Schedule
The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.
Data date
2026-10-21
Source: project
Project finish calc
2026-10-07
early finish of the last activity
Source: activity
Against baseline calc
1 d late
baseline 2026-10-06, set 2025-12-17 by Jordan Pike, PM
Source: baseline_activity
Critical activities
0
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-22 13:35
by Jordan Pike, PM
Source: schedule_run
| Activity | Orig dur | Rem dur | % comp | Start | Finish | BL start | BL finish | Total float calc | Free float | vs BL | Dec 2025Jan 2026Feb 2026Mar 2026Apr 2026May 2026Jun 2026Jul 2026Aug 2026Sep 2026Oct 2026 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 Award and preconstruction 5 activities · 5 complete | 100% | 26-Nov-25 | 20-Dec-25 | 26-Nov-25 | 20-Dec-25 | 0 | |||||
| 1.1 Award and contracts 3 activities · 3 complete | 100% | 26-Nov-25 | 13-Dec-25 | 26-Nov-25 | 13-Dec-25 | 0 | |||||
| PC010 COMPLETE Kickoff meeting and scope walk with the millPMGT · Office and engineering · after PO000 | 2 | 0 | 100% | 26-Nov-25 A | 28-Nov-25 A | 26-Nov-25 | 28-Nov-25 | done | 0 | ||
| PO000 COMPLETE Purchase order receivedPMGT · Office and engineering · Must start on 2025-11-26 | MS | 0 | 100% | 26-Nov-25 A | 26-Nov-25 A | 26-Nov-25 | 26-Nov-25 | done | 0 |
Purchase order received
|
|
| PC030 COMPLETE Award millwright, rigging, line boring, piping, E&I, scaffold and insulationPMGT · Office and engineering · after PC010 | 15 | 0 | 100% | 29-Nov-25 A | 13-Dec-25 A | 29-Nov-25 | 13-Dec-25 | done | 0 | ||
| 1.2 Safety and outage planning 2 activities · 2 complete | 100% | 29-Nov-25 | 20-Dec-25 | 29-Nov-25 | 20-Dec-25 | 0 | |||||
| PC020 COMPLETE Site safety plan, JHAs and outage lift plan approvedPMGT · Office and engineering · after PC010 | 10 | 0 | 100% | 29-Nov-25 A | 08-Dec-25 A | 29-Nov-25 | 08-Dec-25 | done | 0 | ||
| PC040 COMPLETE Baseline schedule and outage plan approved by the millPMGT · Office and engineering · after PC030 | 7 | 0 | 100% | 14-Dec-25 A | 20-Dec-25 A | 14-Dec-25 | 20-Dec-25 | done | 0 | ||
| 2 Engineering 8 activities · 8 complete | 100% | 29-Nov-25 | 14-Jan-26 | 29-Nov-25 | 14-Jan-26 | 0 | |||||
| 2.1 Mechanical design and lift plans 5 activities · 5 complete | 100% | 29-Nov-25 | 14-Jan-26 | 29-Nov-25 | 14-Jan-26 | 0 | |||||
| EN010 COMPLETE Press section design and approval drawings (OEM)PMGT · Office and engineering · after PC010 | 45 | 0 | 100% | 29-Nov-25 A | 14-Jan-26 A | 29-Nov-25 | 14-Jan-26 | done | 0 | ||
| EN030 COMPLETE Gear train review: 14 bull gears and 27 idler gearsMILL · Northfield Millwright Services · Office and engineering · after PC030 | 15 | 0 | 100% | 29-Nov-25 A | 13-Dec-25 A | 29-Nov-25 | 13-Dec-25 | done | 0 | ||
| EN020 COMPLETE Laser scan and survey of the existing dryer sectionSURV · Benchmark Alignment Survey · Dryer section · after PC010 | 4 | 0 | 100% | 09-Dec-25 A | 12-Dec-25 A | 09-Dec-25 | 12-Dec-25 | done | 0 | ||
| EN040 COMPLETE Line bore and sleeve procedure for 5 idler bearing boresMECH · Precision Line Boring Co · Office and engineering · after PC030 | 7 | 0 | 100% | 14-Dec-25 A | 20-Dec-25 A | 14-Dec-25 | 20-Dec-25 | done | 0 | ||
| EN050 COMPLETE Lift plans: press section, dryers, gears, rollsRIG · Apex Rigging and Crane · Office and engineering · after PC030 | 12 | 0 | 100% | 14-Dec-25 A | 26-Dec-25 A | 14-Dec-25 | 26-Dec-25 | done | 0 | ||
| 2.2 Piping and E&I design 2 activities · 2 complete | 100% | 04-Dec-25 | 29-Dec-25 | 04-Dec-25 | 29-Dec-25 | 0 | |||||
| EN070 COMPLETE Drive, controls and instrument designEI · Delta Electric and Controls · Office and engineering · after PC030 | 20 | 0 | 100% | 04-Dec-25 A | 23-Dec-25 A | 04-Dec-25 | 23-Dec-25 | done | 0 | ||
| EN060 COMPLETE Steam joint, syphon and condensate piping isometricsPIPE · Ironwood Piping · Office and engineering · after EN020, PC030 | 15 | 0 | 100% | 14-Dec-25 A | 29-Dec-25 A | 14-Dec-25 | 29-Dec-25 | done | 0 | ||
| 2.3 Quality plans 1 activity · 1 complete | 100% | 19-Dec-25 | 24-Dec-25 | 19-Dec-25 | 24-Dec-25 | 0 | |||||
| EN080 COMPLETE Inspection and test plans approvedQAQC · Office and engineering · after EN010 | 6 | 0 | 100% | 19-Dec-25 A | 24-Dec-25 A | 19-Dec-25 | 24-Dec-25 | done | 0 | ||
| 3 Procurement and fabrication 12 activities · 12 complete | 100% | 13-Dec-25 | 08-Jul-26 | 13-Dec-25 | 29-Jun-26 | -9 | |||||
