SAMPLE PROJECT · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Gantt and activities Schedule check Working over each other 6

Schedule ?

The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.

Data date
2026-10-20
Source: project
Project finish calc
2027-03-14
early finish of the last activity
Source: activity
Against baseline calc
on time
baseline 2027-03-14, set 2026-05-25 by Jordan Pike, PM
Source: baseline_activity
Critical activities
50
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-21 16:50
by Jordan Pike, PM
Source: schedule_run
Critical path 50 Has float 87float bar to late finish In progress 1 Complete 0 Baseline 137 WBS summary Data date 2026-10-20
ActivityOrig durRem dur% compStartFinishBL startBL finishTotal float calcFree floatvs BL
Jul 2026Aug 2026Sep 2026Oct 2026Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027
3 Procurement and fabrication 4 activities 66% 20-Jun-2618-Dec-26 20-Jun-2603-Dec-26 -15
3.1 Voith press section 3 activities 70% 20-Jun-2618-Dec-26 20-Jun-2603-Dec-26 -15
FB010 IN PROGRESS Fabricate new press section (OEM)PMGT · Shops, fabrication and laydown · after EN010
Edit

Predecessors

EN010 FS

Successors

FB020 FS

Progress to the data date

Change the activity

Early 2026-06-20 to 2026-12-02 · late 2026-11-08 to 2026-12-21 · free float 0 · baseline 2026-06-20 to 2026-11-16

150 43 77% 20-Jun-26 A 02-Dec-26 20-Jun-26 16-Nov-26 19 0 -16
FB020 Press section factory acceptance testQAQC · Shops, fabrication and laydown · after FB010
Edit

Predecessors

FB010 FS

Successors

FB030 FS

Progress to the data date

Change the activity

Early 2026-12-03 to 2026-12-06 · late 2026-12-22 to 2026-12-26 · free float 0 · baseline 2026-11-17 to 2026-11-20

4 4 0% 03-Dec-26 06-Dec-26 17-Nov-26 20-Nov-26 19 0 -16
FB030 Ship press section to the millPMGT · Shops, fabrication and laydown · after FB020
Edit

Predecessors

FB020 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2026-12-07 to 2026-12-18 · late 2026-12-27 to 2027-01-08 · free float 0 · baseline 2026-11-21 to 2026-12-03

12 12 0% 07-Dec-26 18-Dec-26 21-Nov-26 03-Dec-26 19 0 -15
3.5 Receiving and staging 1 activity 0% 11-Dec-2618-Dec-26 25-Nov-2603-Dec-26 -15
FB110 Receive, inspect and stage all equipment at the laydownMILL · Northfield Millwright Services · Shops, fabrication and laydown · after FB030, FB050, FB060, FB070, FB080, FB090, FB100
Edit

Predecessors

FB030 FF
FB050 FF
FB060 FF
FB070 FF
FB080 FF
FB090 FF
FB100 FF

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2026-12-11 to 2026-12-18 · late 2026-12-31 to 2027-01-08 · free float 0 · baseline 2026-11-25 to 2026-12-03

8 8 0% 11-Dec-26 18-Dec-26 25-Nov-26 03-Dec-26 19 0 -15
4 Pre-outage, machine running 1 activity 0% 19-Dec-2619-Dec-26 04-Dec-2604-Dec-26 -15
4.1 Site setup and readiness 1 activity 0% 19-Dec-2619-Dec-26 04-Dec-2604-Dec-26 -15
PR080 Outage readiness review with the millPMGT · Office and engineering · after EN080, FB110, PC020, PR010, PR020, PR030, PR040, PR050, PR060, PR070
Edit

Predecessors

EN080 FS
FB110 FS
PC020 FS
PR010 FS
PR020 FS
PR030 FS
PR040 FS
PR050 FS
PR060 FS
PR070 FF

Successors

OT000 FS

Progress to the data date

Change the activity

Early 2026-12-19 to 2026-12-19 · late 2027-01-09 to 2027-01-09 · free float 19 · baseline 2026-12-04 to 2026-12-04

1 1 0% 19-Dec-26 19-Dec-26 04-Dec-26 04-Dec-26 19 19 -15
5 Outage: shut down and remove 55 activities · 21 critical 0% 10-Jan-2721-Jan-27 10-Jan-2721-Jan-27 0
5.1 Shutdown, lockout and disconnect 6 activities · 4 critical 0% 10-Jan-2713-Jan-27 10-Jan-2713-Jan-27 0
OT000 CRITICAL Machine down: last paper off the reelPMGT · Dryer section · Must start on 2027-01-10 · after PR080
Edit

Predecessors

PR080 FS

Successors

OT010 FS

Progress to the data date

Change the activity

Early 2027-01-10 to 2027-01-10 · late 2027-01-10 to 2027-01-10 · free float 0 · baseline 2027-01-10 to 2027-01-10

MS 0 0% 10-Jan-27 10-Jan-27 10-Jan-27 10-Jan-27 0 0 0
Machine down: last paper off the reel
OT010 CRITICAL Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · Dryer section · after OT000
Edit

Predecessors

OT000 FS

Successors

OT020 FS
OT040 FS
OT050 FS

Progress to the data date

Change the activity

Early 2027-01-10 to 2027-01-10 · late 2027-01-10 to 2027-01-10 · free float 0 · baseline 2027-01-10 to 2027-01-10

1 1 0% 10-Jan-27 10-Jan-27 10-Jan-27 10-Jan-27 0 0 0
OT020 CRITICAL Remove press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after OT010
Edit

