13-1 | D-13N | Set new dryer D-13 (top tier) Certified (scale or OEM certificate) |
ID13 29-Jan-27 CP | Machine room crane (60t) | 71,757 | 6,310 | 78,067 | 35,878 2 legs at 90° |
DRAFT | |
| ID14-1 | D-14N | Set new dryer D-14 (bottom tier) Certified (scale or OEM certificate) |
ID14 29-Jan-27 CP | Machine room crane (60t) | 72,146 | 6,310 | 78,456 | 36,073 2 legs at 90° |
DRAFT | |
| IF06-1 | FR-06N | Install new felt roll FR-06 Certified (scale or OEM certificate) |
IF06 29-Jan-27 | Machine room crane (60t) | 12,258 | 3,668 | 15,926 | 7,077 2 legs at 60° |
DRAFT | |
| IF09-1 | FR-09N | Install new felt roll FR-09 Certified (scale or OEM certificate) |
IF09 29-Jan-27 | Machine room crane (60t) | 13,377 | 3,668 | 17,045 | 7,723 2 legs at 60° |
DRAFT | |
| IG11-1 | BG-11N | Install new bull gear BG-11 Certified (scale or OEM certificate) |
IG11 29-Jan-27 | Gear case hoist (10t) | 8,017 | 360 | 8,377 | 4,629 2 legs at 60° |
DRAFT | |
| IG11-2 | IG-21N | Install new idler gear IG-21 Certified (scale or OEM certificate) |
IG11 29-Jan-27 | Gear case hoist (10t) | 2,711 | 360 | 3,071 | 1,565 2 legs at 60° |
DRAFT | |
| IG11-3 | IG-22N | Install new idler gear IG-22 Certified (scale or OEM certificate) |
IG11 29-Jan-27 | Gear case hoist (10t) | 2,842 | 360 | 3,202 | 1,641 2 legs at 60° |
DRAFT | |
| IG12-1 | BG-12N | Install new bull gear BG-12 Certified (scale or OEM certificate) |
IG12 29-Jan-27 | Gear case hoist (10t) | 8,114 | 360 | 8,474 | 4,685 2 legs at 60° |
DRAFT | |
| IG12-2 | IG-23N | Install new idler gear IG-23 Certified (scale or OEM certificate) |
IG12 29-Jan-27 | Gear case hoist (10t) | 1,473 | 360 | 1,833 | 850 2 legs at 60° |
DRAFT | |
| IG12-3 | IG-24N | Install new idler gear IG-24 Certified (scale or OEM certificate) |
IG12 29-Jan-27 | Gear case hoist (10t) | 1,604 | 360 | 1,964 | 926 2 legs at 60° |
DRAFT | |
| IN020-1 | NPR-SPU | Install new suction pick-up roll Certified (scale or OEM certificate) |
IN020 29-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 74 ft radius |
39,100 | 11,050 | 50,150 | 19,550 2 legs at 90° |
DRAFT | |
| IN020-2 | NPR-1T | Install new 1st press top roll Certified (scale or OEM certificate) |
IN020 29-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 80 ft radius |
53,200 | 11,050 | 64,250 | 26,600 2 legs at 90° |
DRAFT | |
| IN020-3 | NPR-SP | Install new suction press roll Certified (scale or OEM certificate) |
IN020 29-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 88 ft radius |
63,800 | 11,050 | 74,850 | 31,900 2 legs at 90° |
DRAFT CRITICAL LIFT | |
| IN020-4 | NPR-2T | Install new 2nd press top roll Certified (scale or OEM certificate) |
IN020 29-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 82 ft radius |
48,400 | 11,050 | 59,450 | 24,200 2 legs at 90° |
DRAFT | |
| IN020-5 | NPR-2B | Install new 2nd press bottom roll Certified (scale or OEM certificate) |
IN020 29-Jan-27 | Mobile crane (250t) 150 ft main boom, full counterweight · 86 ft radius |
45,000 | 11,050 | 56,050 | 22,500 2 legs at 90° |
DRAFT | |
| IF07-1 | FR-07N | Install new felt roll FR-07 Certified (scale or OEM certificate) |
IF07 30-Jan-27 | Machine room crane (60t) | 12,631 | 3,668 | 16,299 | 7,293 2 legs at 60° |
DRAFT | |
| IF10-1 | FR-10N | Install new felt roll FR-10 Certified (scale or OEM certificate) |
IF10 30-Jan-27 | Machine room crane (60t) | 13,750 | 3,668 | 17,418 | 7,939 2 legs at 60° |
DRAFT | |
| IG13-1 | BG-13N | Install new bull gear BG-13 Certified (scale or OEM certificate) |
IG13 30-Jan-27 | Gear case hoist (10t) | 8,211 | 360 | 8,571 | 4,741 2 legs at 60° |
DRAFT | |
