Schedule
The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.
Data date
2026-10-20
Source: project
Project finish calc
2027-03-14
early finish of the last activity
Source: activity
Against baseline calc
on time
baseline 2027-03-14, set 2026-05-25 by Jordan Pike, PM
Source: baseline_activity
Critical activities
50
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-21 16:50
by Jordan Pike, PM
Source: schedule_run
| Activity | Orig dur | Rem dur | % comp | Start | Finish | BL start | BL finish | Total float calc | Free float | vs BL | Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 Outage: shut down and remove 21 activities · 21 critical | 0% | 10-Jan-27 | 21-Jan-27 | 10-Jan-27 | 21-Jan-27 | 0 | |||||
| 5.1 Shutdown, lockout and disconnect 4 activities · 4 critical | 0% | 10-Jan-27 | 13-Jan-27 | 10-Jan-27 | 13-Jan-27 | 0 | |||||
| OT000 CRITICAL Machine down: last paper off the reelPMGT · Dryer section · Must start on 2027-01-10 · after PR080 | MS | 0 | 0% | 10-Jan-27 | 10-Jan-27 | 10-Jan-27 | 10-Jan-27 | 0 | 0 | 0 |
Machine down: last paper off the reel
|
| OT010 CRITICAL Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · Dryer section · after OT000 | 1 | 1 | 0% | 10-Jan-27 | 10-Jan-27 | 10-Jan-27 | 10-Jan-27 | 0 | 0 | 0 | |
| OT020 CRITICAL Remove press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after OT010 | 1 | 1 | 0% | 11-Jan-27 | 11-Jan-27 | 11-Jan-27 | 11-Jan-27 | 0 | 0 | 0 | |
| OT030 CRITICAL Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · Dryer section · after OT020 | 2 | 2 | 0% | 12-Jan-27 | 13-Jan-27 | 12-Jan-27 | 13-Jan-27 | 0 | 0 | 0 | |
| 5.3 Felt roll removal 2 activities · 2 critical | 0% | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 0 | |||||
| RF01 CRITICAL Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 1 | 0% | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 0 | 0 | 0 | |
| RF02 CRITICAL Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 1 | 0% | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 0 | 0 | 0 | |
| 5.4 Blow box removal 1 activity · 1 critical | 0% | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 0 | |||||
| RB01 CRITICAL Remove blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 1 | 0% | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 14-Jan-27 | 0 | 0 | 0 | |
| 5.6 Dryer removal 14 activities · 14 critical | 0% | 15-Jan-27 | 21-Jan-27 | 15-Jan-27 | 21-Jan-27 | 0 | |||||
| RD01 CRITICAL Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RG01 | 1 | 1 | 0% | 15-Jan-27 | 15-Jan-27 | 15-Jan-27 | 15-Jan-27 | 0 | 0 | 0 | |
| RD02 CRITICAL Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RF02, RG02 | 1 | 1 | 0% | 15-Jan-27 | 15-Jan-27 | 15-Jan-27 | 15-Jan-27 | 0 | 0 | 0 | |
| RD03 CRITICAL Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD01, RF02, RF03, RG03 | 1 | 1 | 0% | 16-Jan-27 | 16-Jan-27 | 16-Jan-27 | 16-Jan-27 | 0 | 0 | 0 | |
| RD04 CRITICAL Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD02, RF03, RF04, RG04 | 1 | 1 | 0% | 16-Jan-27 | 16-Jan-27 | 16-Jan-27 | 16-Jan-27 | 0 | 0 | 0 | |
| RD05 CRITICAL Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD03, RF04, RF05, RG05 | 1 | 1 | 0% | 17-Jan-27 | 17-Jan-27 | 17-Jan-27 | 17-Jan-27 | 0 | 0 | 0 | |
| RD06 CRITICAL Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD04, RF05, RF06, RG06 | 1 | 1 | 0% | 17-Jan-27 | 17-Jan-27 | 17-Jan-27 | 17-Jan-27 | 0 | 0 | 0 | |
| RD07 CRITICAL Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD05, RF06, RF07, RG07 | 1 | 1 | 0% | 18-Jan-27 | 18-Jan-27 | 18-Jan-27 | 18-Jan-27 | 0 | 0 | 0 | |
| RD08 CRITICAL Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD06, RF07, RF08, RG08 | 1 | 1 | 0% | 18-Jan-27 | 18-Jan-27 | 18-Jan-27 | 18-Jan-27 | 0 | 0 | 0 | |