Predecessors

OT010 FS

Successors

OT030 FS
RM010 FS

Progress to the data date

Change the activity

Early 2027-01-11 to 2027-01-11 · late 2027-01-11 to 2027-01-11 · free float 0 · baseline 2027-01-11 to 2027-01-11

1 1 0% 11-Jan-27 11-Jan-27 11-Jan-27 11-Jan-27 0 0 0
OT040 Disconnect steam, condensate and lube oilPIPE · Ironwood Piping · Drive side, gear case and basement · after OT010
Edit

Predecessors

OT010 FS

Successors

RG01 FS
RG02 FS
RG03 FS
RG04 FS
RG05 FS
RG06 FS
RG07 FS
RG08 FS
RG09 FS
RG10 FS
RG11 FS
RG12 FS
RG13 FS
RG14 FS

Progress to the data date

Change the activity

Early 2027-01-11 to 2027-01-12 · late 2027-01-12 to 2027-01-13 · free float 0 · baseline 2027-01-11 to 2027-01-12

2 2 0% 11-Jan-27 12-Jan-27 11-Jan-27 12-Jan-27 1 0 0
OT050 Disconnect drives and instrumentsEI · Delta Electric and Controls · Drive side, gear case and basement · after OT010
Edit

Predecessors

OT010 FS

Successors

None

Progress to the data date

Change the activity

Early 2027-01-11 to 2027-01-11 · late 2027-03-14 to 2027-03-14 · free float 62 · baseline 2027-01-11 to 2027-01-11

1 1 0% 11-Jan-27 11-Jan-27 11-Jan-27 11-Jan-27 62 62 0
OT030 CRITICAL Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · Dryer section · after OT020
Edit

Predecessors

OT020 FS

Successors

RB01 FS
RB02 FS
RB03 FS
RB04 FS
RB05 FS
RB06 FS
RF01 FS
RF02 FS
RF03 FS
RF04 FS
RF05 FS
RF06 FS
RF07 FS
RF08 FS
RF09 FS
RF10 FS
RF11 FS
RF12 FS
RF13 FS

Progress to the data date

Change the activity

Early 2027-01-12 to 2027-01-13 · late 2027-01-12 to 2027-01-13 · free float 0 · baseline 2027-01-12 to 2027-01-13

2 2 0% 12-Jan-27 13-Jan-27 12-Jan-27 13-Jan-27 0 0 0
5.2 Press section removal 2 activities 0% 12-Jan-2716-Jan-27 12-Jan-2716-Jan-27 0
RM010 Remove Voith press section: rolls and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after OT020
Edit

Predecessors

OT020 FS

Successors

RM020 FS

Progress to the data date

Change the activity

Early 2027-01-12 to 2027-01-14 · late 2027-01-17 to 2027-01-19 · free float 0 · baseline 2027-01-12 to 2027-01-14

3 3 0% 12-Jan-27 14-Jan-27 12-Jan-27 14-Jan-27 5 0 0
RM020 Remove press section frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after RM010
Edit

Predecessors

RM010 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-16 · late 2027-01-20 to 2027-01-21 · free float 5 · baseline 2027-01-15 to 2027-01-16

2 2 0% 15-Jan-27 16-Jan-27 15-Jan-27 16-Jan-27 5 5 0
5.3 Felt roll removal 13 activities · 2 critical 0% 14-Jan-2714-Jan-27 14-Jan-2714-Jan-27 0
RF01 CRITICAL Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
RF02 CRITICAL Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD02 FS
RD03 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
RF03 Remove felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD03 FS
RD04 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-15 to 2027-01-15 · free float 1 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 1 1 0
RF04 Remove felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD04 FS
RD05 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-15 to 2027-01-15 · free float 1 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 1 1 0
RF05 Remove felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD05 FS
RD06 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-16 to 2027-01-16 · free float 2 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 2 2 0
RF06 Remove felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD06 FS
RD07 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-16 to 2027-01-16 · free float 2 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 2 2 0
RF07 Remove felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD07 FS
RD08 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-17 to 2027-01-17 · free float 3 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 3 3 0
RF08 Remove felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD08 FS
RD09 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-17 to 2027-01-17 · free float 3 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 3 3 0
RF09 Remove felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD09 FS
RD10 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-18 to 2027-01-18 · free float 4 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 4 4 0
RF10 Remove felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD10 FS
RD11 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-18 to 2027-01-18 · free float 4 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 4 4 0
RF11 Remove felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD11 FS
RD12 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-19 to 2027-01-19 · free float 5 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 5 5 0
RF12 Remove felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD12 FS
RD13 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-19 to 2027-01-19 · free float 5 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 5 5 0
RF13 Remove felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD13 FS
RD14 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-20 to 2027-01-20 · free float 6 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 6 6 0
5.4 Blow box removal 6 activities · 1 critical 0% 14-Jan-2714-Jan-27 14-Jan-2714-Jan-27 0
RB01 CRITICAL Remove blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
RB02 Remove blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD03 FS
RD04 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-15 to 2027-01-15 · free float 1 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 1 1 0
RB03 Remove blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD05 FS
RD06 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-16 to 2027-01-16 · free float 2 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 2 2 0
RB04 Remove blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD07 FS
RD08 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-17 to 2027-01-17 · free float 3 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 3 3 0
RB05 Remove blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD09 FS
RD10 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-18 to 2027-01-18 · free float 4 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 4 4 0
RB06 Remove blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD11 FS
RD12 FS
RD13 FS
RD14 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-19 to 2027-01-19 · free float 5 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 5 5 0
5.5 Bull and idler gear removal 14 activities 0% 13-Jan-2719-Jan-27 13-Jan-2719-Jan-27 0
RG01 Remove bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040
Edit

