SAMPLE PROJECT · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Gantt and activities Schedule check Working over each other 6

Schedule ?

The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.

Data date
2026-10-20
Source: project
Project finish calc
2027-03-14
early finish of the last activity
Source: activity
Against baseline calc
on time
baseline 2027-03-14, set 2026-05-25 by Jordan Pike, PM
Source: baseline_activity
Critical activities
50
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-21 16:50
by Jordan Pike, PM
Source: schedule_run
Critical path 50 Has float 0float bar to late finish In progress 0 Complete 0 Baseline 50 WBS summary Data date 2026-10-20
ActivityOrig durRem dur% compStartFinishBL startBL finishTotal float calcFree floatvs BL
Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027
5 Outage: shut down and remove 21 activities · 21 critical 0% 10-Jan-2721-Jan-27 10-Jan-2721-Jan-27 0
5.1 Shutdown, lockout and disconnect 4 activities · 4 critical 0% 10-Jan-2713-Jan-27 10-Jan-2713-Jan-27 0
OT000 CRITICAL Machine down: last paper off the reelPMGT · Dryer section · Must start on 2027-01-10 · after PR080
Edit

Predecessors

PR080 FS

Successors

OT010 FS

Progress to the data date

Change the activity

Early 2027-01-10 to 2027-01-10 · late 2027-01-10 to 2027-01-10 · free float 0 · baseline 2027-01-10 to 2027-01-10

MS 0 0% 10-Jan-27 10-Jan-27 10-Jan-27 10-Jan-27 0 0 0
Machine down: last paper off the reel
OT010 CRITICAL Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · Dryer section · after OT000
Edit

Predecessors

OT000 FS

Successors

OT020 FS
OT040 FS
OT050 FS

Progress to the data date

Change the activity

Early 2027-01-10 to 2027-01-10 · late 2027-01-10 to 2027-01-10 · free float 0 · baseline 2027-01-10 to 2027-01-10

1 1 0% 10-Jan-27 10-Jan-27 10-Jan-27 10-Jan-27 0 0 0
OT020 CRITICAL Remove press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after OT010
Edit

Predecessors

OT010 FS

Successors

OT030 FS
RM010 FS

Progress to the data date

Change the activity

Early 2027-01-11 to 2027-01-11 · late 2027-01-11 to 2027-01-11 · free float 0 · baseline 2027-01-11 to 2027-01-11

1 1 0% 11-Jan-27 11-Jan-27 11-Jan-27 11-Jan-27 0 0 0
OT030 CRITICAL Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · Dryer section · after OT020
Edit

Predecessors

OT020 FS

Successors

RB01 FS
RB02 FS
RB03 FS
RB04 FS
RB05 FS
RB06 FS
RF01 FS
RF02 FS
RF03 FS
RF04 FS
RF05 FS
RF06 FS
RF07 FS
RF08 FS
RF09 FS
RF10 FS
RF11 FS
RF12 FS
RF13 FS

Progress to the data date

Change the activity

Early 2027-01-12 to 2027-01-13 · late 2027-01-12 to 2027-01-13 · free float 0 · baseline 2027-01-12 to 2027-01-13

2 2 0% 12-Jan-27 13-Jan-27 12-Jan-27 13-Jan-27 0 0 0
5.3 Felt roll removal 2 activities · 2 critical 0% 14-Jan-2714-Jan-27 14-Jan-2714-Jan-27 0
RF01 CRITICAL Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
RF02 CRITICAL Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD02 FS
RD03 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
5.4 Blow box removal 1 activity · 1 critical 0% 14-Jan-2714-Jan-27 14-Jan-2714-Jan-27 0
RB01 CRITICAL Remove blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2027-01-14 to 2027-01-14 · late 2027-01-14 to 2027-01-14 · free float 0 · baseline 2027-01-14 to 2027-01-14