| 3.1 New press section 3 activities · 3 complete | 100% | 15-Jan-26 | 08-Jul-26 | 15-Jan-26 | 29-Jun-26 | -9 | |||||
| FB010 COMPLETE Fabricate new press section (OEM)PMGT · Shops, fabrication and laydown · after EN010 | 150 | 0 | 100% | 15-Jan-26 A | 22-Jun-26 A | 15-Jan-26 | 13-Jun-26 | done | -9 | ||
| FB020 COMPLETE Press section factory acceptance testQAQC · Shops, fabrication and laydown · after FB010 | 4 | 0 | 100% | 23-Jun-26 A | 26-Jun-26 A | 14-Jun-26 | 17-Jun-26 | done | -9 | ||
| FB030 COMPLETE Ship press section to the millPMGT · Shops, fabrication and laydown · after FB020 | 12 | 0 | 100% | 27-Jun-26 A | 08-Jul-26 A | 18-Jun-26 | 29-Jun-26 | done | -9 | ||
| 3.2 Dryer cans 3 activities · 3 complete | 100% | 13-Dec-25 | 06-May-26 | 13-Dec-25 | 06-May-26 | 0 | |||||
| FB040 COMPLETE Fabricate 14 dryer cansPMGT · Shops, fabrication and laydown · after EN020 | 130 | 0 | 100% | 13-Dec-25 A | 23-Apr-26 A | 13-Dec-25 | 23-Apr-26 | done | 0 | ||
| FB045 COMPLETE Dryer pressure vessel inspection and code stampsQAQC · Shops, fabrication and laydown · after FB040 | 5 | 0 | 100% | 24-Apr-26 A | 28-Apr-26 A | 24-Apr-26 | 28-Apr-26 | done | 0 | ||
| FB050 COMPLETE Ship 14 dryersPMGT · Shops, fabrication and laydown · after FB045 | 8 | 0 | 100% | 29-Apr-26 A | 06-May-26 A | 29-Apr-26 | 06-May-26 | done | 0 | ||
| 3.3 Gear train 2 activities · 2 complete | 100% | 14-Dec-25 | 25-Mar-26 | 14-Dec-25 | 25-Mar-26 | 0 | |||||
| FB060 COMPLETE Machine 14 bull gearsPMGT · Shops, fabrication and laydown · after EN030 | 100 | 0 | 100% | 14-Dec-25 A | 25-Mar-26 A | 14-Dec-25 | 25-Mar-26 | done | 0 | ||
| FB070 COMPLETE Machine 27 idler gearsPMGT · Shops, fabrication and laydown · after EN030 | 90 | 0 | 100% | 14-Dec-25 A | 15-Mar-26 A | 14-Dec-25 | 15-Mar-26 | done | 0 | ||
| 3.4 Felt rolls, blow boxes and bearings 3 activities · 3 complete | 100% | 13-Dec-25 | 04-Mar-26 | 13-Dec-25 | 04-Mar-26 | 0 | |||||
| FB080 COMPLETE Fabricate and balance 13 felt rollsPMGT · Shops, fabrication and laydown · after EN020 | 80 | 0 | 100% | 13-Dec-25 A | 04-Mar-26 A | 13-Dec-25 | 04-Mar-26 | done | 0 | ||
| FB090 COMPLETE Fabricate 6 blow boxesPMGT · Shops, fabrication and laydown · after EN020 | 70 | 0 | 100% | 13-Dec-25 A | 22-Feb-26 A | 13-Dec-25 | 22-Feb-26 | done | 0 | ||
| FB100 COMPLETE Bearings, bore sleeves and housingsPMGT · Shops, fabrication and laydown · after EN040 | 60 | 0 | 100% | 21-Dec-25 A | 20-Feb-26 A | 21-Dec-25 | 20-Feb-26 | done | 0 | ||
| 3.5 Receiving and staging 1 activity · 1 complete | 100% | 01-Jul-26 | 08-Jul-26 | 22-Jun-26 | 29-Jun-26 | -9 | |||||
| FB110 COMPLETE Receive, inspect and stage all equipment at the laydownMILL · Northfield Millwright Services · Shops, fabrication and laydown · after FB030, FB050, FB060, FB070, FB080, FB090, FB100 | 8 | 0 | 100% | 01-Jul-26 A | 08-Jul-26 A | 22-Jun-26 | 29-Jun-26 | done | -9 | ||
| 4 Pre-outage, machine running 8 activities · 8 complete | 100% | 13-Dec-25 | 31-Jul-26 | 13-Dec-25 | 31-Jul-26 | 0 | |||||
| 4.1 Site setup and readiness 4 activities · 4 complete | 100% | 20-Jun-26 | 31-Jul-26 | 20-Jun-26 | 31-Jul-26 | 0 | |||||
| PR010 COMPLETE Set up laydown, staging and outage trailersMILL · Northfield Millwright Services · Shops, fabrication and laydown · Start on or after 2026-06-20 · after PC040 | 5 | 0 | 100% | 20-Jun-26 A | 24-Jun-26 A | 20-Jun-26 | 24-Jun-26 | done | 0 | ||
| PR020 COMPLETE Scaffold design and pre-build of outage scaffoldsSCAF · Summit Scaffold · Shops, fabrication and laydown · Start on or after 2026-07-05 · after EN050 | 10 | 0 | 100% | 05-Jul-26 A | 14-Jul-26 A | 05-Jul-26 | 14-Jul-26 | done | 0 | ||
| PR070 COMPLETE Outage safety stand-down and site orientation, all crewsPMGT · Office and engineering · Start on or after 2026-07-31 | 1 | 0 | 100% | 31-Jul-26 A | 31-Jul-26 A | 31-Jul-26 | 31-Jul-26 | done | 0 | ||
| PR080 COMPLETE Outage readiness review with the millPMGT · Office and engineering · after EN080, FB110, PC020, PR010, PR020, PR030, PR040, PR050, PR060, PR070 | 1 | 0 | 100% | 31-Jul-26 A | 31-Jul-26 A | 31-Jul-26 | 31-Jul-26 | done | 0 | ||
| 4.2 Prefabrication and cable 2 activities · 2 complete | 100% | 24-Dec-25 | 27-Jan-26 | 24-Dec-25 | 24-Jan-26 | -3 | |||||