Predecessors

OT040 FS

Successors

RD01 FS
RG03 FS

Progress to the data date

Change the activity

Early 2027-01-13 to 2027-01-13 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-13 to 2027-01-13

1 1 0% 13-Jan-27 13-Jan-27 13-Jan-27 13-Jan-27 1 0 0
RG02 Remove bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040
Edit

Predecessors

OT040 FS

Successors

RD02 FS
RG04 FS

Progress to the data date

Change the activity

Early 2027-01-13 to 2027-01-13 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-13 to 2027-01-13

1 1 0% 13-Jan-27 13-Jan-27 13-Jan-27 13-Jan-27 1 0 0
RG03 Remove bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG01
Edit

Predecessors

OT040 FS
RG01 FS

Successors

LB01 FS
RD03 FS
RG05 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 1 0 0
RG04 Remove bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG02
Edit

Predecessors

OT040 FS
RG02 FS

Successors

RD04 FS
RG06 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 1 0 0
RG05 Remove bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG03
Edit

Predecessors

OT040 FS
RG03 FS

Successors

RD05 FS
RG07 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 1 0 0
RG06 Remove bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG04
Edit

Predecessors

OT040 FS
RG04 FS

Successors

LB02 FS
RD06 FS
RG08 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 1 0 0
RG07 Remove bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG05
Edit

Predecessors

OT040 FS
RG05 FS

Successors

RD07 FS
RG09 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 1 0 0
RG08 Remove bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG06
Edit

Predecessors

OT040 FS
RG06 FS

Successors

RD08 FS
RG10 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 1 0 0
RG09 Remove bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG07
Edit

Predecessors

OT040 FS
RG07 FS

Successors

LB03 FS
RD09 FS
RG11 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 1 0 0
RG10 Remove bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG08
Edit

Predecessors

OT040 FS
RG08 FS

Successors

RD10 FS
RG12 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 1 0 0
RG11 Remove bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG09
Edit

Predecessors

OT040 FS
RG09 FS

Successors

RD11 FS
RG13 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 1 0 0
RG12 Remove bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG10
Edit

Predecessors

OT040 FS
RG10 FS

Successors

LB04 FS
RD12 FS
RG14 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 1 0 0
RG13 Remove bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG11
Edit

Predecessors

OT040 FS
RG11 FS

Successors

RD13 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-20 to 2027-01-20 · free float 1 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 1 1 0
RG14 Remove bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after OT040, RG12
Edit

Predecessors

OT040 FS
RG12 FS

Successors

LB05 FS
RD14 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-20 to 2027-01-20 · free float 1 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 1 1 0
5.6 Dryer removal 14 activities · 14 critical 0% 15-Jan-2721-Jan-27 15-Jan-2721-Jan-27 0
RD01 CRITICAL Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RG01
Edit

Predecessors

RB01 FS
RF01 FS
RG01 FS

Successors

RD03 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 0 0 0
RD02 CRITICAL Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RF02, RG02
Edit

Predecessors

RB01 FS
RF01 FS
RF02 FS
RG02 FS

Successors

RD04 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 0 0 0
RD03 CRITICAL Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD01, RF02, RF03, RG03
Edit

Predecessors

RB02 FS
RD01 FS
RF02 FS
RF03 FS
RG03 FS

Successors

RD05 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 0 0 0
RD04 CRITICAL Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD02, RF03, RF04, RG04
Edit

Predecessors

RB02 FS
RD02 FS
RF03 FS
RF04 FS
RG04 FS

Successors

RD06 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 0 0 0
RD05 CRITICAL Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD03, RF04, RF05, RG05
Edit

Predecessors

RB03 FS
RD03 FS
RF04 FS
RF05 FS
RG05 FS

Successors

RD07 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 0 0 0
RD06 CRITICAL Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD04, RF05, RF06, RG06
Edit

Predecessors

RB03 FS
RD04 FS
RF05 FS
RF06 FS
RG06 FS

Successors

RD08 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 0 0 0
RD07 CRITICAL Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD05, RF06, RF07, RG07
Edit

Predecessors

RB04 FS
RD05 FS
RF06 FS
RF07 FS
RG07 FS

Successors

RD09 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 0 0 0
RD08 CRITICAL Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD06, RF07, RF08, RG08
Edit

Predecessors

RB04 FS
RD06 FS
RF07 FS
RF08 FS
RG08 FS

Successors

RD10 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 0 0 0
RD09 CRITICAL Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD07, RF08, RF09, RG09
Edit

Predecessors

RB05 FS
RD07 FS
RF08 FS
RF09 FS
RG09 FS

Successors

RD11 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 0 0 0
RD10 CRITICAL Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD08, RF09, RF10, RG10
Edit

Predecessors

RB05 FS
RD08 FS
RF09 FS
RF10 FS
RG10 FS

Successors

RD12 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 0 0 0
RD11 CRITICAL Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD09, RF10, RF11, RG11
Edit

Predecessors

RB06 FS
RD09 FS
RF10 FS
RF11 FS
RG11 FS

Successors

RD13 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-20 to 2027-01-20 · late 2027-01-20 to 2027-01-20 · free float 0 · baseline 2027-01-20 to 2027-01-20

1 1 0% 20-Jan-27 20-Jan-27 20-Jan-27 20-Jan-27 0 0 0
RD12 CRITICAL Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD10, RF11, RF12, RG12
Edit

Predecessors

RB06 FS
RD10 FS
RF11 FS
RF12 FS
RG12 FS

Successors

RD14 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-20 to 2027-01-20 · late 2027-01-20 to 2027-01-20 · free float 0 · baseline 2027-01-20 to 2027-01-20

