SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Gantt and activities Schedule check Working over each other

Schedule ?

The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.

Data date
2026-10-21
Source: project
Project finish calc
2026-10-07
early finish of the last activity
Source: activity
Against baseline calc
1 d late
baseline 2026-10-06, set 2025-12-17 by Jordan Pike, PM
Source: baseline_activity
Critical activities
0
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-22 13:35
by Jordan Pike, PM
Source: schedule_run
Critical path 0 Has float 0float bar to late finish In progress 0 Complete 165 Baseline 165 WBS summary Data date 2026-10-21
ActivityOrig durRem dur% compStartFinishBL startBL finishTotal float calcFree floatvs BL
Dec 2025Jan 2026Feb 2026Mar 2026Apr 2026May 2026Jun 2026Jul 2026Aug 2026Sep 2026Oct 2026
1 Award and preconstruction 5 activities · 5 complete 100% 26-Nov-2520-Dec-25 26-Nov-2520-Dec-25 0
1.1 Award and contracts 3 activities · 3 complete 100% 26-Nov-2513-Dec-25 26-Nov-2513-Dec-25 0
PC010 COMPLETE Kickoff meeting and scope walk with the millPMGT · Office and engineering · after PO000
Edit

Predecessors

PO000 FS

Successors

EN010 FS
EN020 FS +10d
PC020 FS
PC030 FS

Progress to the data date

Change the activity

Early 2025-11-26 to 2025-11-28 · late 2025-11-26 to 2025-11-28 · free float · baseline 2025-11-26 to 2025-11-28

2 0 100% 26-Nov-25 A 28-Nov-25 A 26-Nov-25 28-Nov-25 done 0
PO000 COMPLETE Purchase order receivedPMGT · Office and engineering · Must start on 2025-11-26
Edit

Predecessors

None

Successors

PC010 FS

Progress to the data date

Change the activity

Early 2025-11-26 to 2025-11-26 · late 2025-11-26 to 2025-11-26 · free float · baseline 2025-11-26 to 2025-11-26

MS 0 100% 26-Nov-25 A 26-Nov-25 A 26-Nov-25 26-Nov-25 done 0
Purchase order received
PC030 COMPLETE Award millwright, rigging, line boring, piping, E&I, scaffold and insulationPMGT · Office and engineering · after PC010
Edit

Predecessors

PC010 FS

Successors

EN030 SS
EN040 FS
EN050 FS
EN060 FS
EN070 SS +5d
PC040 FS

Progress to the data date

Change the activity

Early 2025-11-29 to 2025-12-13 · late 2025-11-29 to 2025-12-13 · free float · baseline 2025-11-29 to 2025-12-13

15 0 100% 29-Nov-25 A 13-Dec-25 A 29-Nov-25 13-Dec-25 done 0
1.2 Safety and outage planning 2 activities · 2 complete 100% 29-Nov-2520-Dec-25 29-Nov-2520-Dec-25 0
PC020 COMPLETE Site safety plan, JHAs and outage lift plan approvedPMGT · Office and engineering · after PC010
Edit

Predecessors

PC010 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2025-11-29 to 2025-12-08 · late 2025-11-29 to 2025-12-08 · free float · baseline 2025-11-29 to 2025-12-08

10 0 100% 29-Nov-25 A 08-Dec-25 A 29-Nov-25 08-Dec-25 done 0
PC040 COMPLETE Baseline schedule and outage plan approved by the millPMGT · Office and engineering · after PC030
Edit

Predecessors

PC030 FS

Successors

PR010 FS

Progress to the data date

Change the activity

Early 2025-12-14 to 2025-12-20 · late 2025-12-14 to 2025-12-20 · free float · baseline 2025-12-14 to 2025-12-20

7 0 100% 14-Dec-25 A 20-Dec-25 A 14-Dec-25 20-Dec-25 done 0
2 Engineering 8 activities · 8 complete 100% 29-Nov-2514-Jan-26 29-Nov-2514-Jan-26 0
2.1 Mechanical design and lift plans 5 activities · 5 complete 100% 29-Nov-2514-Jan-26 29-Nov-2514-Jan-26 0
EN010 COMPLETE Press section design and approval drawings (OEM)PMGT · Office and engineering · after PC010
Edit

Predecessors

PC010 FS

Successors

EN080 SS +20d
FB010 FS

Progress to the data date

Change the activity

Early 2025-11-29 to 2026-01-14 · late 2025-11-29 to 2026-01-14 · free float · baseline 2025-11-29 to 2026-01-14

45 0 100% 29-Nov-25 A 14-Jan-26 A 29-Nov-25 14-Jan-26 done 0
EN030 COMPLETE Gear train review: 14 bull gears and 27 idler gearsMILL · Northfield Millwright Services · Office and engineering · after PC030
Edit

Predecessors

PC030 SS

Successors

FB060 FS
FB070 FS

Progress to the data date

Change the activity

Early 2025-11-29 to 2025-12-13 · late 2025-11-29 to 2025-12-13 · free float · baseline 2025-11-29 to 2025-12-13

15 0 100% 29-Nov-25 A 13-Dec-25 A 29-Nov-25 13-Dec-25 done 0
EN020 COMPLETE Laser scan and survey of the existing dryer sectionSURV · Benchmark Alignment Survey · Dryer section · after PC010
Edit

Predecessors

PC010 FS +10d

Successors

EN060 SS
FB040 FS
FB080 FS
FB090 FS
PR060 FS

Progress to the data date

Change the activity

Early 2025-12-09 to 2025-12-12 · late 2025-12-09 to 2025-12-12 · free float · baseline 2025-12-09 to 2025-12-12

4 0 100% 09-Dec-25 A 12-Dec-25 A 09-Dec-25 12-Dec-25 done 0
EN040 COMPLETE Line bore and sleeve procedure for 5 idler bearing boresMECH · Precision Line Boring Co · Office and engineering · after PC030
Edit

Predecessors

PC030 FS

Successors

FB100 FS

Progress to the data date

Change the activity

Early 2025-12-14 to 2025-12-20 · late 2025-12-14 to 2025-12-20 · free float · baseline 2025-12-14 to 2025-12-20

7 0 100% 14-Dec-25 A 20-Dec-25 A 14-Dec-25 20-Dec-25 done 0
EN050 COMPLETE Lift plans: press section, dryers, gears, rollsRIG · Apex Rigging and Crane · Office and engineering · after PC030
Edit

Predecessors

PC030 FS

Successors

PR020 FS
PR050 FS

Progress to the data date

Change the activity

Early 2025-12-14 to 2025-12-26 · late 2025-12-14 to 2025-12-26 · free float · baseline 2025-12-14 to 2025-12-26

12 0 100% 14-Dec-25 A 26-Dec-25 A 14-Dec-25 26-Dec-25 done 0
2.2 Piping and E&I design 2 activities · 2 complete 100% 04-Dec-2529-Dec-25 04-Dec-2529-Dec-25 0
EN070 COMPLETE Drive, controls and instrument designEI · Delta Electric and Controls · Office and engineering · after PC030
Edit

Predecessors

PC030 SS +5d

Successors

PR040 FS

Progress to the data date

Change the activity

Early 2025-12-04 to 2025-12-23 · late 2025-12-04 to 2025-12-23 · free float · baseline 2025-12-04 to 2025-12-23

20 0 100% 04-Dec-25 A 23-Dec-25 A 04-Dec-25 23-Dec-25 done 0
EN060 COMPLETE Steam joint, syphon and condensate piping isometricsPIPE · Ironwood Piping · Office and engineering · after EN020, PC030
Edit

Predecessors

EN020 SS
PC030 FS

Successors

PR030 FS

Progress to the data date

Change the activity

Early 2025-12-14 to 2025-12-29 · late 2025-12-14 to 2025-12-29 · free float · baseline 2025-12-14 to 2025-12-29

15 0 100% 14-Dec-25 A 29-Dec-25 A 14-Dec-25 29-Dec-25 done 0
2.3 Quality plans 1 activity · 1 complete 100% 19-Dec-2524-Dec-25 19-Dec-2524-Dec-25 0
EN080 COMPLETE Inspection and test plans approvedQAQC · Office and engineering · after EN010
Edit