| PR040 COMPLETE Pull new drive and instrument cables to the MCCEI · Delta Electric and Controls · Drive side, gear case and basement · after EN070 | 12 | 0 | 100% | 24-Dec-25 A | 06-Jan-26 A | 24-Dec-25 | 06-Jan-26 | done | 0 | ||
| PR030 COMPLETE Prefabricate steam, condensate and syphon spoolsPIPE · Ironwood Piping · Shops, fabrication and laydown · after EN060 | 25 | 0 | 100% | 30-Dec-25 A | 27-Jan-26 A | 30-Dec-25 | 24-Jan-26 | done | -3 | ||
| 4.3 Crane and survey control 2 activities · 2 complete | 100% | 13-Dec-25 | 15-Jul-26 | 13-Dec-25 | 15-Jul-26 | 0 | |||||
| PR060 COMPLETE Set survey control network and baselinesSURV · Benchmark Alignment Survey · Dryer section · after EN020 | 3 | 0 | 100% | 13-Dec-25 A | 15-Dec-25 A | 13-Dec-25 | 15-Dec-25 | done | 0 | ||
| PR050 COMPLETE Machine room crane inspection and load testRIG · Apex Rigging and Crane · Dryer section · Start on or after 2026-07-14 · after EN050 | 2 | 0 | 100% | 14-Jul-26 A | 15-Jul-26 A | 14-Jul-26 | 15-Jul-26 | done | 0 | ||
| 5 Outage: shut down and remove 55 activities · 55 complete | 100% | 04-Aug-26 | 15-Aug-26 | 04-Aug-26 | 15-Aug-26 | 0 | |||||
| 5.1 Shutdown, lockout and disconnect 6 activities · 6 complete | 100% | 04-Aug-26 | 07-Aug-26 | 04-Aug-26 | 07-Aug-26 | 0 | |||||
| OT000 COMPLETE Machine down: last paper off the reelPMGT · Dryer section · Must start on 2026-08-04 · after PR080 | MS | 0 | 100% | 04-Aug-26 A | 04-Aug-26 A | 04-Aug-26 | 04-Aug-26 | done | 0 |
Machine down: last paper off the reel
|
|
| OT010 COMPLETE Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · Dryer section · after OT000 | 1 | 0 | 100% | 04-Aug-26 A | 04-Aug-26 A | 04-Aug-26 | 04-Aug-26 | done | 0 | ||
| OT020 COMPLETE Remove press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after OT010 | 1 | 0 | 100% | 05-Aug-26 A | 05-Aug-26 A | 05-Aug-26 | 05-Aug-26 | done | 0 | ||
| OT040 COMPLETE Disconnect steam, condensate and lube oilPIPE · Ironwood Piping · Drive side, gear case and basement · after OT010 | 2 | 0 | 100% | 05-Aug-26 A | 06-Aug-26 A | 05-Aug-26 | 06-Aug-26 | done | 0 | ||
| OT050 COMPLETE Disconnect drives and instrumentsEI · Delta Electric and Controls · Drive side, gear case and basement · after OT010 | 1 | 0 | 100% | 05-Aug-26 A | 05-Aug-26 A | 05-Aug-26 | 05-Aug-26 | done | 0 | ||
| OT030 COMPLETE Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · Dryer section · after OT020 | 2 | 0 | 100% | 06-Aug-26 A | 07-Aug-26 A | 06-Aug-26 | 07-Aug-26 | done | 0 | ||
| 5.2 Press section removal 2 activities · 2 complete | 100% | 06-Aug-26 | 11-Aug-26 | 06-Aug-26 | 10-Aug-26 | -1 | |||||
| RM010 COMPLETE Remove the old press section: rolls and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after OT020 | 3 | 0 | 100% | 06-Aug-26 A | 08-Aug-26 A | 06-Aug-26 | 08-Aug-26 | done | 0 | ||
| RM020 COMPLETE Remove press section frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after RM010 | 2 | 0 | 100% | 09-Aug-26 A | 11-Aug-26 A | 09-Aug-26 | 10-Aug-26 | done | -1 | ||
| 5.3 Felt roll removal 13 activities · 13 complete | 100% | 08-Aug-26 | 08-Aug-26 | 08-Aug-26 | 08-Aug-26 | 0 | |||||
| RF01 COMPLETE Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF02 COMPLETE Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF03 COMPLETE Remove felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF04 COMPLETE Remove felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF05 COMPLETE Remove felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF06 COMPLETE Remove felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF07 COMPLETE Remove felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF08 COMPLETE Remove felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF09 COMPLETE Remove felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF10 COMPLETE Remove felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF11 COMPLETE Remove felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF12 COMPLETE Remove felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RF13 COMPLETE Remove felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| 5.4 Blow box removal 6 activities · 6 complete | 100% | 08-Aug-26 | 08-Aug-26 | 08-Aug-26 | 08-Aug-26 | 0 | |||||