1 1 0% 20-Jan-27 20-Jan-27 20-Jan-27 20-Jan-27 0 0 0
RD13 CRITICAL Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD11, RF12, RF13, RG13
Edit

Predecessors

RB06 FS
RD11 FS
RF12 FS
RF13 FS
RG13 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2027-01-21 to 2027-01-21 · late 2027-01-21 to 2027-01-21 · free float 0 · baseline 2027-01-21 to 2027-01-21

1 1 0% 21-Jan-27 21-Jan-27 21-Jan-27 21-Jan-27 0 0 0
RD14 CRITICAL Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD12, RF13, RG14
Edit

Predecessors

RB06 FS
RD12 FS
RF13 FS
RG14 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2027-01-21 to 2027-01-21 · late 2027-01-21 to 2027-01-21 · free float 0 · baseline 2027-01-21 to 2027-01-21

1 1 0% 21-Jan-27 21-Jan-27 21-Jan-27 21-Jan-27 0 0 0
6 Outage: machining and survey 6 activities · 1 critical 0% 15-Jan-2724-Jan-27 15-Jan-2724-Jan-27 0
6.1 Frame survey 1 activity · 1 critical 0% 22-Jan-2722-Jan-27 22-Jan-2722-Jan-27 0
SV010 CRITICAL Survey the frames after removalSURV · Benchmark Alignment Survey · Dryer section · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020
Edit

Predecessors

RD01 FS
RD02 FS
RD03 FS
RD04 FS
RD05 FS
RD06 FS
RD07 FS
RD08 FS
RD09 FS
RD10 FS
RD11 FS
RD12 FS
RD13 FS
RD14 FS
RM020 FS

Successors

ID01 FS
ID02 FS
ID03 FS
ID04 FS
ID05 FS
ID06 FS
ID07 FS
ID08 FS
ID09 FS
ID10 FS
ID11 FS
ID12 FS
ID13 FS
ID14 FS
IN010 FS

Progress to the data date

Change the activity

Early 2027-01-22 to 2027-01-22 · late 2027-01-22 to 2027-01-22 · free float 0 · baseline 2027-01-22 to 2027-01-22

1 1 0% 22-Jan-27 22-Jan-27 22-Jan-27 22-Jan-27 0 0 0
6.2 Line bore and sleeve idler bores 5 activities 0% 15-Jan-2724-Jan-27 15-Jan-2724-Jan-27 0
LB01 Line bore and sleeve idler bearing bore IB-1MECH · Precision Line Boring Co · Drive side, gear case and basement · after RG03
Edit

Predecessors

RG03 FS

Successors

IG03 FS
LB02 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-16 · late 2027-01-23 to 2027-01-24 · free float 0 · baseline 2027-01-15 to 2027-01-16

2 2 0% 15-Jan-27 16-Jan-27 15-Jan-27 16-Jan-27 8 0 0
LB02 Line bore and sleeve idler bearing bore IB-2MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB01, RG06
Edit

Predecessors

LB01 FS
RG06 FS

Successors

IG06 FS
LB03 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-18 · late 2027-01-25 to 2027-01-26 · free float 0 · baseline 2027-01-17 to 2027-01-18

2 2 0% 17-Jan-27 18-Jan-27 17-Jan-27 18-Jan-27 8 0 0
LB03 Line bore and sleeve idler bearing bore IB-3MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB02, RG09
Edit

Predecessors

LB02 FS
RG09 FS

Successors

IG09 FS
LB04 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-20 · late 2027-01-27 to 2027-01-28 · free float 0 · baseline 2027-01-19 to 2027-01-20

2 2 0% 19-Jan-27 20-Jan-27 19-Jan-27 20-Jan-27 8 0 0
LB04 Line bore and sleeve idler bearing bore IB-4MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB03, RG12
Edit

Predecessors

LB03 FS
RG12 FS

Successors

IG12 FS
LB05 FS

Progress to the data date

Change the activity

Early 2027-01-21 to 2027-01-22 · late 2027-01-29 to 2027-01-30 · free float 0 · baseline 2027-01-21 to 2027-01-22

2 2 0% 21-Jan-27 22-Jan-27 21-Jan-27 22-Jan-27 8 0 0
LB05 Line bore and sleeve idler bearing bore IB-5MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB04, RG14
Edit

Predecessors

LB04 FS
RG14 FS

Successors

IG14 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-24 · late 2027-01-31 to 2027-02-01 · free float 5 · baseline 2027-01-23 to 2027-01-24

2 2 0% 23-Jan-27 24-Jan-27 23-Jan-27 24-Jan-27 8 5 0
7 Outage: install 51 activities · 14 critical 0% 23-Jan-2703-Feb-27 23-Jan-2703-Feb-27 0
7.1 Press section install 4 activities 0% 23-Jan-2703-Feb-27 23-Jan-2703-Feb-27 0
IN010 Set new press frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after SV010
Edit

Predecessors

SV010 FS

Successors

IN015 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-25 · late 2027-01-24 to 2027-01-26 · free float 0 · baseline 2027-01-23 to 2027-01-25

3 3 0% 23-Jan-27 25-Jan-27 23-Jan-27 25-Jan-27 1 0 0
IN015 Grout press sole plates and cureCONC · Granite Grout and Concrete · Press section · after IN010
Edit

Predecessors

IN010 FS

Successors

IN020 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-28 · late 2027-01-27 to 2027-01-29 · free float 0 · baseline 2027-01-26 to 2027-01-28

