Schedule
The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.
Data date
2026-10-20
Source: project
Project finish calc
2027-03-14
early finish of the last activity
Source: activity
Against baseline calc
on time
baseline 2027-03-14, set 2026-05-25 by Jordan Pike, PM
Source: baseline_activity
Critical activities
50
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-21 16:50
by Jordan Pike, PM
Source: schedule_run
| Activity | Orig dur | Rem dur | % comp | Start | Finish | BL start | BL finish | Total float calc | Free float | vs BL | Jul 2026Aug 2026Sep 2026Oct 2026Nov 2026Dec 2026 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 3 Procurement and fabrication 1 activity | 77% | 20-Jun-26 | 02-Dec-26 | 20-Jun-26 | 16-Nov-26 | -16 | |||||
| 3.1 Voith press section 1 activity | 77% | 20-Jun-26 | 02-Dec-26 | 20-Jun-26 | 16-Nov-26 | -16 | |||||
| FB010 IN PROGRESS Fabricate new press section (OEM)PMGT · Shops, fabrication and laydown · after EN010 | 150 | 43 | 77% | 20-Jun-26 A | 02-Dec-26 | 20-Jun-26 | 16-Nov-26 | 19 | 0 | -16 |
Source: activity, activity_rel, baseline_activity, work_calendar, holiday
Add an activity
Run, baseline and publish
Work calendar
Non-work days
2026-11-26 Thanksgiving
2026-12-25 Christmas
2027-01-01 New Year's Day