| RB01 COMPLETE Remove blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RB02 COMPLETE Remove blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RB03 COMPLETE Remove blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RB04 COMPLETE Remove blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RB05 COMPLETE Remove blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RB06 COMPLETE Remove blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| 5.5 Bull and idler gear removal 14 activities · 14 complete | 100% | 07-Aug-26 | 13-Aug-26 | 07-Aug-26 | 13-Aug-26 | 0 | |||||
| RG01 COMPLETE Remove bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040 | 1 | 0 | 100% | 07-Aug-26 A | 07-Aug-26 A | 07-Aug-26 | 07-Aug-26 | done | 0 | ||
| RG02 COMPLETE Remove bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040 | 1 | 0 | 100% | 07-Aug-26 A | 07-Aug-26 A | 07-Aug-26 | 07-Aug-26 | done | 0 | ||
| RG03 COMPLETE Remove bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG01 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RG04 COMPLETE Remove bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG02 | 1 | 0 | 100% | 08-Aug-26 A | 08-Aug-26 A | 08-Aug-26 | 08-Aug-26 | done | 0 | ||
| RG05 COMPLETE Remove bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG03 | 1 | 0 | 100% | 09-Aug-26 A | 09-Aug-26 A | 09-Aug-26 | 09-Aug-26 | done | 0 | ||
| RG06 COMPLETE Remove bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG04 | 1 | 0 | 100% | 09-Aug-26 A | 09-Aug-26 A | 09-Aug-26 | 09-Aug-26 | done | 0 | ||
| RG07 COMPLETE Remove bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG05 | 1 | 0 | 100% | 10-Aug-26 A | 10-Aug-26 A | 10-Aug-26 | 10-Aug-26 | done | 0 | ||
| RG08 COMPLETE Remove bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG06 | 1 | 0 | 100% | 10-Aug-26 A | 10-Aug-26 A | 10-Aug-26 | 10-Aug-26 | done | 0 | ||
| RG09 COMPLETE Remove bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG07 | 1 | 0 | 100% | 11-Aug-26 A | 11-Aug-26 A | 11-Aug-26 | 11-Aug-26 | done | 0 | ||
| RG10 COMPLETE Remove bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG08 | 1 | 0 | 100% | 11-Aug-26 A | 11-Aug-26 A | 11-Aug-26 | 11-Aug-26 | done | 0 | ||
| RG11 COMPLETE Remove bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG09 | 1 | 0 | 100% | 12-Aug-26 A | 12-Aug-26 A | 12-Aug-26 | 12-Aug-26 | done | 0 | ||
| RG12 COMPLETE Remove bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG10 | 1 | 0 | 100% | 12-Aug-26 A | 12-Aug-26 A | 12-Aug-26 | 12-Aug-26 | done | 0 | ||
| RG13 COMPLETE Remove bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG11 | 1 | 0 | 100% | 13-Aug-26 A | 13-Aug-26 A | 13-Aug-26 | 13-Aug-26 | done | 0 | ||
| RG14 COMPLETE Remove bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after OT040, RG12 | 1 | 0 | 100% | 13-Aug-26 A | 13-Aug-26 A | 13-Aug-26 | 13-Aug-26 | done | 0 | ||
| 5.6 Dryer removal 14 activities · 14 complete | 100% | 09-Aug-26 | 15-Aug-26 | 09-Aug-26 | 15-Aug-26 | 0 | |||||
| RD01 COMPLETE Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RG01 | 1 | 0 | 100% | 09-Aug-26 A | 09-Aug-26 A | 09-Aug-26 | 09-Aug-26 | done | 0 | ||
| RD02 COMPLETE Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RF02, RG02 | 1 | 0 | 100% | 09-Aug-26 A | 09-Aug-26 A | 09-Aug-26 | 09-Aug-26 | done | 0 | ||
| RD03 COMPLETE Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD01, RF02, RF03, RG03 | 1 | 0 | 100% | 10-Aug-26 A | 10-Aug-26 A | 10-Aug-26 | 10-Aug-26 | done | 0 | ||
| RD04 COMPLETE Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD02, RF03, RF04, RG04 | 1 | 0 | 100% | 10-Aug-26 A | 10-Aug-26 A | 10-Aug-26 | 10-Aug-26 | done | 0 | ||
| RD05 COMPLETE Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD03, RF04, RF05, RG05 | 1 | 0 | 100% | 11-Aug-26 A | 11-Aug-26 A | 11-Aug-26 | 11-Aug-26 | done | 0 | ||
| RD06 COMPLETE Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD04, RF05, RF06, RG06 | 1 | 0 | 100% | 11-Aug-26 A | 11-Aug-26 A | 11-Aug-26 | 11-Aug-26 | done | 0 | ||
| RD07 COMPLETE Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD05, RF06, RF07, RG07 | 1 | 0 | 100% | 12-Aug-26 A | 12-Aug-26 A | 12-Aug-26 | 12-Aug-26 | done | 0 | ||
| RD08 COMPLETE Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD06, RF07, RF08, RG08 | 1 | 0 | 100% | 12-Aug-26 A | 12-Aug-26 A | 12-Aug-26 | 12-Aug-26 | done | 0 | ||
| RD09 COMPLETE Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD07, RF08, RF09, RG09 | 1 | 0 | 100% | 13-Aug-26 A | 13-Aug-26 A | 13-Aug-26 | 13-Aug-26 | done | 0 | ||