3 3 0% 26-Jan-27 28-Jan-27 26-Jan-27 28-Jan-27 1 0 0
IN020 Install press rolls, suction roll and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after IN015
Edit

Predecessors

IN015 FS

Successors

IN030 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-02-01 · late 2027-01-30 to 2027-02-02 · free float 0 · baseline 2027-01-29 to 2027-02-01

4 4 0% 29-Jan-27 01-Feb-27 29-Jan-27 01-Feb-27 1 0 0
IN030 Align the press sectionSURV · Benchmark Alignment Survey · Press section · after IN020
Edit

Predecessors

IN020 FS

Successors

SY060 FS

Progress to the data date

Change the activity

Early 2027-02-02 to 2027-02-03 · late 2027-02-03 to 2027-02-04 · free float 0 · baseline 2027-02-02 to 2027-02-03

2 2 0% 02-Feb-27 03-Feb-27 02-Feb-27 03-Feb-27 1 0 0
7.2 Dryer install 14 activities · 14 critical 0% 23-Jan-2729-Jan-27 23-Jan-2729-Jan-27 0
ID01 CRITICAL Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

ID03 FS
IG01 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-23 · late 2027-01-23 to 2027-01-23 · free float 0 · baseline 2027-01-23 to 2027-01-23

1 1 0% 23-Jan-27 23-Jan-27 23-Jan-27 23-Jan-27 0 0 0
ID02 CRITICAL Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

IB01 FS
ID04 FS
IF01 FS
IG02 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-23 · late 2027-01-23 to 2027-01-23 · free float 0 · baseline 2027-01-23 to 2027-01-23

1 1 0% 23-Jan-27 23-Jan-27 23-Jan-27 23-Jan-27 0 0 0
ID03 CRITICAL Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID01, SV010
Edit

Predecessors

ID01 FS
SV010 FS

Successors

ID05 FS
IF02 FS
IG03 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-24 to 2027-01-24 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 0 0 0
ID04 CRITICAL Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02, SV010
Edit

Predecessors

ID02 FS
SV010 FS

Successors

IB02 FS
ID06 FS
IF03 FS
IG04 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-24 to 2027-01-24 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 0 0 0
ID05 CRITICAL Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, SV010
Edit

Predecessors

ID03 FS
SV010 FS

Successors

ID07 FS
IF04 FS
IG05 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-25 to 2027-01-25 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 0 0 0
ID06 CRITICAL Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, SV010
Edit

Predecessors

ID04 FS
SV010 FS

Successors

IB03 FS
ID08 FS
IF05 FS
IG06 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-25 to 2027-01-25 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 0 0 0
ID07 CRITICAL Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, SV010
Edit

Predecessors

ID05 FS
SV010 FS

Successors

ID09 FS
IF06 FS
IG07 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-26 to 2027-01-26 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 0 0 0
ID08 CRITICAL Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, SV010
Edit

Predecessors

ID06 FS
SV010 FS

Successors

IB04 FS
ID10 FS
IF07 FS
IG08 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-26 to 2027-01-26 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 0 0 0
ID09 CRITICAL Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, SV010
Edit

Predecessors

ID07 FS
SV010 FS

Successors

ID11 FS
IF08 FS
IG09 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 0 0 0
ID10 CRITICAL Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, SV010
Edit

Predecessors

ID08 FS
SV010 FS

Successors

IB05 FS
ID12 FS
IF09 FS
IG10 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 0 0 0
ID11 CRITICAL Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09, SV010
Edit

Predecessors

ID09 FS
SV010 FS

Successors

ID13 FS
IF10 FS
IG11 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 0 0 0
ID12 CRITICAL Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, SV010
Edit

Predecessors

ID10 FS
SV010 FS

Successors

IB06 FS
ID14 FS
IF11 FS
IG12 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 0 0 0
ID13 CRITICAL Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, SV010
Edit

Predecessors

ID11 FS
SV010 FS

Successors

IF12 FS
IG13 FS
SY010 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 0 0 0
ID14 CRITICAL Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, SV010
Edit

Predecessors

ID12 FS
SV010 FS

Successors

IF13 FS
IG14 FS
SY010 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 0 0 0
7.3 Bull and idler gear install 14 activities 0% 24-Jan-2730-Jan-27 24-Jan-2730-Jan-27 0
IG01 Install bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID01
Edit

Predecessors

ID01 FS

Successors

IG03 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 3 0 0
IG02 Install bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID02
Edit

Predecessors

ID02 FS

Successors

IG04 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 3 0 0
IG03 Install bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID03, IG01, LB01
Edit

Predecessors

ID03 FS
IG01 FS
LB01 FS

Successors

IG05 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 3 0 0
IG04 Install bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID04, IG02
Edit

Predecessors

ID04 FS
IG02 FS

Successors

IG06 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 3 0 0
IG05 Install bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID05, IG03
Edit

Predecessors

ID05 FS
IG03 FS

Successors

IG07 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 3 0 0
IG06 Install bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID06, IG04, LB02
Edit

Predecessors

ID06 FS
IG04 FS
LB02 FS

Successors

IG08 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 3 0 0
IG07 Install bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID07, IG05
Edit

Predecessors

ID07 FS
IG05 FS

Successors

IG09 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-30 to 2027-01-30 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 3 0 0
IG08 Install bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID08, IG06
Edit

Predecessors

ID08 FS
IG06 FS

Successors

IG10 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-30 to 2027-01-30 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 3 0 0
IG09 Install bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID09, IG07, LB03
Edit