| RD09 CRITICAL Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD07, RF08, RF09, RG09 | 1 | 1 | 0% | 19-Jan-27 | 19-Jan-27 | 19-Jan-27 | 19-Jan-27 | 0 | 0 | 0 | |
| RD10 CRITICAL Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD08, RF09, RF10, RG10 | 1 | 1 | 0% | 19-Jan-27 | 19-Jan-27 | 19-Jan-27 | 19-Jan-27 | 0 | 0 | 0 | |
| RD11 CRITICAL Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD09, RF10, RF11, RG11 | 1 | 1 | 0% | 20-Jan-27 | 20-Jan-27 | 20-Jan-27 | 20-Jan-27 | 0 | 0 | 0 | |
| RD12 CRITICAL Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD10, RF11, RF12, RG12 | 1 | 1 | 0% | 20-Jan-27 | 20-Jan-27 | 20-Jan-27 | 20-Jan-27 | 0 | 0 | 0 | |
| RD13 CRITICAL Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD11, RF12, RF13, RG13 | 1 | 1 | 0% | 21-Jan-27 | 21-Jan-27 | 21-Jan-27 | 21-Jan-27 | 0 | 0 | 0 | |
| RD14 CRITICAL Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD12, RF13, RG14 | 1 | 1 | 0% | 21-Jan-27 | 21-Jan-27 | 21-Jan-27 | 21-Jan-27 | 0 | 0 | 0 | |
| 6 Outage: machining and survey 1 activity · 1 critical | 0% | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 0 | |||||
| 6.1 Frame survey 1 activity · 1 critical | 0% | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 0 | |||||
| SV010 CRITICAL Survey the frames after removalSURV · Benchmark Alignment Survey · Dryer section · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020 | 1 | 1 | 0% | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 22-Jan-27 | 0 | 0 | 0 | |
| 7 Outage: install 14 activities · 14 critical | 0% | 23-Jan-27 | 29-Jan-27 | 23-Jan-27 | 29-Jan-27 | 0 | |||||
| 7.2 Dryer install 14 activities · 14 critical | 0% | 23-Jan-27 | 29-Jan-27 | 23-Jan-27 | 29-Jan-27 | 0 | |||||
| ID01 CRITICAL Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010 | 1 | 1 | 0% | 23-Jan-27 | 23-Jan-27 | 23-Jan-27 | 23-Jan-27 | 0 | 0 | 0 | |
| ID02 CRITICAL Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010 | 1 | 1 | 0% | 23-Jan-27 | 23-Jan-27 | 23-Jan-27 | 23-Jan-27 | 0 | 0 | 0 | |
| ID03 CRITICAL Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID01, SV010 | 1 | 1 | 0% | 24-Jan-27 | 24-Jan-27 | 24-Jan-27 | 24-Jan-27 | 0 | 0 | 0 | |
| ID04 CRITICAL Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02, SV010 | 1 | 1 | 0% | 24-Jan-27 | 24-Jan-27 | 24-Jan-27 | 24-Jan-27 | 0 | 0 | 0 | |
| ID05 CRITICAL Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, SV010 | 1 | 1 | 0% | 25-Jan-27 | 25-Jan-27 | 25-Jan-27 | 25-Jan-27 | 0 | 0 | 0 | |
| ID06 CRITICAL Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, SV010 | 1 | 1 | 0% | 25-Jan-27 | 25-Jan-27 | 25-Jan-27 | 25-Jan-27 | 0 | 0 | 0 | |
| ID07 CRITICAL Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, SV010 | 1 | 1 | 0% | 26-Jan-27 | 26-Jan-27 | 26-Jan-27 | 26-Jan-27 | 0 | 0 | 0 | |
| ID08 CRITICAL Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, SV010 | 1 | 1 | 0% | 26-Jan-27 | 26-Jan-27 | 26-Jan-27 | 26-Jan-27 | 0 | 0 | 0 | |
| ID09 CRITICAL Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, SV010 | 1 | 1 | 0% | 27-Jan-27 | 27-Jan-27 | 27-Jan-27 | 27-Jan-27 | 0 | 0 | 0 | |
| ID10 CRITICAL Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, SV010 | 1 | 1 | 0% | 27-Jan-27 | 27-Jan-27 | 27-Jan-27 | 27-Jan-27 | 0 | 0 | 0 | |
| ID11 CRITICAL Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09, SV010 | 1 | 1 | 0% | 28-Jan-27 | 28-Jan-27 | 28-Jan-27 | 28-Jan-27 | 0 | 0 | 0 | |
| ID12 CRITICAL Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, SV010 | 1 | 1 | 0% | 28-Jan-27 | 28-Jan-27 | 28-Jan-27 | 28-Jan-27 | 0 | 0 | 0 | |
| ID13 CRITICAL Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, SV010 | 1 | 1 | 0% | 29-Jan-27 | 29-Jan-27 | 29-Jan-27 | 29-Jan-27 | 0 | 0 | 0 | |