Predecessors

EN010 SS +20d

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2025-12-19 to 2025-12-24 · late 2025-12-19 to 2025-12-24 · free float · baseline 2025-12-19 to 2025-12-24

6 0 100% 19-Dec-25 A 24-Dec-25 A 19-Dec-25 24-Dec-25 done 0
3 Procurement and fabrication 12 activities · 12 complete 100% 13-Dec-2508-Jul-26 13-Dec-2529-Jun-26 -9
3.1 New press section 3 activities · 3 complete 100% 15-Jan-2608-Jul-26 15-Jan-2629-Jun-26 -9
FB010 COMPLETE Fabricate new press section (OEM)PMGT · Shops, fabrication and laydown · after EN010
Edit

Predecessors

EN010 FS

Successors

FB020 FS

Progress to the data date

Change the activity

Early 2026-01-15 to 2026-06-22 · late 2026-01-15 to 2026-06-22 · free float · baseline 2026-01-15 to 2026-06-13

150 0 100% 15-Jan-26 A 22-Jun-26 A 15-Jan-26 13-Jun-26 done -9
FB020 COMPLETE Press section factory acceptance testQAQC · Shops, fabrication and laydown · after FB010
Edit

Predecessors

FB010 FS

Successors

FB030 FS

Progress to the data date

Change the activity

Early 2026-06-23 to 2026-06-26 · late 2026-06-23 to 2026-06-26 · free float · baseline 2026-06-14 to 2026-06-17

4 0 100% 23-Jun-26 A 26-Jun-26 A 14-Jun-26 17-Jun-26 done -9
FB030 COMPLETE Ship press section to the millPMGT · Shops, fabrication and laydown · after FB020
Edit

Predecessors

FB020 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2026-06-27 to 2026-07-08 · late 2026-06-27 to 2026-07-08 · free float · baseline 2026-06-18 to 2026-06-29

12 0 100% 27-Jun-26 A 08-Jul-26 A 18-Jun-26 29-Jun-26 done -9
3.2 Dryer cans 3 activities · 3 complete 100% 13-Dec-2506-May-26 13-Dec-2506-May-26 0
FB040 COMPLETE Fabricate 14 dryer cansPMGT · Shops, fabrication and laydown · after EN020
Edit

Predecessors

EN020 FS

Successors

FB045 FS

Progress to the data date

Change the activity

Early 2025-12-13 to 2026-04-23 · late 2025-12-13 to 2026-04-23 · free float · baseline 2025-12-13 to 2026-04-23

130 0 100% 13-Dec-25 A 23-Apr-26 A 13-Dec-25 23-Apr-26 done 0
FB045 COMPLETE Dryer pressure vessel inspection and code stampsQAQC · Shops, fabrication and laydown · after FB040
Edit

Predecessors

FB040 FS

Successors

FB050 FS

Progress to the data date

Change the activity

Early 2026-04-24 to 2026-04-28 · late 2026-04-24 to 2026-04-28 · free float · baseline 2026-04-24 to 2026-04-28

5 0 100% 24-Apr-26 A 28-Apr-26 A 24-Apr-26 28-Apr-26 done 0
FB050 COMPLETE Ship 14 dryersPMGT · Shops, fabrication and laydown · after FB045
Edit

Predecessors

FB045 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2026-04-29 to 2026-05-06 · late 2026-04-29 to 2026-05-06 · free float · baseline 2026-04-29 to 2026-05-06

8 0 100% 29-Apr-26 A 06-May-26 A 29-Apr-26 06-May-26 done 0
3.3 Gear train 2 activities · 2 complete 100% 14-Dec-2525-Mar-26 14-Dec-2525-Mar-26 0
FB060 COMPLETE Machine 14 bull gearsPMGT · Shops, fabrication and laydown · after EN030
Edit

Predecessors

EN030 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2025-12-14 to 2026-03-25 · late 2025-12-14 to 2026-03-25 · free float · baseline 2025-12-14 to 2026-03-25

100 0 100% 14-Dec-25 A 25-Mar-26 A 14-Dec-25 25-Mar-26 done 0
FB070 COMPLETE Machine 27 idler gearsPMGT · Shops, fabrication and laydown · after EN030
Edit

Predecessors

EN030 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2025-12-14 to 2026-03-15 · late 2025-12-14 to 2026-03-15 · free float · baseline 2025-12-14 to 2026-03-15

90 0 100% 14-Dec-25 A 15-Mar-26 A 14-Dec-25 15-Mar-26 done 0
3.4 Felt rolls, blow boxes and bearings 3 activities · 3 complete 100% 13-Dec-2504-Mar-26 13-Dec-2504-Mar-26 0
FB080 COMPLETE Fabricate and balance 13 felt rollsPMGT · Shops, fabrication and laydown · after EN020
Edit

Predecessors

EN020 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2025-12-13 to 2026-03-04 · late 2025-12-13 to 2026-03-04 · free float · baseline 2025-12-13 to 2026-03-04

80 0 100% 13-Dec-25 A 04-Mar-26 A 13-Dec-25 04-Mar-26 done 0
FB090 COMPLETE Fabricate 6 blow boxesPMGT · Shops, fabrication and laydown · after EN020
Edit

Predecessors

EN020 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2025-12-13 to 2026-02-22 · late 2025-12-13 to 2026-02-22 · free float · baseline 2025-12-13 to 2026-02-22

70 0 100% 13-Dec-25 A 22-Feb-26 A 13-Dec-25 22-Feb-26 done 0
FB100 COMPLETE Bearings, bore sleeves and housingsPMGT · Shops, fabrication and laydown · after EN040
Edit

Predecessors

EN040 FS

Successors

FB110 FF

Progress to the data date

Change the activity

Early 2025-12-21 to 2026-02-20 · late 2025-12-21 to 2026-02-20 · free float · baseline 2025-12-21 to 2026-02-20

60 0 100% 21-Dec-25 A 20-Feb-26 A 21-Dec-25 20-Feb-26 done 0
3.5 Receiving and staging 1 activity · 1 complete 100% 01-Jul-2608-Jul-26 22-Jun-2629-Jun-26 -9
FB110 COMPLETE Receive, inspect and stage all equipment at the laydownMILL · Northfield Millwright Services · Shops, fabrication and laydown · after FB030, FB050, FB060, FB070, FB080, FB090, FB100
Edit

Predecessors

FB030 FF
FB050 FF
FB060 FF
FB070 FF
FB080 FF
FB090 FF
FB100 FF

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2026-07-01 to 2026-07-08 · late 2026-07-01 to 2026-07-08 · free float · baseline 2026-06-22 to 2026-06-29

8 0 100% 01-Jul-26 A 08-Jul-26 A 22-Jun-26 29-Jun-26 done -9
4 Pre-outage, machine running 8 activities · 8 complete 100% 13-Dec-2531-Jul-26 13-Dec-2531-Jul-26 0
4.1 Site setup and readiness 4 activities · 4 complete 100% 20-Jun-2631-Jul-26 20-Jun-2631-Jul-26 0
PR010 COMPLETE Set up laydown, staging and outage trailersMILL · Northfield Millwright Services · Shops, fabrication and laydown · Start on or after 2026-06-20 · after PC040
Edit

Predecessors

PC040 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2026-06-20 to 2026-06-24 · late 2026-06-20 to 2026-06-24 · free float · baseline 2026-06-20 to 2026-06-24

5 0 100% 20-Jun-26 A 24-Jun-26 A 20-Jun-26 24-Jun-26 done 0
PR020 COMPLETE Scaffold design and pre-build of outage scaffoldsSCAF · Summit Scaffold · Shops, fabrication and laydown · Start on or after 2026-07-05 · after EN050
Edit

Predecessors

EN050 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2026-07-05 to 2026-07-14 · late 2026-07-05 to 2026-07-14 · free float · baseline 2026-07-05 to 2026-07-14

10 0 100% 05-Jul-26 A 14-Jul-26 A 05-Jul-26 14-Jul-26 done 0
PR070 COMPLETE Outage safety stand-down and site orientation, all crewsPMGT · Office and engineering · Start on or after 2026-07-31
Edit