Predecessors

ID09 FS
IG07 FS
LB03 FS

Successors

IG11 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-31 to 2027-01-31 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 3 0 0
IG10 Install bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID10, IG08
Edit

Predecessors

ID10 FS
IG08 FS

Successors

IG12 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-31 to 2027-01-31 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 3 0 0
IG11 Install bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID11, IG09
Edit

Predecessors

ID11 FS
IG09 FS

Successors

IG13 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-02-01 to 2027-02-01 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 3 0 0
IG12 Install bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID12, IG10, LB04
Edit

Predecessors

ID12 FS
IG10 FS
LB04 FS

Successors

IG14 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-02-01 to 2027-02-01 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 3 0 0
IG13 Install bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID13, IG11
Edit

Predecessors

ID13 FS
IG11 FS

Successors

SY050 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-01-30 · late 2027-02-02 to 2027-02-02 · free float 0 · baseline 2027-01-30 to 2027-01-30

1 1 0% 30-Jan-27 30-Jan-27 30-Jan-27 30-Jan-27 3 0 0
IG14 Install bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after ID14, IG12, LB05
Edit

Predecessors

ID14 FS
IG12 FS
LB05 FS

Successors

SY040 SS
SY050 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-01-30 · late 2027-02-02 to 2027-02-02 · free float 0 · baseline 2027-01-30 to 2027-01-30

1 1 0% 30-Jan-27 30-Jan-27 30-Jan-27 30-Jan-27 3 0 0
7.4 Felt roll install 13 activities 0% 24-Jan-2702-Feb-27 24-Jan-2702-Feb-27 0
IF01 Install felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02
Edit

Predecessors

ID02 FS

Successors

IF02 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-31 to 2027-01-31 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 7 0 0
IF02 Install felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, IF01
Edit

Predecessors

ID03 FS
IF01 FS

Successors

IF03 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-02-01 to 2027-02-01 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 7 0 0
IF03 Install felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, IF02
Edit

Predecessors

ID04 FS
IF02 FS

Successors

IF04 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-02-02 to 2027-02-02 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 7 0 0
IF04 Install felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, IF03
Edit

Predecessors

ID05 FS
IF03 FS

Successors

IF05 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-02-03 to 2027-02-03 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 7 0 0
IF05 Install felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, IF04
Edit

Predecessors

ID06 FS
IF04 FS

Successors

IF06 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-02-04 to 2027-02-04 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 7 0 0
IF08 Install felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09
Edit

Predecessors

ID09 FS

Successors

IF09 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-02-01 to 2027-02-01 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 4 0 0
IF06 Install felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, IF05
Edit

Predecessors

ID07 FS
IF05 FS

Successors

IF07 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-02-05 to 2027-02-05 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 7 0 0
IF09 Install felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, IF08
Edit

Predecessors

ID10 FS
IF08 FS

Successors

IF10 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-02-02 to 2027-02-02 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 4 0 0
IF07 Install felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, IF06
Edit

Predecessors

ID08 FS
IF06 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-01-30 · late 2027-02-06 to 2027-02-06 · free float 7 · baseline 2027-01-30 to 2027-01-30

1 1 0% 30-Jan-27 30-Jan-27 30-Jan-27 30-Jan-27 7 7 0
IF10 Install felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, IF09
Edit

Predecessors

ID11 FS
IF09 FS

Successors

IF11 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-01-30 · late 2027-02-03 to 2027-02-03 · free float 0 · baseline 2027-01-30 to 2027-01-30

1 1 0% 30-Jan-27 30-Jan-27 30-Jan-27 30-Jan-27 4 0 0
IF11 Install felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, IF10
Edit

Predecessors

ID12 FS
IF10 FS

Successors

IF12 FS

Progress to the data date

Change the activity

Early 2027-01-31 to 2027-01-31 · late 2027-02-04 to 2027-02-04 · free float 0 · baseline 2027-01-31 to 2027-01-31

1 1 0% 31-Jan-27 31-Jan-27 31-Jan-27 31-Jan-27 4 0 0
IF12 Install felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID13, IF11
Edit

Predecessors

ID13 FS
IF11 FS

Successors

IF13 FS

Progress to the data date

Change the activity

Early 2027-02-01 to 2027-02-01 · late 2027-02-05 to 2027-02-05 · free float 0 · baseline 2027-02-01 to 2027-02-01

1 1 0% 01-Feb-27 01-Feb-27 01-Feb-27 01-Feb-27 4 0 0
IF13 Install felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID14, IF12
Edit

Predecessors

ID14 FS
IF12 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-02-02 to 2027-02-02 · late 2027-02-06 to 2027-02-06 · free float 4 · baseline 2027-02-02 to 2027-02-02

1 1 0% 02-Feb-27 02-Feb-27 02-Feb-27 02-Feb-27 4 4 0
7.5 Blow box install 6 activities 0% 24-Jan-2729-Jan-27 24-Jan-2729-Jan-27 0
IB01 Install blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02
Edit

Predecessors

ID02 FS

Successors

IB02 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-02-01 to 2027-02-01 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 8 0 0
IB02 Install blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB01, ID04
Edit

Predecessors

IB01 FS
ID04 FS

Successors

IB03 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-02-02 to 2027-02-02 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 8 0 0
IB03 Install blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB02, ID06
Edit

Predecessors

IB02 FS
ID06 FS

Successors

IB04 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-02-03 to 2027-02-03 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 8 0 0
IB04 Install blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB03, ID08
Edit

Predecessors

IB03 FS
ID08 FS

Successors

IB05 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-02-04 to 2027-02-04 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 8 0 0
IB05 Install blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB04, ID10
Edit

