Construction Manager roll-up
Reads the trade boards' registers, not raw sources, so every number matches the trade board it came from.
Is this page current? All feeds OK
CM look-ahead
OK
3 h ago · expected every 24 h
Contractor daily logs
OK
71 min ago · expected every 24 h
Cost report
OK
9 h ago · expected every 7 d
Doc control drawings
OK
51 min ago · expected every 24 h
Meeting records
OK
22 h ago · expected every 7 d
Procurement register
OK
26 h ago · expected every 7 d
Schedule (P6 export)
OK
41 min ago · expected every 24 h
Watch list register
OK
21 min ago · expected every 24 h
Live from the boards updates by itself
- 16:00 · Elena Varga, CM released a client report
- 11:00 · Elena Varga, CM updated the delay log
- 15:00 · Jordan Pike, PM updated changes
- 11:00 · Document Controller loaded a drawing revision
- 16:00 · Jordan Pike, PM updated a meeting
- 10:00 · Elena Varga, CM updated a pay app
- 13:48 · Survey and Layout · Hannah Price added a field log entry
- 13:30 · Dale Whitaker updated schedule progress
- 13:15 · Line Boring and Machining · Wes Turner added a turnover
- 12:58 · R. Okafor updated a lift plan
- 12:40 · Rigging and Heavy Lift · R. Okafor added a watch item
- 12:25 · Millwrights · Dale Whitaker added a field log entry
Source: live_event · every saved change on the project
Trades
| Board | Current | Late activities | Overdue items | Blocked | Needs a decision |
|---|---|---|---|---|---|
| Millwrights Millwright Lead |
OK | 0 | 0 | 0 | None |
| Rigging and Heavy Lift Lift Supervisor |
OK | 0 | 0 | 0 | None |
| Piping Piping Lead |
OK | 0 | 0 | 0 | None |
| Electrical and Instrumentation E&I Lead |
OK | 0 | 0 | 0 | None |
| Scaffolding Scaffold Coordinator |
OK | 0 | 0 | 0 | None |
| Insulation Insulation Lead |
OK | 0 | 0 | 0 | None |
| Concrete Concrete Lead |
OK | 0 | 0 | 0 | None |
| Survey and Layout Survey Lead |
OK | 0 | 0 | 0 | None |
| Welding and QA/QC QA/QC Lead |
OK | 0 | 0 | 0 | None |
| Commissioning Commissioning Lead |
OK | 0 | 0 | 0 | None |
| Line Boring and Machining Line Boring and Machining Lead |
OK | 0 | 0 | 0 | None |
| Project Management and Procurement Project Management and Procurement Lead |
OK | 0 | 0 | 0 | None |
Source: watch_item, activity, feed (same sections as each trade board)
Crane sequence, all trades
| Crane | Trade | Activity | Start | Finish |
|---|
Source: activity
Decision register
2026-10-05 Lessons learned go into the next outage execution plan for PM1; the client keeps the register.
Decided by Meeting: Closeout and Lessons Learned Review · entered by Jordan Pike, PM
2026-10-05 Retainage is released at the end of the 12-month warranty, not at turnover.
Decided by Meeting: Closeout and Lessons Learned Review · entered by Jordan Pike, PM
2026-08-24 Re-bore the FR-02 bearing housing on site rather than wait for a replacement
Decided by Elena Varga, CM · entered by Dale Whitaker · W-102
2026-08-24 BG-03 / IG-05 backlash accepted at 0.46 mm on the gear supplier's letter
Decided by Elena Varga, CM · entered by Dale Whitaker · W-107
2026-08-22 Press roll install starts only after the grout cure check passes
Decided by Carl Mendez, Superintendent · entered by Luis Ortega · W-104
2026-08-22 Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives.
Decided by Meeting: Daily Outage Coordination, day 18 · entered by Dale Whitaker
2026-08-22 Press roll install IN020 starts only after the grout cure check passes.
Decided by Meeting: Daily Outage Coordination, day 18 · entered by R. Okafor
2026-08-20 Set BB-2 on its supports and continue BB-3 to BB-6; bolt BB-2 up when the adapter arrives
Decided by Elena Varga, CM · entered by Dale Whitaker · W-101
2026-08-15 Line Boring and Machining runs IB-3 to IB-5 on nights so the idler gears keep their dates.
Decided by Meeting: Weekly Outage Coordination, day 11 · entered by Wes Turner
2026-08-15 The machine room crane sets the blow boxes; no second mobile crane day (change order CO-004).
Decided by Meeting: Weekly Outage Coordination, day 11 · entered by R. Okafor
Source: decision
Shift turnovers, all trades
| Shift | Trade | Lead | Contractor | Verdict |
|---|---|---|---|---|
| 2026-09-03 DAYS | QAQC | Punch walk done; 41 items, none holding startup | Mechanically complete | AGREE |
| 2026-08-28 NIGHTS | MILL | BB-6 set and bolted | Blow boxes complete | AGREE |
| 2026-08-27 DAYS | RIG | Press rolls in; crane released after IN020 | Press install complete | AGREE |
| 2026-08-24 DAYS | MILL | D-13, D-14 set; IG-25 to IG-27 installed | Dryer install complete | AGREE |
| 2026-08-23 NIGHTS | MILL | D-13/D-14 rigging laid out, gears BG-11/BG-12 staged | Dryers D-13, D-14 started | awaiting lead |
| 2026-08-22 NIGHTS | MECH | IB-5 final bore done, report to follow | Line boring complete | AGREE |
| 2026-08-22 DAYS | MILL | D-11 and D-12 set; BB-2 on supports, not bolted | D-11, D-12, BB-2 complete | DISAGREE |
| 2026-08-22 DAYS | RIG | Press frames set; crane re-rigged for rolls | Press frames complete | AGREE |
Source: shift_turnover