| ID14 CRITICAL Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, SV010 | 1 | 1 | 0% | 29-Jan-27 | 29-Jan-27 | 29-Jan-27 | 29-Jan-27 | 0 | 0 | 0 | |
| 8 Outage: systems and checks 5 activities · 5 critical | 0% | 30-Jan-27 | 09-Feb-27 | 30-Jan-27 | 09-Feb-27 | 0 | |||||
| 8.1 Steam, condensate and lube 3 activities · 3 critical | 0% | 30-Jan-27 | 06-Feb-27 | 30-Jan-27 | 06-Feb-27 | 0 | |||||
| SY010 CRITICAL Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · Drive side, gear case and basement · after ID13, ID14 | 4 | 4 | 0% | 30-Jan-27 | 02-Feb-27 | 30-Jan-27 | 02-Feb-27 | 0 | 0 | 0 | |
| SY020 CRITICAL Hydro test dryers and steam jointsQAQC · Drive side, gear case and basement · after SY010 | 1 | 1 | 0% | 03-Feb-27 | 03-Feb-27 | 03-Feb-27 | 03-Feb-27 | 0 | 0 | 0 | |
| SY070 CRITICAL Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · Drive side, gear case and basement · after SY020 | 3 | 3 | 0% | 04-Feb-27 | 06-Feb-27 | 04-Feb-27 | 06-Feb-27 | 0 | 0 | 0 | |
| 8.4 Demobilize and punch walk 2 activities · 2 critical | 0% | 07-Feb-27 | 09-Feb-27 | 07-Feb-27 | 09-Feb-27 | 0 | |||||
| SY080 CRITICAL Strike outage scaffoldingSCAF · Summit Scaffold · Dryer section · after IB06, IF07, IF13, SY060, SY070 | 2 | 2 | 0% | 07-Feb-27 | 08-Feb-27 | 07-Feb-27 | 08-Feb-27 | 0 | 0 | 0 | |
| SY090 CRITICAL Punch walk and pre-startup safety reviewQAQC · Dryer section · after SY030, SY040, SY080 | 1 | 1 | 0% | 09-Feb-27 | 09-Feb-27 | 09-Feb-27 | 09-Feb-27 | 0 | 0 | 0 | |
| 9 Startup 5 activities · 5 critical | 0% | 10-Feb-27 | 14-Feb-27 | 10-Feb-27 | 14-Feb-27 | 0 | |||||
| SU010 CRITICAL Remove locks and hand the machine back to operationsCOMM · Dryer section · after SY090 | 1 | 1 | 0% | 10-Feb-27 | 10-Feb-27 | 10-Feb-27 | 10-Feb-27 | 0 | 0 | 0 | |
| SU020 CRITICAL Dry run and jog the drivesCOMM · Dryer section · after SU010 | 2 | 2 | 0% | 11-Feb-27 | 12-Feb-27 | 11-Feb-27 | 12-Feb-27 | 0 | 0 | 0 | |
| SU030 CRITICAL Hang new press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after SU020 | 1 | 1 | 0% | 13-Feb-27 | 13-Feb-27 | 13-Feb-27 | 13-Feb-27 | 0 | 0 | 0 | |
| SU040 CRITICAL Steam up and warm the dryersCOMM · Dryer section · after SU030 | 1 | 1 | 0% | 14-Feb-27 | 14-Feb-27 | 14-Feb-27 | 14-Feb-27 | 0 | 0 | 0 | |
| SU050 CRITICAL Paper on the reelCOMM · Dryer section · Finish on or before 2027-02-14 · after SU040 | MS | 0 | 0% | 14-Feb-27 | 14-Feb-27 | 14-Feb-27 | 14-Feb-27 | 0 | 0 | 0 |
Paper on the reel
|
| 10 Performance and turnover 4 activities · 4 critical | 0% | 15-Feb-27 | 14-Mar-27 | 15-Feb-27 | 14-Mar-27 | 0 | |||||
| 10.1 Performance run 1 activity · 1 critical | 0% | 15-Feb-27 | 17-Feb-27 | 15-Feb-27 | 17-Feb-27 | 0 | |||||
| CL010 CRITICAL 72-hour performance runCOMM · Dryer section · after SU050 | 3 | 3 | 0% | 15-Feb-27 | 17-Feb-27 | 15-Feb-27 | 17-Feb-27 | 0 | 0 | 0 | |
| 10.2 Closeout 3 activities · 3 critical | 0% | 18-Feb-27 | 14-Mar-27 | 18-Feb-27 | 14-Mar-27 | 0 | |||||
| CL040 CRITICAL As-built drawings and alignment reportsPMGT · Office and engineering · after CL010 | 15 | 15 | 0% | 18-Feb-27 | 04-Mar-27 | 18-Feb-27 | 04-Mar-27 | 0 | 0 | 0 | |
| CL050 CRITICAL Final cost report and lessons learnedPMGT · Office and engineering · after CL030, CL040 | 10 | 10 | 0% | 05-Mar-27 | 14-Mar-27 | 05-Mar-27 | 14-Mar-27 | 0 | 0 | 0 | |
| CL900 CRITICAL Project turned overPMGT · Office and engineering · after CL020, CL050 | MS | 0 | 0% | 14-Mar-27 | 14-Mar-27 | 14-Mar-27 | 14-Mar-27 | 0 | 0 | 0 |
Project turned over
|
Source: activity, activity_rel, baseline_activity, work_calendar, holiday
Add an activity
Run, baseline and publish
Work calendar
Non-work days
2026-11-26 Thanksgiving
2026-12-25 Christmas
2027-01-01 New Year's Day