Predecessors

None

Successors

PR080 FF

Progress to the data date

Change the activity

Early 2026-07-31 to 2026-07-31 · late 2026-07-31 to 2026-07-31 · free float · baseline 2026-07-31 to 2026-07-31

1 0 100% 31-Jul-26 A 31-Jul-26 A 31-Jul-26 31-Jul-26 done 0
PR080 COMPLETE Outage readiness review with the millPMGT · Office and engineering · after EN080, FB110, PC020, PR010, PR020, PR030, PR040, PR050, PR060, PR070
Edit

Predecessors

EN080 FS
FB110 FS
PC020 FS
PR010 FS
PR020 FS
PR030 FS
PR040 FS
PR050 FS
PR060 FS
PR070 FF

Successors

OT000 FS

Progress to the data date

Change the activity

Early 2026-07-31 to 2026-07-31 · late 2026-07-31 to 2026-07-31 · free float · baseline 2026-07-31 to 2026-07-31

1 0 100% 31-Jul-26 A 31-Jul-26 A 31-Jul-26 31-Jul-26 done 0
4.2 Prefabrication and cable 2 activities · 2 complete 100% 24-Dec-2527-Jan-26 24-Dec-2524-Jan-26 -3
PR040 COMPLETE Pull new drive and instrument cables to the MCCEI · Delta Electric and Controls · Drive side, gear case and basement · after EN070
Edit

Predecessors

EN070 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2025-12-24 to 2026-01-06 · late 2025-12-24 to 2026-01-06 · free float · baseline 2025-12-24 to 2026-01-06

12 0 100% 24-Dec-25 A 06-Jan-26 A 24-Dec-25 06-Jan-26 done 0
PR030 COMPLETE Prefabricate steam, condensate and syphon spoolsPIPE · Ironwood Piping · Shops, fabrication and laydown · after EN060
Edit

Predecessors

EN060 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2025-12-30 to 2026-01-27 · late 2025-12-30 to 2026-01-27 · free float · baseline 2025-12-30 to 2026-01-24

25 0 100% 30-Dec-25 A 27-Jan-26 A 30-Dec-25 24-Jan-26 done -3
4.3 Crane and survey control 2 activities · 2 complete 100% 13-Dec-2515-Jul-26 13-Dec-2515-Jul-26 0
PR060 COMPLETE Set survey control network and baselinesSURV · Benchmark Alignment Survey · Dryer section · after EN020
Edit

Predecessors

EN020 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2025-12-13 to 2025-12-15 · late 2025-12-13 to 2025-12-15 · free float · baseline 2025-12-13 to 2025-12-15

3 0 100% 13-Dec-25 A 15-Dec-25 A 13-Dec-25 15-Dec-25 done 0
PR050 COMPLETE Machine room crane inspection and load testRIG · Apex Rigging and Crane · Dryer section · Start on or after 2026-07-14 · after EN050
Edit

Predecessors

EN050 FS

Successors

PR080 FS

Progress to the data date

Change the activity

Early 2026-07-14 to 2026-07-15 · late 2026-07-14 to 2026-07-15 · free float · baseline 2026-07-14 to 2026-07-15

2 0 100% 14-Jul-26 A 15-Jul-26 A 14-Jul-26 15-Jul-26 done 0
5 Outage: shut down and remove 55 activities · 55 complete 100% 04-Aug-2615-Aug-26 04-Aug-2615-Aug-26 0
5.1 Shutdown, lockout and disconnect 6 activities · 6 complete 100% 04-Aug-2607-Aug-26 04-Aug-2607-Aug-26 0
OT000 COMPLETE Machine down: last paper off the reelPMGT · Dryer section · Must start on 2026-08-04 · after PR080
Edit

Predecessors

PR080 FS

Successors

OT010 FS

Progress to the data date

Change the activity

Early 2026-08-04 to 2026-08-04 · late 2026-08-04 to 2026-08-04 · free float · baseline 2026-08-04 to 2026-08-04

MS 0 100% 04-Aug-26 A 04-Aug-26 A 04-Aug-26 04-Aug-26 done 0
Machine down: last paper off the reel
OT010 COMPLETE Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · Dryer section · after OT000
Edit

Predecessors

OT000 FS

Successors

OT020 FS
OT040 FS
OT050 FS

Progress to the data date

Change the activity

Early 2026-08-04 to 2026-08-04 · late 2026-08-04 to 2026-08-04 · free float · baseline 2026-08-04 to 2026-08-04

1 0 100% 04-Aug-26 A 04-Aug-26 A 04-Aug-26 04-Aug-26 done 0
OT020 COMPLETE Remove press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after OT010
Edit

Predecessors

OT010 FS

Successors

OT030 FS
RM010 FS

Progress to the data date

Change the activity

Early 2026-08-05 to 2026-08-05 · late 2026-08-05 to 2026-08-05 · free float · baseline 2026-08-05 to 2026-08-05

1 0 100% 05-Aug-26 A 05-Aug-26 A 05-Aug-26 05-Aug-26 done 0
OT040 COMPLETE Disconnect steam, condensate and lube oilPIPE · Ironwood Piping · Drive side, gear case and basement · after OT010
Edit

Predecessors

OT010 FS

Successors

RG01 FS
RG02 FS
RG03 FS
RG04 FS
RG05 FS
RG06 FS
RG07 FS
RG08 FS
RG09 FS
RG10 FS
RG11 FS
RG12 FS
RG13 FS
RG14 FS

Progress to the data date

Change the activity

Early 2026-08-05 to 2026-08-06 · late 2026-08-05 to 2026-08-06 · free float · baseline 2026-08-05 to 2026-08-06

2 0 100% 05-Aug-26 A 06-Aug-26 A 05-Aug-26 06-Aug-26 done 0
OT050 COMPLETE Disconnect drives and instrumentsEI · Delta Electric and Controls · Drive side, gear case and basement · after OT010
Edit

Predecessors

OT010 FS

Successors

None

Progress to the data date

Change the activity

Early 2026-08-05 to 2026-08-05 · late 2026-08-05 to 2026-08-05 · free float · baseline 2026-08-05 to 2026-08-05

1 0 100% 05-Aug-26 A 05-Aug-26 A 05-Aug-26 05-Aug-26 done 0
OT030 COMPLETE Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · Dryer section · after OT020
Edit

Predecessors

OT020 FS

Successors

RB01 FS
RB02 FS
RB03 FS
RB04 FS
RB05 FS
RB06 FS
RF01 FS
RF02 FS
RF03 FS
RF04 FS
RF05 FS
RF06 FS
RF07 FS
RF08 FS
RF09 FS
RF10 FS
RF11 FS
RF12 FS
RF13 FS

Progress to the data date

Change the activity

Early 2026-08-06 to 2026-08-07 · late 2026-08-06 to 2026-08-07 · free float · baseline 2026-08-06 to 2026-08-07

2 0 100% 06-Aug-26 A 07-Aug-26 A 06-Aug-26 07-Aug-26 done 0
5.2 Press section removal 2 activities · 2 complete 100% 06-Aug-2611-Aug-26 06-Aug-2610-Aug-26 -1
RM010 COMPLETE Remove the old press section: rolls and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after OT020
Edit

Predecessors

OT020 FS

Successors

RM020 FS

Progress to the data date

Change the activity

Early 2026-08-06 to 2026-08-08 · late 2026-08-06 to 2026-08-08 · free float · baseline 2026-08-06 to 2026-08-08

3 0 100% 06-Aug-26 A 08-Aug-26 A 06-Aug-26 08-Aug-26 done 0
RM020 COMPLETE Remove press section frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after RM010
Edit

Predecessors

RM010 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-11 · late 2026-08-09 to 2026-08-11 · free float · baseline 2026-08-09 to 2026-08-10