| RD10 COMPLETE Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD08, RF09, RF10, RG10 | 1 | 0 | 100% | 13-Aug-26 A | 13-Aug-26 A | 13-Aug-26 | 13-Aug-26 | done | 0 | ||
| RD11 COMPLETE Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD09, RF10, RF11, RG11 | 1 | 0 | 100% | 14-Aug-26 A | 14-Aug-26 A | 14-Aug-26 | 14-Aug-26 | done | 0 | ||
| RD12 COMPLETE Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD10, RF11, RF12, RG12 | 1 | 0 | 100% | 14-Aug-26 A | 14-Aug-26 A | 14-Aug-26 | 14-Aug-26 | done | 0 | ||
| RD13 COMPLETE Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD11, RF12, RF13, RG13 | 1 | 0 | 100% | 15-Aug-26 A | 15-Aug-26 A | 15-Aug-26 | 15-Aug-26 | done | 0 | ||
| RD14 COMPLETE Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD12, RF13, RG14 | 1 | 0 | 100% | 15-Aug-26 A | 15-Aug-26 A | 15-Aug-26 | 15-Aug-26 | done | 0 | ||
| 6 Outage: machining and survey 6 activities · 6 complete | 100% | 09-Aug-26 | 19-Aug-26 | 09-Aug-26 | 18-Aug-26 | -1 | |||||
| 6.1 Frame survey 1 activity · 1 complete | 100% | 16-Aug-26 | 16-Aug-26 | 16-Aug-26 | 16-Aug-26 | 0 | |||||
| SV010 COMPLETE Survey the frames after removalSURV · Benchmark Alignment Survey · Dryer section · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020 | 1 | 0 | 100% | 16-Aug-26 A | 16-Aug-26 A | 16-Aug-26 | 16-Aug-26 | done | 0 | ||
| 6.2 Line bore and sleeve idler bores 5 activities · 5 complete | 100% | 09-Aug-26 | 19-Aug-26 | 09-Aug-26 | 18-Aug-26 | -1 | |||||
| LB01 COMPLETE Line bore and sleeve idler bearing bore IB-1MECH · Precision Line Boring Co · Drive side, gear case and basement · after RG03 | 2 | 0 | 100% | 09-Aug-26 A | 10-Aug-26 A | 09-Aug-26 | 10-Aug-26 | done | 0 | ||
| LB02 COMPLETE Line bore and sleeve idler bearing bore IB-2MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB01, RG06 | 2 | 0 | 100% | 11-Aug-26 A | 13-Aug-26 A | 11-Aug-26 | 12-Aug-26 | done | -1 | ||
| LB03 COMPLETE Line bore and sleeve idler bearing bore IB-3MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB02, RG09 | 2 | 0 | 100% | 14-Aug-26 A | 15-Aug-26 A | 13-Aug-26 | 14-Aug-26 | done | -1 | ||
| LB04 COMPLETE Line bore and sleeve idler bearing bore IB-4MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB03, RG12 | 2 | 0 | 100% | 16-Aug-26 A | 17-Aug-26 A | 15-Aug-26 | 16-Aug-26 | done | -1 | ||
| LB05 COMPLETE Line bore and sleeve idler bearing bore IB-5MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB04, RG14 | 2 | 0 | 100% | 18-Aug-26 A | 19-Aug-26 A | 17-Aug-26 | 18-Aug-26 | done | -1 | ||
| 7 Outage: install 51 activities · 51 complete | 100% | 17-Aug-26 | 30-Aug-26 | 17-Aug-26 | 28-Aug-26 | -2 | |||||
| 7.1 Press section install 4 activities · 4 complete | 100% | 17-Aug-26 | 29-Aug-26 | 17-Aug-26 | 28-Aug-26 | -1 | |||||
| IN010 COMPLETE Set new press frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after SV010 | 3 | 0 | 100% | 17-Aug-26 A | 20-Aug-26 A | 17-Aug-26 | 19-Aug-26 | done | -1 | ||
| IN015 COMPLETE Grout press sole plates and cureCONC · Granite Grout and Concrete · Press section · after IN010 | 3 | 0 | 100% | 21-Aug-26 A | 23-Aug-26 A | 20-Aug-26 | 22-Aug-26 | done | -1 | ||
| IN020 COMPLETE Install press rolls, suction roll and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after IN015 | 4 | 0 | 100% | 24-Aug-26 A | 27-Aug-26 A | 23-Aug-26 | 26-Aug-26 | done | -1 | ||
| IN030 COMPLETE Align the press sectionSURV · Benchmark Alignment Survey · Press section · after IN020 | 2 | 0 | 100% | 28-Aug-26 A | 29-Aug-26 A | 27-Aug-26 | 28-Aug-26 | done | -1 | ||
| 7.2 Dryer install 14 activities · 14 complete | 100% | 17-Aug-26 | 23-Aug-26 | 17-Aug-26 | 23-Aug-26 | 0 | |||||
| ID01 COMPLETE Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010 | 1 | 0 | 100% | 17-Aug-26 A | 17-Aug-26 A | 17-Aug-26 | 17-Aug-26 | done | 0 | ||
| ID02 COMPLETE Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010 | 1 | 0 | 100% | 17-Aug-26 A | 17-Aug-26 A | 17-Aug-26 | 17-Aug-26 | done | 0 | ||
| ID03 COMPLETE Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID01, SV010 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| ID04 COMPLETE Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02, SV010 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| ID05 COMPLETE Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, SV010 | 1 | 0 | 100% | 19-Aug-26 A | 19-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | 0 | ||