1 1 0% 14-Jan-27 14-Jan-27 14-Jan-27 14-Jan-27 0 0 0
5.6 Dryer removal 14 activities · 14 critical 0% 15-Jan-2721-Jan-27 15-Jan-2721-Jan-27 0
RD01 CRITICAL Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RG01
Edit

Predecessors

RB01 FS
RF01 FS
RG01 FS

Successors

RD03 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 0 0 0
RD02 CRITICAL Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RF02, RG02
Edit

Predecessors

RB01 FS
RF01 FS
RF02 FS
RG02 FS

Successors

RD04 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-15 to 2027-01-15 · late 2027-01-15 to 2027-01-15 · free float 0 · baseline 2027-01-15 to 2027-01-15

1 1 0% 15-Jan-27 15-Jan-27 15-Jan-27 15-Jan-27 0 0 0
RD03 CRITICAL Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD01, RF02, RF03, RG03
Edit

Predecessors

RB02 FS
RD01 FS
RF02 FS
RF03 FS
RG03 FS

Successors

RD05 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 0 0 0
RD04 CRITICAL Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD02, RF03, RF04, RG04
Edit

Predecessors

RB02 FS
RD02 FS
RF03 FS
RF04 FS
RG04 FS

Successors

RD06 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-16 to 2027-01-16 · late 2027-01-16 to 2027-01-16 · free float 0 · baseline 2027-01-16 to 2027-01-16

1 1 0% 16-Jan-27 16-Jan-27 16-Jan-27 16-Jan-27 0 0 0
RD05 CRITICAL Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD03, RF04, RF05, RG05
Edit

Predecessors

RB03 FS
RD03 FS
RF04 FS
RF05 FS
RG05 FS

Successors

RD07 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 0 0 0
RD06 CRITICAL Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD04, RF05, RF06, RG06
Edit

Predecessors

RB03 FS
RD04 FS
RF05 FS
RF06 FS
RG06 FS

Successors

RD08 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-17 to 2027-01-17 · late 2027-01-17 to 2027-01-17 · free float 0 · baseline 2027-01-17 to 2027-01-17

1 1 0% 17-Jan-27 17-Jan-27 17-Jan-27 17-Jan-27 0 0 0
RD07 CRITICAL Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD05, RF06, RF07, RG07
Edit

Predecessors

RB04 FS
RD05 FS
RF06 FS
RF07 FS
RG07 FS

Successors

RD09 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 0 0 0
RD08 CRITICAL Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD06, RF07, RF08, RG08
Edit

Predecessors

RB04 FS
RD06 FS
RF07 FS
RF08 FS
RG08 FS

Successors

RD10 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-18 to 2027-01-18 · late 2027-01-18 to 2027-01-18 · free float 0 · baseline 2027-01-18 to 2027-01-18

1 1 0% 18-Jan-27 18-Jan-27 18-Jan-27 18-Jan-27 0 0 0
RD09 CRITICAL Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD07, RF08, RF09, RG09
Edit

Predecessors

RB05 FS
RD07 FS
RF08 FS
RF09 FS
RG09 FS

Successors

RD11 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 0 0 0
RD10 CRITICAL Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD08, RF09, RF10, RG10
Edit

Predecessors

RB05 FS
RD08 FS
RF09 FS
RF10 FS
RG10 FS

Successors

RD12 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-19 to 2027-01-19 · late 2027-01-19 to 2027-01-19 · free float 0 · baseline 2027-01-19 to 2027-01-19

1 1 0% 19-Jan-27 19-Jan-27 19-Jan-27 19-Jan-27 0 0 0
RD11 CRITICAL Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD09, RF10, RF11, RG11
Edit

Predecessors

RB06 FS
RD09 FS
RF10 FS
RF11 FS
RG11 FS

Successors

RD13 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-20 to 2027-01-20 · late 2027-01-20 to 2027-01-20 · free float 0 · baseline 2027-01-20 to 2027-01-20

1 1 0% 20-Jan-27 20-Jan-27 20-Jan-27 20-Jan-27 0 0 0
RD12 CRITICAL Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD10, RF11, RF12, RG12
Edit