2 0 100% 09-Aug-26 A 11-Aug-26 A 09-Aug-26 10-Aug-26 done -1
5.3 Felt roll removal 13 activities · 13 complete 100% 08-Aug-2608-Aug-26 08-Aug-2608-Aug-26 0
RF01 COMPLETE Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF02 COMPLETE Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD02 FS
RD03 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF03 COMPLETE Remove felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD03 FS
RD04 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF04 COMPLETE Remove felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD04 FS
RD05 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF05 COMPLETE Remove felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD05 FS
RD06 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF06 COMPLETE Remove felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD06 FS
RD07 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF07 COMPLETE Remove felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD07 FS
RD08 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF08 COMPLETE Remove felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD08 FS
RD09 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF09 COMPLETE Remove felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD09 FS
RD10 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF10 COMPLETE Remove felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD10 FS
RD11 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF11 COMPLETE Remove felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD11 FS
RD12 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF12 COMPLETE Remove felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD12 FS
RD13 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RF13 COMPLETE Remove felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD13 FS
RD14 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
5.4 Blow box removal 6 activities · 6 complete 100% 08-Aug-2608-Aug-26 08-Aug-2608-Aug-26 0
RB01 COMPLETE Remove blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD01 FS
RD02 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RB02 COMPLETE Remove blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD03 FS
RD04 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RB03 COMPLETE Remove blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD05 FS
RD06 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RB04 COMPLETE Remove blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD07 FS
RD08 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RB05 COMPLETE Remove blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD09 FS
RD10 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RB06 COMPLETE Remove blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after OT030
Edit

Predecessors

OT030 FS

Successors

RD11 FS
RD12 FS
RD13 FS
RD14 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
5.5 Bull and idler gear removal 14 activities · 14 complete 100% 07-Aug-2613-Aug-26 07-Aug-2613-Aug-26 0
RG01 COMPLETE Remove bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040
Edit

Predecessors

OT040 FS

Successors

RD01 FS
RG03 FS

Progress to the data date

Change the activity

Early 2026-08-07 to 2026-08-07 · late 2026-08-07 to 2026-08-07 · free float · baseline 2026-08-07 to 2026-08-07

1 0 100% 07-Aug-26 A 07-Aug-26 A 07-Aug-26 07-Aug-26 done 0
RG02 COMPLETE Remove bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040
Edit

Predecessors

OT040 FS

Successors

RD02 FS
RG04 FS

Progress to the data date

Change the activity

Early 2026-08-07 to 2026-08-07 · late 2026-08-07 to 2026-08-07 · free float · baseline 2026-08-07 to 2026-08-07

1 0 100% 07-Aug-26 A 07-Aug-26 A 07-Aug-26 07-Aug-26 done 0
RG03 COMPLETE Remove bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG01
Edit

Predecessors

OT040 FS
RG01 FS

Successors

LB01 FS
RD03 FS
RG05 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RG04 COMPLETE Remove bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG02
Edit

Predecessors

OT040 FS
RG02 FS

Successors

RD04 FS
RG06 FS

Progress to the data date

Change the activity

Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08

1 0 100% 08-Aug-26 A 08-Aug-26 A 08-Aug-26 08-Aug-26 done 0
RG05 COMPLETE Remove bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG03
Edit

Predecessors

OT040 FS
RG03 FS

Successors

RD05 FS
RG07 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09

1 0 100% 09-Aug-26 A 09-Aug-26 A 09-Aug-26 09-Aug-26 done 0
RG06 COMPLETE Remove bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG04
Edit

Predecessors

OT040 FS
RG04 FS

Successors

LB02 FS
RD06 FS
RG08 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09

1 0 100% 09-Aug-26 A 09-Aug-26 A 09-Aug-26 09-Aug-26 done 0
RG07 COMPLETE Remove bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG05
Edit

Predecessors

OT040 FS
RG05 FS

Successors

RD07 FS
RG09 FS

Progress to the data date

Change the activity

Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10

1 0 100% 10-Aug-26 A 10-Aug-26 A 10-Aug-26 10-Aug-26 done 0
RG08 COMPLETE Remove bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG06
Edit

Predecessors

OT040 FS
RG06 FS

Successors

RD08 FS
RG10 FS

Progress to the data date

Change the activity

Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10

1 0 100% 10-Aug-26 A 10-Aug-26 A 10-Aug-26 10-Aug-26 done 0
RG09 COMPLETE Remove bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG07
Edit

Predecessors

OT040 FS
RG07 FS

Successors

LB03 FS
RD09 FS
RG11 FS

Progress to the data date

Change the activity

Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11

1 0 100% 11-Aug-26 A 11-Aug-26 A 11-Aug-26 11-Aug-26 done 0
RG10 COMPLETE Remove bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG08
Edit

Predecessors

OT040 FS
RG08 FS

Successors

RD10 FS
RG12 FS

Progress to the data date

Change the activity

Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11

1 0 100% 11-Aug-26 A 11-Aug-26 A 11-Aug-26 11-Aug-26 done 0
RG11 COMPLETE Remove bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG09
Edit

Predecessors

OT040 FS
RG09 FS

Successors

RD11 FS
RG13 FS

Progress to the data date

Change the activity

Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12

1 0 100% 12-Aug-26 A 12-Aug-26 A 12-Aug-26 12-Aug-26 done 0
RG12 COMPLETE Remove bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG10
Edit

Predecessors

OT040 FS
RG10 FS

Successors

LB04 FS
RD12 FS
RG14 FS

Progress to the data date

Change the activity

Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12

1 0 100% 12-Aug-26 A 12-Aug-26 A 12-Aug-26 12-Aug-26 done 0
RG13 COMPLETE Remove bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after OT040, RG11
Edit

Predecessors

OT040 FS
RG11 FS

Successors

RD13 FS

Progress to the data date

Change the activity

Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13

1 0 100% 13-Aug-26 A 13-Aug-26 A 13-Aug-26 13-Aug-26 done 0
RG14 COMPLETE Remove bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after OT040, RG12
Edit

Predecessors

OT040 FS
RG12 FS

Successors

LB05 FS
RD14 FS

Progress to the data date

Change the activity

Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13

1 0 100% 13-Aug-26 A 13-Aug-26 A 13-Aug-26 13-Aug-26 done 0
5.6 Dryer removal 14 activities · 14 complete 100% 09-Aug-2615-Aug-26 09-Aug-2615-Aug-26 0
RD01 COMPLETE Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RG01
Edit

Predecessors

RB01 FS
RF01 FS
RG01 FS

Successors

RD03 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09

1 0 100% 09-Aug-26 A 09-Aug-26 A 09-Aug-26 09-Aug-26 done 0
RD02 COMPLETE Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB01, RF01, RF02, RG02
Edit

Predecessors

RB01 FS
RF01 FS
RF02 FS
RG02 FS

Successors

RD04 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09

1 0 100% 09-Aug-26 A 09-Aug-26 A 09-Aug-26 09-Aug-26 done 0
RD03 COMPLETE Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD01, RF02, RF03, RG03
Edit

Predecessors

RB02 FS
RD01 FS
RF02 FS
RF03 FS
RG03 FS

Successors

RD05 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10

1 0 100% 10-Aug-26 A 10-Aug-26 A 10-Aug-26 10-Aug-26 done 0
RD04 COMPLETE Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB02, RD02, RF03, RF04, RG04
Edit

Predecessors

RB02 FS
RD02 FS
RF03 FS
RF04 FS
RG04 FS

Successors

RD06 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10

1 0 100% 10-Aug-26 A 10-Aug-26 A 10-Aug-26 10-Aug-26 done 0
RD05 COMPLETE Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD03, RF04, RF05, RG05
Edit

Predecessors

RB03 FS
RD03 FS
RF04 FS
RF05 FS
RG05 FS

Successors

RD07 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11

1 0 100% 11-Aug-26 A 11-Aug-26 A 11-Aug-26 11-Aug-26 done 0
RD06 COMPLETE Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB03, RD04, RF05, RF06, RG06
Edit

Predecessors

RB03 FS
RD04 FS
RF05 FS
RF06 FS
RG06 FS

Successors

RD08 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11

1 0 100% 11-Aug-26 A 11-Aug-26 A 11-Aug-26 11-Aug-26 done 0
RD07 COMPLETE Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD05, RF06, RF07, RG07
Edit