Predecessors

IB04 FS
ID10 FS

Successors

IB06 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-02-05 to 2027-02-05 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 8 0 0
IB06 Install blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB05, ID12
Edit

Predecessors

IB05 FS
ID12 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-02-06 to 2027-02-06 · free float 8 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 8 8 0
8 Outage: systems and checks 9 activities · 5 critical 0% 30-Jan-2709-Feb-27 30-Jan-2709-Feb-27 0
8.1 Steam, condensate and lube 4 activities · 3 critical 0% 30-Jan-2706-Feb-27 30-Jan-2706-Feb-27 0
SY010 CRITICAL Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · Drive side, gear case and basement · after ID13, ID14
Edit

Predecessors

ID13 FS
ID14 FS

Successors

SY020 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-02-02 · late 2027-01-30 to 2027-02-02 · free float 0 · baseline 2027-01-30 to 2027-02-02

4 4 0% 30-Jan-27 02-Feb-27 30-Jan-27 02-Feb-27 0 0 0
SY020 CRITICAL Hydro test dryers and steam jointsQAQC · Drive side, gear case and basement · after SY010
Edit

Predecessors

SY010 FS

Successors

SY030 SS
SY070 FS

Progress to the data date

Change the activity

Early 2027-02-03 to 2027-02-03 · late 2027-02-03 to 2027-02-03 · free float 0 · baseline 2027-02-03 to 2027-02-03

1 1 0% 03-Feb-27 03-Feb-27 03-Feb-27 03-Feb-27 0 0 0
SY030 Flush the lube oil systemPIPE · Ironwood Piping · Drive side, gear case and basement · after SY020
Edit

Predecessors

SY020 SS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2027-02-03 to 2027-02-05 · late 2027-02-06 to 2027-02-08 · free float 3 · baseline 2027-02-03 to 2027-02-05

3 3 0% 03-Feb-27 05-Feb-27 03-Feb-27 05-Feb-27 3 3 0
SY070 CRITICAL Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · Drive side, gear case and basement · after SY020
Edit

Predecessors

SY020 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-02-04 to 2027-02-06 · late 2027-02-04 to 2027-02-06 · free float 0 · baseline 2027-02-04 to 2027-02-06

3 3 0% 04-Feb-27 06-Feb-27 04-Feb-27 06-Feb-27 0 0 0
8.2 Drives and instruments 1 activity 0% 30-Jan-2701-Feb-27 30-Jan-2701-Feb-27 0
SY040 Reconnect drives and instruments, loop checkEI · Delta Electric and Controls · Drive side, gear case and basement · after IG14
Edit

Predecessors

IG14 SS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-02-01 · late 2027-02-06 to 2027-02-08 · free float 7 · baseline 2027-01-30 to 2027-02-01

3 3 0% 30-Jan-27 01-Feb-27 30-Jan-27 01-Feb-27 7 7 0
8.3 Mechanical checks and alignment 2 activities 0% 31-Jan-2705-Feb-27 31-Jan-2705-Feb-27 0
SY050 Gear mesh, backlash and runout checksMILL · Northfield Millwright Services · Drive side, gear case and basement · after IG13, IG14
Edit

Predecessors

IG13 FS
IG14 FS

Successors

SY060 FS

Progress to the data date

Change the activity

Early 2027-01-31 to 2027-02-01 · late 2027-02-03 to 2027-02-04 · free float 2 · baseline 2027-01-31 to 2027-02-01

2 2 0% 31-Jan-27 01-Feb-27 31-Jan-27 01-Feb-27 3 2 0
SY060 Final alignment survey: press and dryersSURV · Benchmark Alignment Survey · Dryer section · after IN030, SY050
Edit

Predecessors

IN030 FS
SY050 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-02-04 to 2027-02-05 · late 2027-02-05 to 2027-02-06 · free float 1 · baseline 2027-02-04 to 2027-02-05

2 2 0% 04-Feb-27 05-Feb-27 04-Feb-27 05-Feb-27 1 1 0
8.4 Demobilize and punch walk 2 activities · 2 critical 0% 07-Feb-2709-Feb-27 07-Feb-2709-Feb-27 0
SY080 CRITICAL Strike outage scaffoldingSCAF · Summit Scaffold · Dryer section · after IB06, IF07, IF13, SY060, SY070
Edit

Predecessors

IB06 FS
IF07 FS
IF13 FS
SY060 FS
SY070 FS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2027-02-07 to 2027-02-08 · late 2027-02-07 to 2027-02-08 · free float 0 · baseline 2027-02-07 to 2027-02-08

2 2 0% 07-Feb-27 08-Feb-27 07-Feb-27 08-Feb-27 0 0 0
SY090 CRITICAL Punch walk and pre-startup safety reviewQAQC · Dryer section · after SY030, SY040, SY080
Edit

Predecessors

SY030 FS
SY040 FS
SY080 FS

Successors

SU010 FS

Progress to the data date

Change the activity

Early 2027-02-09 to 2027-02-09 · late 2027-02-09 to 2027-02-09 · free float 0 · baseline 2027-02-09 to 2027-02-09

1 1 0% 09-Feb-27 09-Feb-27 09-Feb-27 09-Feb-27 0 0 0
9 Startup 5 activities · 5 critical 0% 10-Feb-2714-Feb-27 10-Feb-2714-Feb-27 0
SU010 CRITICAL Remove locks and hand the machine back to operationsCOMM · Dryer section · after SY090
Edit