Predecessors

RB06 FS
RD10 FS
RF11 FS
RF12 FS
RG12 FS

Successors

RD14 FS
SV010 FS

Progress to the data date

Change the activity

Early 2027-01-20 to 2027-01-20 · late 2027-01-20 to 2027-01-20 · free float 0 · baseline 2027-01-20 to 2027-01-20

1 1 0% 20-Jan-27 20-Jan-27 20-Jan-27 20-Jan-27 0 0 0
RD13 CRITICAL Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD11, RF12, RF13, RG13
Edit

Predecessors

RB06 FS
RD11 FS
RF12 FS
RF13 FS
RG13 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2027-01-21 to 2027-01-21 · late 2027-01-21 to 2027-01-21 · free float 0 · baseline 2027-01-21 to 2027-01-21

1 1 0% 21-Jan-27 21-Jan-27 21-Jan-27 21-Jan-27 0 0 0
RD14 CRITICAL Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD12, RF13, RG14
Edit

Predecessors

RB06 FS
RD12 FS
RF13 FS
RG14 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2027-01-21 to 2027-01-21 · late 2027-01-21 to 2027-01-21 · free float 0 · baseline 2027-01-21 to 2027-01-21

1 1 0% 21-Jan-27 21-Jan-27 21-Jan-27 21-Jan-27 0 0 0
6 Outage: machining and survey 1 activity · 1 critical 0% 22-Jan-2722-Jan-27 22-Jan-2722-Jan-27 0
6.1 Frame survey 1 activity · 1 critical 0% 22-Jan-2722-Jan-27 22-Jan-2722-Jan-27 0
SV010 CRITICAL Survey the frames after removalSURV · Benchmark Alignment Survey · Dryer section · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020
Edit

Predecessors

RD01 FS
RD02 FS
RD03 FS
RD04 FS
RD05 FS
RD06 FS
RD07 FS
RD08 FS
RD09 FS
RD10 FS
RD11 FS
RD12 FS
RD13 FS
RD14 FS
RM020 FS

Successors

ID01 FS
ID02 FS
ID03 FS
ID04 FS
ID05 FS
ID06 FS
ID07 FS
ID08 FS
ID09 FS
ID10 FS
ID11 FS
ID12 FS
ID13 FS
ID14 FS
IN010 FS

Progress to the data date

Change the activity

Early 2027-01-22 to 2027-01-22 · late 2027-01-22 to 2027-01-22 · free float 0 · baseline 2027-01-22 to 2027-01-22

1 1 0% 22-Jan-27 22-Jan-27 22-Jan-27 22-Jan-27 0 0 0
7 Outage: install 14 activities · 14 critical 0% 23-Jan-2729-Jan-27 23-Jan-2729-Jan-27 0
7.2 Dryer install 14 activities · 14 critical 0% 23-Jan-2729-Jan-27 23-Jan-2729-Jan-27 0
ID01 CRITICAL Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

ID03 FS
IG01 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-23 · late 2027-01-23 to 2027-01-23 · free float 0 · baseline 2027-01-23 to 2027-01-23

1 1 0% 23-Jan-27 23-Jan-27 23-Jan-27 23-Jan-27 0 0 0
ID02 CRITICAL Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

IB01 FS
ID04 FS
IF01 FS
IG02 FS

Progress to the data date

Change the activity

Early 2027-01-23 to 2027-01-23 · late 2027-01-23 to 2027-01-23 · free float 0 · baseline 2027-01-23 to 2027-01-23

1 1 0% 23-Jan-27 23-Jan-27 23-Jan-27 23-Jan-27 0 0 0
ID03 CRITICAL Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID01, SV010
Edit

Predecessors

ID01 FS
SV010 FS

Successors

ID05 FS
IF02 FS
IG03 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-24 to 2027-01-24 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 0 0 0
ID04 CRITICAL Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02, SV010
Edit