Predecessors

RB04 FS
RD05 FS
RF06 FS
RF07 FS
RG07 FS

Successors

RD09 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12

1 0 100% 12-Aug-26 A 12-Aug-26 A 12-Aug-26 12-Aug-26 done 0
RD08 COMPLETE Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB04, RD06, RF07, RF08, RG08
Edit

Predecessors

RB04 FS
RD06 FS
RF07 FS
RF08 FS
RG08 FS

Successors

RD10 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12

1 0 100% 12-Aug-26 A 12-Aug-26 A 12-Aug-26 12-Aug-26 done 0
RD09 COMPLETE Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD07, RF08, RF09, RG09
Edit

Predecessors

RB05 FS
RD07 FS
RF08 FS
RF09 FS
RG09 FS

Successors

RD11 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13

1 0 100% 13-Aug-26 A 13-Aug-26 A 13-Aug-26 13-Aug-26 done 0
RD10 COMPLETE Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB05, RD08, RF09, RF10, RG10
Edit

Predecessors

RB05 FS
RD08 FS
RF09 FS
RF10 FS
RG10 FS

Successors

RD12 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13

1 0 100% 13-Aug-26 A 13-Aug-26 A 13-Aug-26 13-Aug-26 done 0
RD11 COMPLETE Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD09, RF10, RF11, RG11
Edit

Predecessors

RB06 FS
RD09 FS
RF10 FS
RF11 FS
RG11 FS

Successors

RD13 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-14 to 2026-08-14 · late 2026-08-14 to 2026-08-14 · free float · baseline 2026-08-14 to 2026-08-14

1 0 100% 14-Aug-26 A 14-Aug-26 A 14-Aug-26 14-Aug-26 done 0
RD12 COMPLETE Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD10, RF11, RF12, RG12
Edit

Predecessors

RB06 FS
RD10 FS
RF11 FS
RF12 FS
RG12 FS

Successors

RD14 FS
SV010 FS

Progress to the data date

Change the activity

Early 2026-08-14 to 2026-08-14 · late 2026-08-14 to 2026-08-14 · free float · baseline 2026-08-14 to 2026-08-14

1 0 100% 14-Aug-26 A 14-Aug-26 A 14-Aug-26 14-Aug-26 done 0
RD13 COMPLETE Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD11, RF12, RF13, RG13
Edit

Predecessors

RB06 FS
RD11 FS
RF12 FS
RF13 FS
RG13 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2026-08-15 to 2026-08-15 · late 2026-08-15 to 2026-08-15 · free float · baseline 2026-08-15 to 2026-08-15

1 0 100% 15-Aug-26 A 15-Aug-26 A 15-Aug-26 15-Aug-26 done 0
RD14 COMPLETE Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after RB06, RD12, RF13, RG14
Edit

Predecessors

RB06 FS
RD12 FS
RF13 FS
RG14 FS

Successors

SV010 FS

Progress to the data date

Change the activity

Early 2026-08-15 to 2026-08-15 · late 2026-08-15 to 2026-08-15 · free float · baseline 2026-08-15 to 2026-08-15

1 0 100% 15-Aug-26 A 15-Aug-26 A 15-Aug-26 15-Aug-26 done 0
6 Outage: machining and survey 6 activities · 6 complete 100% 09-Aug-2619-Aug-26 09-Aug-2618-Aug-26 -1
6.1 Frame survey 1 activity · 1 complete 100% 16-Aug-2616-Aug-26 16-Aug-2616-Aug-26 0
SV010 COMPLETE Survey the frames after removalSURV · Benchmark Alignment Survey · Dryer section · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020
Edit

Predecessors

RD01 FS
RD02 FS
RD03 FS
RD04 FS
RD05 FS
RD06 FS
RD07 FS
RD08 FS
RD09 FS
RD10 FS
RD11 FS
RD12 FS
RD13 FS
RD14 FS
RM020 FS

Successors

ID01 FS
ID02 FS
ID03 FS
ID04 FS
ID05 FS
ID06 FS
ID07 FS
ID08 FS
ID09 FS
ID10 FS
ID11 FS
ID12 FS
ID13 FS
ID14 FS
IN010 FS

Progress to the data date

Change the activity

Early 2026-08-16 to 2026-08-16 · late 2026-08-16 to 2026-08-16 · free float · baseline 2026-08-16 to 2026-08-16

1 0 100% 16-Aug-26 A 16-Aug-26 A 16-Aug-26 16-Aug-26 done 0
6.2 Line bore and sleeve idler bores 5 activities · 5 complete 100% 09-Aug-2619-Aug-26 09-Aug-2618-Aug-26 -1
LB01 COMPLETE Line bore and sleeve idler bearing bore IB-1MECH · Precision Line Boring Co · Drive side, gear case and basement · after RG03
Edit

Predecessors

RG03 FS

Successors

IG03 FS
LB02 FS

Progress to the data date

Change the activity

Early 2026-08-09 to 2026-08-10 · late 2026-08-09 to 2026-08-10 · free float · baseline 2026-08-09 to 2026-08-10

2 0 100% 09-Aug-26 A 10-Aug-26 A 09-Aug-26 10-Aug-26 done 0
LB02 COMPLETE Line bore and sleeve idler bearing bore IB-2MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB01, RG06
Edit

Predecessors

LB01 FS
RG06 FS

Successors

IG06 FS
LB03 FS

Progress to the data date

Change the activity

Early 2026-08-11 to 2026-08-13 · late 2026-08-11 to 2026-08-13 · free float · baseline 2026-08-11 to 2026-08-12

2 0 100% 11-Aug-26 A 13-Aug-26 A 11-Aug-26 12-Aug-26 done -1
LB03 COMPLETE Line bore and sleeve idler bearing bore IB-3MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB02, RG09
Edit

Predecessors

LB02 FS
RG09 FS

Successors

IG09 FS
LB04 FS

Progress to the data date

Change the activity

Early 2026-08-14 to 2026-08-15 · late 2026-08-14 to 2026-08-15 · free float · baseline 2026-08-13 to 2026-08-14

2 0 100% 14-Aug-26 A 15-Aug-26 A 13-Aug-26 14-Aug-26 done -1
LB04 COMPLETE Line bore and sleeve idler bearing bore IB-4MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB03, RG12
Edit

Predecessors

LB03 FS
RG12 FS

Successors

IG12 FS
LB05 FS

Progress to the data date

Change the activity

Early 2026-08-16 to 2026-08-17 · late 2026-08-16 to 2026-08-17 · free float · baseline 2026-08-15 to 2026-08-16

2 0 100% 16-Aug-26 A 17-Aug-26 A 15-Aug-26 16-Aug-26 done -1
LB05 COMPLETE Line bore and sleeve idler bearing bore IB-5MECH · Precision Line Boring Co · Drive side, gear case and basement · after LB04, RG14
Edit

Predecessors

LB04 FS
RG14 FS

Successors

IG14 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-19 · late 2026-08-18 to 2026-08-19 · free float · baseline 2026-08-17 to 2026-08-18

2 0 100% 18-Aug-26 A 19-Aug-26 A 17-Aug-26 18-Aug-26 done -1
7 Outage: install 51 activities · 51 complete 100% 17-Aug-2630-Aug-26 17-Aug-2628-Aug-26 -2
7.1 Press section install 4 activities · 4 complete 100% 17-Aug-2629-Aug-26 17-Aug-2628-Aug-26 -1
IN010 COMPLETE Set new press frames and sole platesRIG · Apex Rigging and Crane · Press section · 2 lift plans · after SV010
Edit

Predecessors

SV010 FS

Successors

IN015 FS

Progress to the data date

Change the activity

Early 2026-08-17 to 2026-08-20 · late 2026-08-17 to 2026-08-20 · free float · baseline 2026-08-17 to 2026-08-19

3 0 100% 17-Aug-26 A 20-Aug-26 A 17-Aug-26 19-Aug-26 done -1
IN015 COMPLETE Grout press sole plates and cureCONC · Granite Grout and Concrete · Press section · after IN010
Edit

Predecessors

IN010 FS

Successors

IN020 FS

Progress to the data date

Change the activity

Early 2026-08-21 to 2026-08-23 · late 2026-08-21 to 2026-08-23 · free float · baseline 2026-08-20 to 2026-08-22