Predecessors

SY090 FS

Successors

SU020 FS

Progress to the data date

Change the activity

Early 2027-02-10 to 2027-02-10 · late 2027-02-10 to 2027-02-10 · free float 0 · baseline 2027-02-10 to 2027-02-10

1 1 0% 10-Feb-27 10-Feb-27 10-Feb-27 10-Feb-27 0 0 0
SU020 CRITICAL Dry run and jog the drivesCOMM · Dryer section · after SU010
Edit

Predecessors

SU010 FS

Successors

SU030 FS

Progress to the data date

Change the activity

Early 2027-02-11 to 2027-02-12 · late 2027-02-11 to 2027-02-12 · free float 0 · baseline 2027-02-11 to 2027-02-12

2 2 0% 11-Feb-27 12-Feb-27 11-Feb-27 12-Feb-27 0 0 0
SU030 CRITICAL Hang new press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after SU020
Edit

Predecessors

SU020 FS

Successors

SU040 FS

Progress to the data date

Change the activity

Early 2027-02-13 to 2027-02-13 · late 2027-02-13 to 2027-02-13 · free float 0 · baseline 2027-02-13 to 2027-02-13

1 1 0% 13-Feb-27 13-Feb-27 13-Feb-27 13-Feb-27 0 0 0
SU040 CRITICAL Steam up and warm the dryersCOMM · Dryer section · after SU030
Edit

Predecessors

SU030 FS

Successors

SU050 FS

Progress to the data date

Change the activity

Early 2027-02-14 to 2027-02-14 · late 2027-02-14 to 2027-02-14 · free float 0 · baseline 2027-02-14 to 2027-02-14

1 1 0% 14-Feb-27 14-Feb-27 14-Feb-27 14-Feb-27 0 0 0
SU050 CRITICAL Paper on the reelCOMM · Dryer section · Finish on or before 2027-02-14 · after SU040
Edit

Predecessors

SU040 FS

Successors

CL010 FS

Progress to the data date

Change the activity

Early 2027-02-14 to 2027-02-14 · late 2027-02-14 to 2027-02-14 · free float 0 · baseline 2027-02-14 to 2027-02-14

MS 0 0% 14-Feb-27 14-Feb-27 14-Feb-27 14-Feb-27 0 0 0
Paper on the reel
10 Performance and turnover 6 activities · 4 critical 0% 15-Feb-2714-Mar-27 15-Feb-2714-Mar-27 0
10.1 Performance run 1 activity · 1 critical 0% 15-Feb-2717-Feb-27 15-Feb-2717-Feb-27 0
CL010 CRITICAL 72-hour performance runCOMM · Dryer section · after SU050
Edit

Predecessors

SU050 FS

Successors

CL020 FS
CL030 FS
CL040 FS

Progress to the data date

Change the activity

Early 2027-02-15 to 2027-02-17 · late 2027-02-15 to 2027-02-17 · free float 0 · baseline 2027-02-15 to 2027-02-17

3 3 0% 15-Feb-27 17-Feb-27 15-Feb-27 17-Feb-27 0 0 0
10.2 Closeout 5 activities · 3 critical 0% 18-Feb-2714-Mar-27 18-Feb-2714-Mar-27 0
CL020 Close the punch listQAQC · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL900 FS

Progress to the data date

Change the activity

Early 2027-02-18 to 2027-02-27 · late 2027-03-05 to 2027-03-14 · free float 15 · baseline 2027-02-18 to 2027-02-27

10 10 0% 18-Feb-27 27-Feb-27 18-Feb-27 27-Feb-27 15 15 0
CL030 Turnover packages accepted by the millPMGT · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL050 FS

Progress to the data date

Change the activity

Early 2027-02-18 to 2027-02-27 · late 2027-02-23 to 2027-03-04 · free float 5 · baseline 2027-02-18 to 2027-02-27

10 10 0% 18-Feb-27 27-Feb-27 18-Feb-27 27-Feb-27 5 5 0
CL040 CRITICAL As-built drawings and alignment reportsPMGT · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL050 FS

Progress to the data date

Change the activity

Early 2027-02-18 to 2027-03-04 · late 2027-02-18 to 2027-03-04 · free float 0 · baseline 2027-02-18 to 2027-03-04

15 15 0% 18-Feb-27 04-Mar-27 18-Feb-27 04-Mar-27 0 0 0
CL050 CRITICAL Final cost report and lessons learnedPMGT · Office and engineering · after CL030, CL040
Edit

Predecessors

CL030 FS
CL040 FS

Successors

CL900 FS

Progress to the data date

Change the activity

Early 2027-03-05 to 2027-03-14 · late 2027-03-05 to 2027-03-14 · free float 0 · baseline 2027-03-05 to 2027-03-14

10 10 0% 05-Mar-27 14-Mar-27 05-Mar-27 14-Mar-27 0 0 0
CL900 CRITICAL Project turned overPMGT · Office and engineering · after CL020, CL050
Edit

Predecessors

CL020 FS
CL050 FS

Successors

None

Progress to the data date

Change the activity

Early 2027-03-14 to 2027-03-14 · late 2027-03-14 to 2027-03-14 · free float 0 · baseline 2027-03-14 to 2027-03-14

MS 0 0% 14-Mar-27 14-Mar-27 14-Mar-27 14-Mar-27 0 0 0
Project turned over
Source: activity, activity_rel, baseline_activity, work_calendar, holiday

Add an activity

Run, baseline and publish

Keeps a snapshot. Unfinished activities whose finish moved since the last update go to the delay log for review, and contractors are asked about missed dates.

Work calendar

Non-work days

2026-11-26 Thanksgiving
2026-12-25 Christmas
2027-01-01 New Year's Day