Rigging and lift plans
Every lift by equipment tag, with the weight, rigging, crane and people, and the checks the platform runs.
Make a lift plan
- Open Safety, then Lift plans, and press New lift plan.
- Load: equipment tag, item weight and where it came from (certified, drawing, calculated, estimated). Estimates are planned 10% heavy.
- Rigging by tag, the crane and set-up, radius, pick and set points, exclusion zone and wind limit.
- People: lift director, operator, rigger and signal person. Press Save lift plan.
Checks and approval
- The platform adds rigging and hook block to the weight, reads the load chart at the next radius out, and checks each sling and shackle at the sling angle.
- Over 75% of the chart, a tandem pick or a load over people is a critical lift: it needs a lift review and PM, CM or superintendent approval.
- A plan with a failed check cannot be approved, and nobody approves their own plan.
- After the lift, Record the lift as made.
The arithmetic is a cross-check. The crane chart, rigging ratings and the qualified lift director's sign-off govern the lift.