| ID06 COMPLETE Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, SV010 | 1 | 0 | 100% | 19-Aug-26 A | 19-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | 0 | ||
| ID07 COMPLETE Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, SV010 | 1 | 0 | 100% | 20-Aug-26 A | 20-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | 0 | ||
| ID08 COMPLETE Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, SV010 | 1 | 0 | 100% | 20-Aug-26 A | 20-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | 0 | ||
| ID09 COMPLETE Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, SV010 | 1 | 0 | 100% | 21-Aug-26 A | 21-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | 0 | ||
| ID10 COMPLETE Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, SV010 | 1 | 0 | 100% | 21-Aug-26 A | 21-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | 0 | ||
| ID11 COMPLETE Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09, SV010 | 1 | 0 | 100% | 22-Aug-26 A | 22-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | 0 | ||
| ID12 COMPLETE Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, SV010 | 1 | 0 | 100% | 22-Aug-26 A | 22-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | 0 | ||
| ID13 COMPLETE Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, SV010 | 1 | 0 | 100% | 23-Aug-26 A | 23-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | 0 | ||
| ID14 COMPLETE Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, SV010 | 1 | 0 | 100% | 23-Aug-26 A | 23-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | 0 | ||
| 7.3 Bull and idler gear install 14 activities · 14 complete | 100% | 18-Aug-26 | 24-Aug-26 | 18-Aug-26 | 24-Aug-26 | 0 | |||||
| IG01 COMPLETE Install bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID01 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| IG02 COMPLETE Install bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID02 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| IG03 COMPLETE Install bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID03, IG01, LB01 | 1 | 0 | 100% | 19-Aug-26 A | 19-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | 0 | ||
| IG04 COMPLETE Install bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID04, IG02 | 1 | 0 | 100% | 19-Aug-26 A | 19-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | 0 | ||
| IG05 COMPLETE Install bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID05, IG03 | 1 | 0 | 100% | 20-Aug-26 A | 20-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | 0 | ||
| IG06 COMPLETE Install bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID06, IG04, LB02 | 1 | 0 | 100% | 20-Aug-26 A | 20-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | 0 | ||
| IG07 COMPLETE Install bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID07, IG05 | 1 | 0 | 100% | 21-Aug-26 A | 21-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | 0 | ||
| IG08 COMPLETE Install bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID08, IG06 | 1 | 0 | 100% | 21-Aug-26 A | 21-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | 0 | ||
| IG09 COMPLETE Install bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID09, IG07, LB03 | 1 | 0 | 100% | 22-Aug-26 A | 22-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | 0 | ||
| IG10 COMPLETE Install bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID10, IG08 | 1 | 0 | 100% | 22-Aug-26 A | 22-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | 0 | ||
| IG11 COMPLETE Install bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID11, IG09 | 1 | 0 | 100% | 23-Aug-26 A | 23-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | 0 | ||
| IG12 COMPLETE Install bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID12, IG10, LB04 | 1 | 0 | 100% | 23-Aug-26 A | 23-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | 0 | ||
| IG13 COMPLETE Install bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID13, IG11 | 1 | 0 | 100% | 24-Aug-26 A | 24-Aug-26 A | 24-Aug-26 | 24-Aug-26 | done | 0 | ||
| IG14 COMPLETE Install bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after ID14, IG12, LB05 | 1 | 0 | 100% | 24-Aug-26 A | 24-Aug-26 A | 24-Aug-26 | 24-Aug-26 | done | 0 | ||
