SAMPLE PROJECT · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
OverviewPre-task plansPermitsInspectionsCorrective actionsIncidents and near missesStop workToolbox talksObservationsTraining and cardsLift plans

All lift plans

Lift plan RM010-1: PR-SPU Remove suction pick-up roll to the laydown ?

APPROVED Prepared by R. Okafor, Apex Rigging lift planner 2026-09-30 · approved by Jordan Pike, PM 2026-10-07

Item weight
38,400 lb
From the drawing
Source: lift_plan
Gross load calc
49,450 lb
item + 6,250 rigging + 4,800 hook block
Source: lift_plan, rigging_gear, lift_crane
Capacity at radius calc
116,000 lb
Mobile crane (250t), 74 ft
Source: lift_chart, lift_crane
% of chart calc
42.6%
critical over 75%, not allowed over 90%
Source: lift_plan, lift_chart
Sling load per leg calc
19,200 lb
2 of 2 legs carrying at 90°
Source: lift_plan

Load and rigging

ItemQtyWLL lbWeight lb
PR-SPU Remove suction pick-up roll to the laydown138,400
SH-01 Bolt-type shackle, 35 t270,000190
SL-06 1-3/4 in wire rope sling, 20 ft, choked on journal256,000660
SP-02 Press roll spreader beam, 60 t, 20 ft1120,0005,400
Hook block, Mobile crane (250t)14,800
Gross load49,450

Crane, path and people

Crane
Mobile crane (250t) (Mobile crane, rated 500,000 lb, inspected 2026-06-23)
Set-up
150 ft main boom, full counterweight · boom 150 ft · radius 74 ft
Pick
Suction pick-up roll journals, press section · EL 120
Set
North laydown cribbing · EL 100
Exclusion zone
Press section and north pad barricaded, roof hatch watch posted, no one under the load path
Wind limit
20 mph
Lift director
M. Alvarez, Apex Rigging lift director
Operator
D. Reyes, Apex Rigging operator
Rigger
K. Brandt, Northfield Millwright rigger
Signal person
S. Whitfield, Apex Rigging signal person
Schedule
RM010 Remove Voith press section: rolls and felt run, 12-Jan-27 to 14-Jan-27

Checks

PASSCrane capacity49,450 lb gross is 42.6% of 116,000 lb (chart at 80 ft, 150 ft main boom, full counterweight). Limit 90%; over 75% is a critical lift.
PASSSling angle90° from horizontal; under 45° raises sling tension sharply and under 30° is not allowed.
PASSSH-01 shackleWLL 70,000 lb against 19,200 lb per leg (2 legs carrying at 90°)
PASSSL-06 slingWLL 56,000 lb against 19,200 lb per leg (2 legs carrying at 90°)
PASSSP-02 spreader or lifting beamWLL 120,000 lb against 38,400 lb
PASSPeople namedLift director, operator, rigger and signal person named.
PASSExclusion zonePress section and north pad barricaded, roof hatch watch posted, no one under the load path

A cross-check for the lift team. The crane manufacturer's chart, the rigging ratings and the qualified lift director's sign-off govern the lift.

Lift made

Cancel

Change the plan

Load
Crane
Rigging
People and area