3 0 100% 21-Aug-26 A 23-Aug-26 A 20-Aug-26 22-Aug-26 done -1
IN020 COMPLETE Install press rolls, suction roll and felt runRIG · Apex Rigging and Crane · Press section · 5 lift plans · after IN015
Edit

Predecessors

IN015 FS

Successors

IN030 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-27 · late 2026-08-24 to 2026-08-27 · free float · baseline 2026-08-23 to 2026-08-26

4 0 100% 24-Aug-26 A 27-Aug-26 A 23-Aug-26 26-Aug-26 done -1
IN030 COMPLETE Align the press sectionSURV · Benchmark Alignment Survey · Press section · after IN020
Edit

Predecessors

IN020 FS

Successors

SY060 FS

Progress to the data date

Change the activity

Early 2026-08-28 to 2026-08-29 · late 2026-08-28 to 2026-08-29 · free float · baseline 2026-08-27 to 2026-08-28

2 0 100% 28-Aug-26 A 29-Aug-26 A 27-Aug-26 28-Aug-26 done -1
7.2 Dryer install 14 activities · 14 complete 100% 17-Aug-2623-Aug-26 17-Aug-2623-Aug-26 0
ID01 COMPLETE Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

ID03 FS
IG01 FS

Progress to the data date

Change the activity

Early 2026-08-17 to 2026-08-17 · late 2026-08-17 to 2026-08-17 · free float · baseline 2026-08-17 to 2026-08-17

1 0 100% 17-Aug-26 A 17-Aug-26 A 17-Aug-26 17-Aug-26 done 0
ID02 COMPLETE Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after SV010
Edit

Predecessors

SV010 FS

Successors

IB01 FS
ID04 FS
IF01 FS
IG02 FS

Progress to the data date

Change the activity

Early 2026-08-17 to 2026-08-17 · late 2026-08-17 to 2026-08-17 · free float · baseline 2026-08-17 to 2026-08-17

1 0 100% 17-Aug-26 A 17-Aug-26 A 17-Aug-26 17-Aug-26 done 0
ID03 COMPLETE Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID01, SV010
Edit

Predecessors

ID01 FS
SV010 FS

Successors

ID05 FS
IF02 FS
IG03 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
ID04 COMPLETE Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02, SV010
Edit

Predecessors

ID02 FS
SV010 FS

Successors

IB02 FS
ID06 FS
IF03 FS
IG04 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
ID05 COMPLETE Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, SV010
Edit

Predecessors

ID03 FS
SV010 FS

Successors

ID07 FS
IF04 FS
IG05 FS

Progress to the data date

Change the activity

Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 19-Aug-26 A 19-Aug-26 A 19-Aug-26 19-Aug-26 done 0
ID06 COMPLETE Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, SV010
Edit

Predecessors

ID04 FS
SV010 FS

Successors

IB03 FS
ID08 FS
IF05 FS
IG06 FS

Progress to the data date

Change the activity

Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 19-Aug-26 A 19-Aug-26 A 19-Aug-26 19-Aug-26 done 0
ID07 COMPLETE Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, SV010
Edit

Predecessors

ID05 FS
SV010 FS

Successors

ID09 FS
IF06 FS
IG07 FS

Progress to the data date

Change the activity

Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 20-Aug-26 A 20-Aug-26 A 20-Aug-26 20-Aug-26 done 0
ID08 COMPLETE Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, SV010
Edit

Predecessors

ID06 FS
SV010 FS

Successors

IB04 FS
ID10 FS
IF07 FS
IG08 FS

Progress to the data date

Change the activity

Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 20-Aug-26 A 20-Aug-26 A 20-Aug-26 20-Aug-26 done 0
ID09 COMPLETE Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, SV010
Edit

Predecessors

ID07 FS
SV010 FS

Successors

ID11 FS
IF08 FS
IG09 FS

Progress to the data date

Change the activity

Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 21-Aug-26 A 21-Aug-26 A 21-Aug-26 21-Aug-26 done 0
ID10 COMPLETE Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, SV010
Edit

Predecessors

ID08 FS
SV010 FS

Successors

IB05 FS
ID12 FS
IF09 FS
IG10 FS

Progress to the data date

Change the activity

Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 21-Aug-26 A 21-Aug-26 A 21-Aug-26 21-Aug-26 done 0
ID11 COMPLETE Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09, SV010
Edit

Predecessors

ID09 FS
SV010 FS

Successors

ID13 FS
IF10 FS
IG11 FS

Progress to the data date

Change the activity

Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 22-Aug-26 A 22-Aug-26 A 22-Aug-26 22-Aug-26 done 0
ID12 COMPLETE Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, SV010
Edit

Predecessors

ID10 FS
SV010 FS

Successors

IB06 FS
ID14 FS
IF11 FS
IG12 FS

Progress to the data date

Change the activity

Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 22-Aug-26 A 22-Aug-26 A 22-Aug-26 22-Aug-26 done 0
ID13 COMPLETE Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, SV010
Edit

Predecessors

ID11 FS
SV010 FS

Successors

IF12 FS
IG13 FS
SY010 FS

Progress to the data date

Change the activity

Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 23-Aug-26 A 23-Aug-26 A 23-Aug-26 23-Aug-26 done 0
ID14 COMPLETE Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, SV010
Edit

Predecessors

ID12 FS
SV010 FS

Successors

IF13 FS
IG14 FS
SY010 FS

Progress to the data date

Change the activity

Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 23-Aug-26 A 23-Aug-26 A 23-Aug-26 23-Aug-26 done 0
7.3 Bull and idler gear install 14 activities · 14 complete 100% 18-Aug-2624-Aug-26 18-Aug-2624-Aug-26 0
IG01 COMPLETE Install bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID01
Edit

Predecessors

ID01 FS

Successors

IG03 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
IG02 COMPLETE Install bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID02
Edit

Predecessors

ID02 FS

Successors

IG04 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
IG03 COMPLETE Install bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID03, IG01, LB01
Edit

Predecessors

ID03 FS
IG01 FS
LB01 FS

Successors

IG05 FS

Progress to the data date

Change the activity

Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 19-Aug-26 A 19-Aug-26 A 19-Aug-26 19-Aug-26 done 0
IG04 COMPLETE Install bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID04, IG02
Edit

Predecessors

ID04 FS
IG02 FS

Successors

IG06 FS

Progress to the data date

Change the activity

Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 19-Aug-26 A 19-Aug-26 A 19-Aug-26 19-Aug-26 done 0
IG05 COMPLETE Install bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID05, IG03
Edit

Predecessors

ID05 FS
IG03 FS

Successors

IG07 FS

Progress to the data date

Change the activity

Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 20-Aug-26 A 20-Aug-26 A 20-Aug-26 20-Aug-26 done 0
IG06 COMPLETE Install bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID06, IG04, LB02
Edit

Predecessors

ID06 FS
IG04 FS
LB02 FS

Successors

IG08 FS

Progress to the data date

Change the activity

Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 20-Aug-26 A 20-Aug-26 A 20-Aug-26 20-Aug-26 done 0
IG07 COMPLETE Install bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID07, IG05
Edit

Predecessors

ID07 FS
IG05 FS

Successors

IG09 FS

Progress to the data date

Change the activity

Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 21-Aug-26 A 21-Aug-26 A 21-Aug-26 21-Aug-26 done 0
IG08 COMPLETE Install bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID08, IG06
Edit

Predecessors

ID08 FS
IG06 FS

Successors

IG10 FS

Progress to the data date

Change the activity

Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 21-Aug-26 A 21-Aug-26 A 21-Aug-26 21-Aug-26 done 0
IG09 COMPLETE Install bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID09, IG07, LB03
Edit

Predecessors

ID09 FS
IG07 FS
LB03 FS

Successors

IG11 FS

Progress to the data date

Change the activity

Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 22-Aug-26 A 22-Aug-26 A 22-Aug-26 22-Aug-26 done 0
IG10 COMPLETE Install bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID10, IG08
Edit