Predecessors

ID02 FS
SV010 FS

Successors

IB02 FS
ID06 FS
IF03 FS
IG04 FS

Progress to the data date

Change the activity

Early 2027-01-24 to 2027-01-24 · late 2027-01-24 to 2027-01-24 · free float 0 · baseline 2027-01-24 to 2027-01-24

1 1 0% 24-Jan-27 24-Jan-27 24-Jan-27 24-Jan-27 0 0 0
ID05 CRITICAL Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, SV010
Edit

Predecessors

ID03 FS
SV010 FS

Successors

ID07 FS
IF04 FS
IG05 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-25 to 2027-01-25 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 0 0 0
ID06 CRITICAL Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, SV010
Edit

Predecessors

ID04 FS
SV010 FS

Successors

IB03 FS
ID08 FS
IF05 FS
IG06 FS

Progress to the data date

Change the activity

Early 2027-01-25 to 2027-01-25 · late 2027-01-25 to 2027-01-25 · free float 0 · baseline 2027-01-25 to 2027-01-25

1 1 0% 25-Jan-27 25-Jan-27 25-Jan-27 25-Jan-27 0 0 0
ID07 CRITICAL Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, SV010
Edit

Predecessors

ID05 FS
SV010 FS

Successors

ID09 FS
IF06 FS
IG07 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-26 to 2027-01-26 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 0 0 0
ID08 CRITICAL Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, SV010
Edit

Predecessors

ID06 FS
SV010 FS

Successors

IB04 FS
ID10 FS
IF07 FS
IG08 FS

Progress to the data date

Change the activity

Early 2027-01-26 to 2027-01-26 · late 2027-01-26 to 2027-01-26 · free float 0 · baseline 2027-01-26 to 2027-01-26

1 1 0% 26-Jan-27 26-Jan-27 26-Jan-27 26-Jan-27 0 0 0
ID09 CRITICAL Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, SV010
Edit

Predecessors

ID07 FS
SV010 FS

Successors

ID11 FS
IF08 FS
IG09 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 0 0 0
ID10 CRITICAL Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, SV010
Edit

Predecessors

ID08 FS
SV010 FS

Successors

IB05 FS
ID12 FS
IF09 FS
IG10 FS

Progress to the data date

Change the activity

Early 2027-01-27 to 2027-01-27 · late 2027-01-27 to 2027-01-27 · free float 0 · baseline 2027-01-27 to 2027-01-27

1 1 0% 27-Jan-27 27-Jan-27 27-Jan-27 27-Jan-27 0 0 0
ID11 CRITICAL Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09, SV010
Edit

Predecessors

ID09 FS
SV010 FS

Successors

ID13 FS
IF10 FS
IG11 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 0 0 0
ID12 CRITICAL Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, SV010
Edit

Predecessors

ID10 FS
SV010 FS

Successors

IB06 FS
ID14 FS
IF11 FS
IG12 FS

Progress to the data date

Change the activity

Early 2027-01-28 to 2027-01-28 · late 2027-01-28 to 2027-01-28 · free float 0 · baseline 2027-01-28 to 2027-01-28

1 1 0% 28-Jan-27 28-Jan-27 28-Jan-27 28-Jan-27 0 0 0
ID13 CRITICAL Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, SV010
Edit

Predecessors

ID11 FS
SV010 FS

Successors

IF12 FS
IG13 FS
SY010 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 0 0 0
ID14 CRITICAL Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, SV010
Edit

Predecessors

ID12 FS
SV010 FS

Successors

IF13 FS
IG14 FS
SY010 FS

Progress to the data date

Change the activity

Early 2027-01-29 to 2027-01-29 · late 2027-01-29 to 2027-01-29 · free float 0 · baseline 2027-01-29 to 2027-01-29

1 1 0% 29-Jan-27 29-Jan-27 29-Jan-27 29-Jan-27 0 0 0
8 Outage: systems and checks 5 activities · 5 critical 0% 30-Jan-2709-Feb-27 30-Jan-2709-Feb-27 0
8.1 Steam, condensate and lube 3 activities · 3 critical 0% 30-Jan-2706-Feb-27 30-Jan-2706-Feb-27 0
SY010 CRITICAL Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · Drive side, gear case and basement · after ID13, ID14
Edit