| IG13-2 | IG-25N | Install new idler gear IG-25 Certified (scale or OEM certificate) |
IG13 30-Jan-27 | Gear case hoist (10t) | 1,735 | 360 | 2,095 | 1,002 2 legs at 60° |
DRAFT | |
| IG13-3 | IG-26N | Install new idler gear IG-26 Certified (scale or OEM certificate) |
IG13 30-Jan-27 | Gear case hoist (10t) | 1,866 | 360 | 2,226 | 1,077 2 legs at 60° |
DRAFT | |
| IG14-1 | BG-14N | Install new bull gear BG-14 Certified (scale or OEM certificate) |
IG14 30-Jan-27 | Gear case hoist (10t) | 8,308 | 360 | 8,668 | 4,797 2 legs at 60° |
DRAFT | |
| IG14-2 | IG-27N | Install new idler gear IG-27 Certified (scale or OEM certificate) |
IG14 30-Jan-27 | Gear case hoist (10t) | 1,997 | 360 | 2,357 | 1,153 2 legs at 60° |
DRAFT | |
| IF11-1 | FR-11N | Install new felt roll FR-11 Certified (scale or OEM certificate) |
IF11 31-Jan-27 | Machine room crane (60t) | 14,123 | 3,668 | 17,791 | 8,154 2 legs at 60° |
DRAFT | |
| IF12-1 | FR-12N | Install new felt roll FR-12 Certified (scale or OEM certificate) |
IF12 01-Feb-27 | Machine room crane (60t) | 14,496 | 3,668 | 18,164 | 8,369 2 legs at 60° |
DRAFT | |
| IF13-1 | FR-13N | Install new felt roll FR-13 Certified (scale or OEM certificate) |
IF13 02-Feb-27 | Machine room crane (60t) | 10,069 | 3,668 | 13,737 | 5,813 2 legs at 60° |
DRAFT |
Cranes and hoists
Gear case hoist (10t) Chain hoist or come-along
Rated 20,000 lb · hook block 180 lb · inspected 2026-06-23 · 82 lifts, highest 43.3% of chart
Machine room crane (60t) Overhead bridge crane
Rated 120,000 lb · hook block 2,500 lb · inspected 2026-06-23 · 66 lifts, highest 65.4% of chart
Mobile crane (250t) Mobile crane
Rated 500,000 lb · hook block 4,800 lb · inspected 2026-06-23 · 14 lifts, highest 87.0% of chart
Load chart (9 points)
| Set-up | Radius ft | Capacity lb |
|---|---|---|
| 150 ft main boom, full counterweight | 30 | 330,000 |
| 150 ft main boom, full counterweight | 40 | 262,000 |
| 150 ft main boom, full counterweight | 50 | 207,000 |
| 150 ft main boom, full counterweight | 60 | 168,000 |
| 150 ft main boom, full counterweight | 70 | 139,000 |
| 150 ft main boom, full counterweight | 80 | 116,000 |
| 150 ft main boom, full counterweight | 90 | 98,000 |
| 150 ft main boom, full counterweight | 100 | 83,000 |
| 150 ft main boom, full counterweight | 110 | 71,000 |
Add or update a crane
Rigging by tag
| Tag | What | WLL lb | Weight lb | Inspected |
|---|---|---|---|---|
| BC-01 | Beam trolley over the gear case, 10 t Beam clamp or trolley | 20,000 | 160 | 2026-06-23 |
| LL-01 | Gear lifting eye bolts, pair, 5 t Hook or lifting lug | 10,000 | 6 | 2026-06-23 |
| SH-01 | Bolt-type shackle, 35 t Shackle | 70,000 | 95 | 2026-06-23 |
| SH-10 | Bolt-type shackle, 17 t Shackle | 34,000 | 40 | 2026-06-23 |
| SH-20 | Screw-pin shackle, 8.5 t Shackle | 17,000 | 12 | 2026-06-23 |
| SH-30 | Screw-pin shackle, 3.25 t Shackle | 6,500 | 3 | 2026-06-23 |
| SL-05 | 1-1/2 in wire rope sling, 16 ft, choked on journal Sling | 42,000 | 210 | 2026-06-23 |
| SL-06 | 1-3/4 in wire rope sling, 20 ft, choked on journal Sling | 56,000 | 330 | 2026-06-23 |
| SL-10 | Round sling, 12 ft, vertical Sling | 21,200 | 22 | 2026-06-23 |
| SL-20 | Round sling, 8 ft, vertical Sling | 8,400 | 8 | 2026-06-23 |
| SL-30 | Nylon web sling, 2 in, 6 ft, vertical Sling | 6,400 | 4 | 2026-06-23 |
| SP-01 | Dryer spreader beam, 40 t, 14 ft Spreader or lifting beam | 80,000 | 3,200 | 2026-06-23 |
| SP-02 | Press roll spreader beam, 60 t, 20 ft Spreader or lifting beam | 120,000 | 5,400 | 2026-06-23 |
| SP-03 | Felt roll lifting beam, 10 t, 26 ft Spreader or lifting beam | 20,000 | 1,100 | 2026-06-23 |