Predecessors

ID10 FS
IG08 FS

Successors

IG12 FS

Progress to the data date

Change the activity

Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 22-Aug-26 A 22-Aug-26 A 22-Aug-26 22-Aug-26 done 0
IG11 COMPLETE Install bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID11, IG09
Edit

Predecessors

ID11 FS
IG09 FS

Successors

IG13 FS

Progress to the data date

Change the activity

Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 23-Aug-26 A 23-Aug-26 A 23-Aug-26 23-Aug-26 done 0
IG12 COMPLETE Install bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID12, IG10, LB04
Edit

Predecessors

ID12 FS
IG10 FS
LB04 FS

Successors

IG14 FS

Progress to the data date

Change the activity

Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 23-Aug-26 A 23-Aug-26 A 23-Aug-26 23-Aug-26 done 0
IG13 COMPLETE Install bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · Drive side, gear case and basement · 3 lift plans · after ID13, IG11
Edit

Predecessors

ID13 FS
IG11 FS

Successors

SY050 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24

1 0 100% 24-Aug-26 A 24-Aug-26 A 24-Aug-26 24-Aug-26 done 0
IG14 COMPLETE Install bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · Drive side, gear case and basement · 2 lift plans · after ID14, IG12, LB05
Edit

Predecessors

ID14 FS
IG12 FS
LB05 FS

Successors

SY040 SS
SY050 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24

1 0 100% 24-Aug-26 A 24-Aug-26 A 24-Aug-26 24-Aug-26 done 0
7.4 Felt roll install 13 activities · 13 complete 100% 18-Aug-2630-Aug-26 18-Aug-2627-Aug-26 -3
IF01 COMPLETE Install felt roll FR-01 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02
Edit

Predecessors

ID02 FS

Successors

IF02 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
IF08 COMPLETE Install felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID09
Edit

Predecessors

ID09 FS

Successors

IF09 FS

Progress to the data date

Change the activity

Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 22-Aug-26 A 22-Aug-26 A 22-Aug-26 22-Aug-26 done 0
IF09 COMPLETE Install felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID10, IF08
Edit

Predecessors

ID10 FS
IF08 FS

Successors

IF10 FS

Progress to the data date

Change the activity

Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 23-Aug-26 A 23-Aug-26 A 23-Aug-26 23-Aug-26 done 0
IF02 COMPLETE Install felt roll FR-02 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID03, IF01
Edit

Predecessors

ID03 FS
IF01 FS

Successors

IF03 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 24-Aug-26 A 24-Aug-26 A 19-Aug-26 19-Aug-26 done -5
IF10 COMPLETE Install felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID11, IF09
Edit

Predecessors

ID11 FS
IF09 FS

Successors

IF11 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24

1 0 100% 24-Aug-26 A 24-Aug-26 A 24-Aug-26 24-Aug-26 done 0
IF03 COMPLETE Install felt roll FR-03 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID04, IF02
Edit

Predecessors

ID04 FS
IF02 FS

Successors

IF04 FS

Progress to the data date

Change the activity

Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 25-Aug-26 A 25-Aug-26 A 20-Aug-26 20-Aug-26 done -5
IF11 COMPLETE Install felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID12, IF10
Edit

Predecessors

ID12 FS
IF10 FS

Successors

IF12 FS

Progress to the data date

Change the activity

Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-25 to 2026-08-25

1 0 100% 25-Aug-26 A 25-Aug-26 A 25-Aug-26 25-Aug-26 done 0
IF04 COMPLETE Install felt roll FR-04 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID05, IF03
Edit

Predecessors

ID05 FS
IF03 FS

Successors

IF05 FS

Progress to the data date

Change the activity

Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 26-Aug-26 A 26-Aug-26 A 21-Aug-26 21-Aug-26 done -5
IF12 COMPLETE Install felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID13, IF11
Edit

Predecessors

ID13 FS
IF11 FS

Successors

IF13 FS

Progress to the data date

Change the activity

Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-26 to 2026-08-26

1 0 100% 26-Aug-26 A 26-Aug-26 A 26-Aug-26 26-Aug-26 done 0
IF05 COMPLETE Install felt roll FR-05 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID06, IF04
Edit

Predecessors

ID06 FS
IF04 FS

Successors

IF06 FS

Progress to the data date

Change the activity

Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 27-Aug-26 A 27-Aug-26 A 22-Aug-26 22-Aug-26 done -5
IF13 COMPLETE Install felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID14, IF12
Edit

Predecessors

ID14 FS
IF12 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-27 to 2026-08-27

1 0 100% 27-Aug-26 A 27-Aug-26 A 27-Aug-26 27-Aug-26 done 0
IF06 COMPLETE Install felt roll FR-06 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID07, IF05
Edit

Predecessors

ID07 FS
IF05 FS

Successors

IF07 FS

Progress to the data date

Change the activity

Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 28-Aug-26 A 28-Aug-26 A 23-Aug-26 23-Aug-26 done -5
IF07 COMPLETE Install felt roll FR-07 (top felt)MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID08, IF06
Edit

Predecessors

ID08 FS
IF06 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2026-08-29 to 2026-08-30 · late 2026-08-29 to 2026-08-30 · free float · baseline 2026-08-24 to 2026-08-24

1 0 100% 29-Aug-26 A 30-Aug-26 A 24-Aug-26 24-Aug-26 done -6
7.5 Blow box install 6 activities · 6 complete 100% 18-Aug-2628-Aug-26 18-Aug-2623-Aug-26 -5
IB01 COMPLETE Install blow box BB-1MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after ID02
Edit

Predecessors

ID02 FS

Successors

IB02 FS

Progress to the data date

Change the activity

Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18

1 0 100% 18-Aug-26 A 18-Aug-26 A 18-Aug-26 18-Aug-26 done 0
IB02 COMPLETE Install blow box BB-2MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB01, ID04
Edit

Predecessors

IB01 FS
ID04 FS

Successors

IB03 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-19 to 2026-08-19

1 0 100% 24-Aug-26 A 24-Aug-26 A 19-Aug-26 19-Aug-26 done -5
IB03 COMPLETE Install blow box BB-3MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB02, ID06
Edit

Predecessors

IB02 FS
ID06 FS

Successors

IB04 FS

Progress to the data date

Change the activity

Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-20 to 2026-08-20

1 0 100% 25-Aug-26 A 25-Aug-26 A 20-Aug-26 20-Aug-26 done -5
IB04 COMPLETE Install blow box BB-4MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB03, ID08
Edit

Predecessors

IB03 FS
ID08 FS

Successors

IB05 FS

Progress to the data date

Change the activity

Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-21 to 2026-08-21

1 0 100% 26-Aug-26 A 26-Aug-26 A 21-Aug-26 21-Aug-26 done -5
IB05 COMPLETE Install blow box BB-5MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB04, ID10
Edit

Predecessors

IB04 FS
ID10 FS

Successors

IB06 FS

Progress to the data date

Change the activity

Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-22 to 2026-08-22

1 0 100% 27-Aug-26 A 27-Aug-26 A 22-Aug-26 22-Aug-26 done -5
IB06 COMPLETE Install blow box BB-6MILL · Northfield Millwright Services · Dryer section · 1 lift plan · after IB05, ID12
Edit

Predecessors

IB05 FS
ID12 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-23 to 2026-08-23

1 0 100% 28-Aug-26 A 28-Aug-26 A 23-Aug-26 23-Aug-26 done -5
8 Outage: systems and checks 9 activities · 9 complete 100% 24-Aug-2603-Sep-26 24-Aug-2603-Sep-26 0
8.1 Steam, condensate and lube 4 activities · 4 complete 100% 24-Aug-2631-Aug-26 24-Aug-2631-Aug-26 0
SY010 COMPLETE Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · Drive side, gear case and basement · after ID13, ID14
Edit

Predecessors

ID13 FS
ID14 FS

Successors

SY020 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-27 · late 2026-08-24 to 2026-08-27 · free float · baseline 2026-08-24 to 2026-08-27

4 0 100% 24-Aug-26 A 27-Aug-26 A 24-Aug-26 27-Aug-26 done 0
SY020 COMPLETE Hydro test dryers and steam jointsQAQC · Drive side, gear case and basement · after SY010
Edit