Predecessors

ID13 FS
ID14 FS

Successors

SY020 FS

Progress to the data date

Change the activity

Early 2027-01-30 to 2027-02-02 · late 2027-01-30 to 2027-02-02 · free float 0 · baseline 2027-01-30 to 2027-02-02

4 4 0% 30-Jan-27 02-Feb-27 30-Jan-27 02-Feb-27 0 0 0
SY020 CRITICAL Hydro test dryers and steam jointsQAQC · Drive side, gear case and basement · after SY010
Edit

Predecessors

SY010 FS

Successors

SY030 SS
SY070 FS

Progress to the data date

Change the activity

Early 2027-02-03 to 2027-02-03 · late 2027-02-03 to 2027-02-03 · free float 0 · baseline 2027-02-03 to 2027-02-03

1 1 0% 03-Feb-27 03-Feb-27 03-Feb-27 03-Feb-27 0 0 0
SY070 CRITICAL Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · Drive side, gear case and basement · after SY020
Edit

Predecessors

SY020 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2027-02-04 to 2027-02-06 · late 2027-02-04 to 2027-02-06 · free float 0 · baseline 2027-02-04 to 2027-02-06

3 3 0% 04-Feb-27 06-Feb-27 04-Feb-27 06-Feb-27 0 0 0
8.4 Demobilize and punch walk 2 activities · 2 critical 0% 07-Feb-2709-Feb-27 07-Feb-2709-Feb-27 0
SY080 CRITICAL Strike outage scaffoldingSCAF · Summit Scaffold · Dryer section · after IB06, IF07, IF13, SY060, SY070
Edit

Predecessors

IB06 FS
IF07 FS
IF13 FS
SY060 FS
SY070 FS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2027-02-07 to 2027-02-08 · late 2027-02-07 to 2027-02-08 · free float 0 · baseline 2027-02-07 to 2027-02-08

2 2 0% 07-Feb-27 08-Feb-27 07-Feb-27 08-Feb-27 0 0 0
SY090 CRITICAL Punch walk and pre-startup safety reviewQAQC · Dryer section · after SY030, SY040, SY080
Edit

Predecessors

SY030 FS
SY040 FS
SY080 FS

Successors

SU010 FS

Progress to the data date

Change the activity

Early 2027-02-09 to 2027-02-09 · late 2027-02-09 to 2027-02-09 · free float 0 · baseline 2027-02-09 to 2027-02-09

1 1 0% 09-Feb-27 09-Feb-27 09-Feb-27 09-Feb-27 0 0 0
9 Startup 5 activities · 5 critical 0% 10-Feb-2714-Feb-27 10-Feb-2714-Feb-27 0
SU010 CRITICAL Remove locks and hand the machine back to operationsCOMM · Dryer section · after SY090
Edit

Predecessors

SY090 FS

Successors

SU020 FS

Progress to the data date

Change the activity

Early 2027-02-10 to 2027-02-10 · late 2027-02-10 to 2027-02-10 · free float 0 · baseline 2027-02-10 to 2027-02-10

1 1 0% 10-Feb-27 10-Feb-27 10-Feb-27 10-Feb-27 0 0 0
SU020 CRITICAL Dry run and jog the drivesCOMM · Dryer section · after SU010
Edit

Predecessors

SU010 FS

Successors

SU030 FS

Progress to the data date

Change the activity

Early 2027-02-11 to 2027-02-12 · late 2027-02-11 to 2027-02-12 · free float 0 · baseline 2027-02-11 to 2027-02-12

2 2 0% 11-Feb-27 12-Feb-27 11-Feb-27 12-Feb-27 0 0 0
SU030 CRITICAL Hang new press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after SU020
Edit