| 7.4 Felt roll install 13 activities · 13 complete | 100% | 18-Aug-26 | 30-Aug-26 | 18-Aug-26 | 27-Aug-26 | -3 | |||||
| IF01 COMPLETE Install felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| IF08 COMPLETE Install felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09 | 1 | 0 | 100% | 22-Aug-26 A | 22-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | 0 | ||
| IF09 COMPLETE Install felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, IF08 | 1 | 0 | 100% | 23-Aug-26 A | 23-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | 0 | ||
| IF02 COMPLETE Install felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, IF01 | 1 | 0 | 100% | 24-Aug-26 A | 24-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | -5 | ||
| IF10 COMPLETE Install felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, IF09 | 1 | 0 | 100% | 24-Aug-26 A | 24-Aug-26 A | 24-Aug-26 | 24-Aug-26 | done | 0 | ||
| IF03 COMPLETE Install felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, IF02 | 1 | 0 | 100% | 25-Aug-26 A | 25-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | -5 | ||
| IF11 COMPLETE Install felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, IF10 | 1 | 0 | 100% | 25-Aug-26 A | 25-Aug-26 A | 25-Aug-26 | 25-Aug-26 | done | 0 | ||
| IF04 COMPLETE Install felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, IF03 | 1 | 0 | 100% | 26-Aug-26 A | 26-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | -5 | ||
| IF12 COMPLETE Install felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID13, IF11 | 1 | 0 | 100% | 26-Aug-26 A | 26-Aug-26 A | 26-Aug-26 | 26-Aug-26 | done | 0 | ||
| IF05 COMPLETE Install felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, IF04 | 1 | 0 | 100% | 27-Aug-26 A | 27-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | -5 | ||
| IF13 COMPLETE Install felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID14, IF12 | 1 | 0 | 100% | 27-Aug-26 A | 27-Aug-26 A | 27-Aug-26 | 27-Aug-26 | done | 0 | ||
| IF06 COMPLETE Install felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, IF05 | 1 | 0 | 100% | 28-Aug-26 A | 28-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | -5 | ||
| IF07 COMPLETE Install felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, IF06 | 1 | 0 | 100% | 29-Aug-26 A | 30-Aug-26 A | 24-Aug-26 | 24-Aug-26 | done | -6 | ||
| 7.5 Blow box install 6 activities · 6 complete | 100% | 18-Aug-26 | 28-Aug-26 | 18-Aug-26 | 23-Aug-26 | -5 | |||||
| IB01 COMPLETE Install blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02 | 1 | 0 | 100% | 18-Aug-26 A | 18-Aug-26 A | 18-Aug-26 | 18-Aug-26 | done | 0 | ||
| IB02 COMPLETE Install blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB01, ID04 | 1 | 0 | 100% | 24-Aug-26 A | 24-Aug-26 A | 19-Aug-26 | 19-Aug-26 | done | -5 | ||
| IB03 COMPLETE Install blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB02, ID06 | 1 | 0 | 100% | 25-Aug-26 A | 25-Aug-26 A | 20-Aug-26 | 20-Aug-26 | done | -5 | ||
| IB04 COMPLETE Install blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB03, ID08 | 1 | 0 | 100% | 26-Aug-26 A | 26-Aug-26 A | 21-Aug-26 | 21-Aug-26 | done | -5 | ||
| IB05 COMPLETE Install blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB04, ID10 | 1 | 0 | 100% | 27-Aug-26 A | 27-Aug-26 A | 22-Aug-26 | 22-Aug-26 | done | -5 | ||
| IB06 COMPLETE Install blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB05, ID12 | 1 | 0 | 100% | 28-Aug-26 A | 28-Aug-26 A | 23-Aug-26 | 23-Aug-26 | done | -5 | ||
| 8 Outage: systems and checks 9 activities · 9 complete | 100% | 24-Aug-26 | 03-Sep-26 | 24-Aug-26 | 03-Sep-26 | 0 | |||||
| 8.1 Steam, condensate and lube 4 activities · 4 complete | 100% | 24-Aug-26 | 31-Aug-26 | 24-Aug-26 | 31-Aug-26 | 0 | |||||
| SY010 COMPLETE Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · Drive side, gear case and basement · after ID13, ID14 | 4 | 0 | 100% | 24-Aug-26 A | 27-Aug-26 A | 24-Aug-26 | 27-Aug-26 | done | 0 | ||
| SY020 COMPLETE Hydro test dryers and steam jointsQAQC · Drive side, gear case and basement · after SY010 | 1 | 0 | 100% | 28-Aug-26 A | 28-Aug-26 A | 28-Aug-26 | 28-Aug-26 | done | 0 | ||
| SY030 COMPLETE Flush the lube oil systemPIPE · Ironwood Piping · Drive side, gear case and basement · after SY020 | 3 | 0 | 100% | 28-Aug-26 A | 30-Aug-26 A | 28-Aug-26 | 30-Aug-26 | done | 0 | ||
