XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Commissioning ?

Trade lead: Nina Brooks, Owner Commissioning · Everything saved here shows live on the PM and CM screens.

Owner: Commissioning Lead · Readers: Construction Manager, Project Manager · Trades: COMM · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
1.03
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
1 / 1
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $600,000 · approved changes $0 · revised $600,000 · pending $0 · back-charges open $0 · value returned $0

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

DECISION Retainage is released at the end of the 12-month warranty, not at turnover. in decision register · Closeout and Lessons Learned Review 2026-10-05, line 21

ACTION [Grant Fowler] Hand the signed turnover package index TO-PKG-01 to the client by 2026-10-06. watch item MTG-4-28 · Closeout and Lessons Learned Review 2026-10-05, line 25

DATE Paper on the reel holds 2026-09-08 (SU050). watch item MTG-2-18 · Weekly Outage Coordination, day 11 2026-08-15, line 22

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
CX-4000-01Startup, dry run and steam-up procedure 11 CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
CX-4000-01Startup, dry run and steam-up procedure1 COMM2026-08-09Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

2026-09-08 Paper on the reel

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
COMM-10.1-A2010.1 · A20$225,000$225,000$218,200$218,200
COMM-9-A209 · A20$375,000$375,000$363,800$363,800
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
Source: daily_log

Shift turnover

No turnovers.

Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-09-21 Steam-up walk-down: all vents and drains confirmed with operations. Referred to Site Safety Lead

2026-09-11 Steam-up walk-down: all vents and drains confirmed with operations. Referred to Site Safety Lead

2026-09-06 Steam-up walk-down: all vents and drains confirmed with operations. Referred to Site Safety Lead

2026-09-01 Steam-up walk-down: all vents and drains confirmed with operations. Referred to Site Safety Lead

2026-08-27 Steam-up walk-down: all vents and drains confirmed with operations. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • System turnover package
  • Pre-commissioning checklist
  • Punch list walkdown
Source: board settings