Predecessors

SU020 FS

Successors

SU040 FS

Progress to the data date

Change the activity

Early 2027-02-13 to 2027-02-13 · late 2027-02-13 to 2027-02-13 · free float 0 · baseline 2027-02-13 to 2027-02-13

1 1 0% 13-Feb-27 13-Feb-27 13-Feb-27 13-Feb-27 0 0 0
SU040 CRITICAL Steam up and warm the dryersCOMM · Dryer section · after SU030
Edit

Predecessors

SU030 FS

Successors

SU050 FS

Progress to the data date

Change the activity

Early 2027-02-14 to 2027-02-14 · late 2027-02-14 to 2027-02-14 · free float 0 · baseline 2027-02-14 to 2027-02-14

1 1 0% 14-Feb-27 14-Feb-27 14-Feb-27 14-Feb-27 0 0 0
SU050 CRITICAL Paper on the reelCOMM · Dryer section · Finish on or before 2027-02-14 · after SU040
Edit

Predecessors

SU040 FS

Successors

CL010 FS

Progress to the data date

Change the activity

Early 2027-02-14 to 2027-02-14 · late 2027-02-14 to 2027-02-14 · free float 0 · baseline 2027-02-14 to 2027-02-14

MS 0 0% 14-Feb-27 14-Feb-27 14-Feb-27 14-Feb-27 0 0 0
Paper on the reel
10 Performance and turnover 4 activities · 4 critical 0% 15-Feb-2714-Mar-27 15-Feb-2714-Mar-27 0
10.1 Performance run 1 activity · 1 critical 0% 15-Feb-2717-Feb-27 15-Feb-2717-Feb-27 0
CL010 CRITICAL 72-hour performance runCOMM · Dryer section · after SU050
Edit

Predecessors

SU050 FS

Successors

CL020 FS
CL030 FS
CL040 FS

Progress to the data date

Change the activity

Early 2027-02-15 to 2027-02-17 · late 2027-02-15 to 2027-02-17 · free float 0 · baseline 2027-02-15 to 2027-02-17

3 3 0% 15-Feb-27 17-Feb-27 15-Feb-27 17-Feb-27 0 0 0
10.2 Closeout 3 activities · 3 critical 0% 18-Feb-2714-Mar-27 18-Feb-2714-Mar-27 0
CL040 CRITICAL As-built drawings and alignment reportsPMGT · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL050 FS

Progress to the data date

Change the activity

Early 2027-02-18 to 2027-03-04 · late 2027-02-18 to 2027-03-04 · free float 0 · baseline 2027-02-18 to 2027-03-04

15 15 0% 18-Feb-27 04-Mar-27 18-Feb-27 04-Mar-27 0 0 0
CL050 CRITICAL Final cost report and lessons learnedPMGT · Office and engineering · after CL030, CL040
Edit

Predecessors

CL030 FS
CL040 FS

Successors

CL900 FS

Progress to the data date

Change the activity

Early 2027-03-05 to 2027-03-14 · late 2027-03-05 to 2027-03-14 · free float 0 · baseline 2027-03-05 to 2027-03-14

10 10 0% 05-Mar-27 14-Mar-27 05-Mar-27 14-Mar-27 0 0 0
CL900 CRITICAL Project turned overPMGT · Office and engineering · after CL020, CL050
Edit

Predecessors

CL020 FS
CL050 FS

Successors

None

Progress to the data date

Change the activity

Early 2027-03-14 to 2027-03-14 · late 2027-03-14 to 2027-03-14 · free float 0 · baseline 2027-03-14 to 2027-03-14

MS 0 0% 14-Mar-27 14-Mar-27 14-Mar-27 14-Mar-27 0 0 0
Project turned over
Source: activity, activity_rel, baseline_activity, work_calendar, holiday

Add an activity

Run, baseline and publish

Keeps a snapshot. Unfinished activities whose finish moved since the last update go to the delay log for review, and contractors are asked about missed dates.

Work calendar

Non-work days

2026-11-26 Thanksgiving
2026-12-25 Christmas
2027-01-01 New Year's Day