| SY070 COMPLETE Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · Drive side, gear case and basement · after SY020 | 3 | 0 | 100% | 29-Aug-26 A | 31-Aug-26 A | 29-Aug-26 | 31-Aug-26 | done | 0 | ||
| 8.2 Drives and instruments 1 activity · 1 complete | 100% | 24-Aug-26 | 26-Aug-26 | 24-Aug-26 | 26-Aug-26 | 0 | |||||
| SY040 COMPLETE Reconnect drives and instruments, loop checkEI · Delta Electric and Controls · Drive side, gear case and basement · after IG14 | 3 | 0 | 100% | 24-Aug-26 A | 26-Aug-26 A | 24-Aug-26 | 26-Aug-26 | done | 0 | ||
| 8.3 Mechanical checks and alignment 2 activities · 2 complete | 100% | 25-Aug-26 | 31-Aug-26 | 25-Aug-26 | 30-Aug-26 | -1 | |||||
| SY050 COMPLETE Gear mesh, backlash and runout checksMILL · Northfield Millwright Services · Drive side, gear case and basement · after IG13, IG14 | 2 | 0 | 100% | 25-Aug-26 A | 26-Aug-26 A | 25-Aug-26 | 26-Aug-26 | done | 0 | ||
| SY060 COMPLETE Final alignment survey: press and dryersSURV · Benchmark Alignment Survey · Dryer section · after IN030, SY050 | 2 | 0 | 100% | 30-Aug-26 A | 31-Aug-26 A | 29-Aug-26 | 30-Aug-26 | done | -1 | ||
| 8.4 Demobilize and punch walk 2 activities · 2 complete | 100% | 01-Sep-26 | 03-Sep-26 | 01-Sep-26 | 03-Sep-26 | 0 | |||||
| SY080 COMPLETE Strike outage scaffoldingSCAF · Summit Scaffold · Dryer section · after IB06, IF07, IF13, SY060, SY070 | 2 | 0 | 100% | 01-Sep-26 A | 02-Sep-26 A | 01-Sep-26 | 02-Sep-26 | done | 0 | ||
| SY090 COMPLETE Punch walk and pre-startup safety reviewQAQC · Dryer section · after SY030, SY040, SY080 | 1 | 0 | 100% | 03-Sep-26 A | 03-Sep-26 A | 03-Sep-26 | 03-Sep-26 | done | 0 | ||
| 9 Startup 5 activities · 5 complete | 100% | 04-Sep-26 | 08-Sep-26 | 04-Sep-26 | 08-Sep-26 | 0 | |||||
| SU010 COMPLETE Remove locks and hand the machine back to operationsCOMM · Dryer section · after SY090 | 1 | 0 | 100% | 04-Sep-26 A | 04-Sep-26 A | 04-Sep-26 | 04-Sep-26 | done | 0 | ||
| SU020 COMPLETE Dry run and jog the drivesCOMM · Dryer section · after SU010 | 2 | 0 | 100% | 05-Sep-26 A | 06-Sep-26 A | 05-Sep-26 | 06-Sep-26 | done | 0 | ||
| SU030 COMPLETE Hang new press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after SU020 | 1 | 0 | 100% | 07-Sep-26 A | 07-Sep-26 A | 07-Sep-26 | 07-Sep-26 | done | 0 | ||
| SU040 COMPLETE Steam up and warm the dryersCOMM · Dryer section · after SU030 | 1 | 0 | 100% | 08-Sep-26 A | 08-Sep-26 A | 08-Sep-26 | 08-Sep-26 | done | 0 | ||
| SU050 COMPLETE Paper on the reelCOMM · Dryer section · Finish on or before 2026-09-08 · after SU040 | MS | 0 | 100% | 08-Sep-26 A | 08-Sep-26 A | 08-Sep-26 | 08-Sep-26 | done | 0 |
Paper on the reel
|
|
| 10 Performance and turnover 6 activities · 6 complete | 100% | 09-Sep-26 | 07-Oct-26 | 09-Sep-26 | 06-Oct-26 | -1 | |||||
| 10.1 Performance run 1 activity · 1 complete | 100% | 09-Sep-26 | 11-Sep-26 | 09-Sep-26 | 11-Sep-26 | 0 | |||||
| CL010 COMPLETE 72-hour performance runCOMM · Dryer section · after SU050 | 3 | 0 | 100% | 09-Sep-26 A | 11-Sep-26 A | 09-Sep-26 | 11-Sep-26 | done | 0 | ||
| 10.2 Closeout 5 activities · 5 complete | 100% | 12-Sep-26 | 07-Oct-26 | 12-Sep-26 | 06-Oct-26 | -1 | |||||
| CL020 COMPLETE Close the punch listQAQC · Office and engineering · after CL010 | 10 | 0 | 100% | 12-Sep-26 A | 21-Sep-26 A | 12-Sep-26 | 21-Sep-26 | done | 0 | ||
| CL030 COMPLETE Turnover packages accepted by the millPMGT · Office and engineering · after CL010 | 10 | 0 | 100% | 12-Sep-26 A | 21-Sep-26 A | 12-Sep-26 | 21-Sep-26 | done | 0 | ||
| CL040 COMPLETE As-built drawings and alignment reportsPMGT · Office and engineering · after CL010 | 15 | 0 | 100% | 12-Sep-26 A | 27-Sep-26 A | 12-Sep-26 | 26-Sep-26 | done | -1 | ||
| CL050 COMPLETE Final cost report and lessons learnedPMGT · Office and engineering · after CL030, CL040 | 10 | 0 | 100% | 28-Sep-26 A | 07-Oct-26 A | 27-Sep-26 | 06-Oct-26 | done | -1 | ||
| CL900 COMPLETE Project turned overPMGT · Office and engineering · after CL020, CL050 | MS | 0 | 100% | 07-Oct-26 A | 07-Oct-26 A | 06-Oct-26 | 06-Oct-26 | done | -1 |
Project turned over
|
Source: activity, activity_rel, baseline_activity, work_calendar, holiday
Add an activity
Run, baseline and publish
Work calendar
Non-work days
2025-11-27 Thanksgiving
2025-12-25 Christmas
2026-01-01 New Year's Day