Predecessors

SY010 FS

Successors

SY030 SS
SY070 FS

Progress to the data date

Change the activity

Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-28 to 2026-08-28

1 0 100% 28-Aug-26 A 28-Aug-26 A 28-Aug-26 28-Aug-26 done 0
SY030 COMPLETE Flush the lube oil systemPIPE · Ironwood Piping · Drive side, gear case and basement · after SY020
Edit

Predecessors

SY020 SS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2026-08-28 to 2026-08-30 · late 2026-08-28 to 2026-08-30 · free float · baseline 2026-08-28 to 2026-08-30

3 0 100% 28-Aug-26 A 30-Aug-26 A 28-Aug-26 30-Aug-26 done 0
SY070 COMPLETE Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · Drive side, gear case and basement · after SY020
Edit

Predecessors

SY020 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2026-08-29 to 2026-08-31 · late 2026-08-29 to 2026-08-31 · free float · baseline 2026-08-29 to 2026-08-31

3 0 100% 29-Aug-26 A 31-Aug-26 A 29-Aug-26 31-Aug-26 done 0
8.2 Drives and instruments 1 activity · 1 complete 100% 24-Aug-2626-Aug-26 24-Aug-2626-Aug-26 0
SY040 COMPLETE Reconnect drives and instruments, loop checkEI · Delta Electric and Controls · Drive side, gear case and basement · after IG14
Edit

Predecessors

IG14 SS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2026-08-24 to 2026-08-26 · late 2026-08-24 to 2026-08-26 · free float · baseline 2026-08-24 to 2026-08-26

3 0 100% 24-Aug-26 A 26-Aug-26 A 24-Aug-26 26-Aug-26 done 0
8.3 Mechanical checks and alignment 2 activities · 2 complete 100% 25-Aug-2631-Aug-26 25-Aug-2630-Aug-26 -1
SY050 COMPLETE Gear mesh, backlash and runout checksMILL · Northfield Millwright Services · Drive side, gear case and basement · after IG13, IG14
Edit

Predecessors

IG13 FS
IG14 FS

Successors

SY060 FS

Progress to the data date

Change the activity

Early 2026-08-25 to 2026-08-26 · late 2026-08-25 to 2026-08-26 · free float · baseline 2026-08-25 to 2026-08-26

2 0 100% 25-Aug-26 A 26-Aug-26 A 25-Aug-26 26-Aug-26 done 0
SY060 COMPLETE Final alignment survey: press and dryersSURV · Benchmark Alignment Survey · Dryer section · after IN030, SY050
Edit

Predecessors

IN030 FS
SY050 FS

Successors

SY080 FS

Progress to the data date

Change the activity

Early 2026-08-30 to 2026-08-31 · late 2026-08-30 to 2026-08-31 · free float · baseline 2026-08-29 to 2026-08-30

2 0 100% 30-Aug-26 A 31-Aug-26 A 29-Aug-26 30-Aug-26 done -1
8.4 Demobilize and punch walk 2 activities · 2 complete 100% 01-Sep-2603-Sep-26 01-Sep-2603-Sep-26 0
SY080 COMPLETE Strike outage scaffoldingSCAF · Summit Scaffold · Dryer section · after IB06, IF07, IF13, SY060, SY070
Edit

Predecessors

IB06 FS
IF07 FS
IF13 FS
SY060 FS
SY070 FS

Successors

SY090 FS

Progress to the data date

Change the activity

Early 2026-09-01 to 2026-09-02 · late 2026-09-01 to 2026-09-02 · free float · baseline 2026-09-01 to 2026-09-02

2 0 100% 01-Sep-26 A 02-Sep-26 A 01-Sep-26 02-Sep-26 done 0
SY090 COMPLETE Punch walk and pre-startup safety reviewQAQC · Dryer section · after SY030, SY040, SY080
Edit

Predecessors

SY030 FS
SY040 FS
SY080 FS

Successors

SU010 FS

Progress to the data date

Change the activity

Early 2026-09-03 to 2026-09-03 · late 2026-09-03 to 2026-09-03 · free float · baseline 2026-09-03 to 2026-09-03

1 0 100% 03-Sep-26 A 03-Sep-26 A 03-Sep-26 03-Sep-26 done 0
9 Startup 5 activities · 5 complete 100% 04-Sep-2608-Sep-26 04-Sep-2608-Sep-26 0
SU010 COMPLETE Remove locks and hand the machine back to operationsCOMM · Dryer section · after SY090
Edit

Predecessors

SY090 FS

Successors

SU020 FS

Progress to the data date

Change the activity

Early 2026-09-04 to 2026-09-04 · late 2026-09-04 to 2026-09-04 · free float · baseline 2026-09-04 to 2026-09-04

1 0 100% 04-Sep-26 A 04-Sep-26 A 04-Sep-26 04-Sep-26 done 0
SU020 COMPLETE Dry run and jog the drivesCOMM · Dryer section · after SU010
Edit

Predecessors

SU010 FS

Successors

SU030 FS

Progress to the data date

Change the activity

Early 2026-09-05 to 2026-09-06 · late 2026-09-05 to 2026-09-06 · free float · baseline 2026-09-05 to 2026-09-06

2 0 100% 05-Sep-26 A 06-Sep-26 A 05-Sep-26 06-Sep-26 done 0
SU030 COMPLETE Hang new press and dryer feltsMILL · Northfield Millwright Services · Dryer section · after SU020
Edit

Predecessors

SU020 FS

Successors

SU040 FS

Progress to the data date

Change the activity

Early 2026-09-07 to 2026-09-07 · late 2026-09-07 to 2026-09-07 · free float · baseline 2026-09-07 to 2026-09-07

1 0 100% 07-Sep-26 A 07-Sep-26 A 07-Sep-26 07-Sep-26 done 0
SU040 COMPLETE Steam up and warm the dryersCOMM · Dryer section · after SU030
Edit

Predecessors

SU030 FS

Successors

SU050 FS

Progress to the data date

Change the activity

Early 2026-09-08 to 2026-09-08 · late 2026-09-08 to 2026-09-08 · free float · baseline 2026-09-08 to 2026-09-08

1 0 100% 08-Sep-26 A 08-Sep-26 A 08-Sep-26 08-Sep-26 done 0
SU050 COMPLETE Paper on the reelCOMM · Dryer section · Finish on or before 2026-09-08 · after SU040
Edit

Predecessors

SU040 FS

Successors

CL010 FS

Progress to the data date

Change the activity

Early 2026-09-08 to 2026-09-08 · late 2026-09-08 to 2026-09-08 · free float · baseline 2026-09-08 to 2026-09-08

MS 0 100% 08-Sep-26 A 08-Sep-26 A 08-Sep-26 08-Sep-26 done 0
Paper on the reel
10 Performance and turnover 6 activities · 6 complete 100% 09-Sep-2607-Oct-26 09-Sep-2606-Oct-26 -1
10.1 Performance run 1 activity · 1 complete 100% 09-Sep-2611-Sep-26 09-Sep-2611-Sep-26 0
CL010 COMPLETE 72-hour performance runCOMM · Dryer section · after SU050
Edit

Predecessors

SU050 FS

Successors

CL020 FS
CL030 FS
CL040 FS

Progress to the data date

Change the activity

Early 2026-09-09 to 2026-09-11 · late 2026-09-09 to 2026-09-11 · free float · baseline 2026-09-09 to 2026-09-11

3 0 100% 09-Sep-26 A 11-Sep-26 A 09-Sep-26 11-Sep-26 done 0
10.2 Closeout 5 activities · 5 complete 100% 12-Sep-2607-Oct-26 12-Sep-2606-Oct-26 -1
CL020 COMPLETE Close the punch listQAQC · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL900 FS

Progress to the data date

Change the activity

Early 2026-09-12 to 2026-09-21 · late 2026-09-12 to 2026-09-21 · free float · baseline 2026-09-12 to 2026-09-21

10 0 100% 12-Sep-26 A 21-Sep-26 A 12-Sep-26 21-Sep-26 done 0
CL030 COMPLETE Turnover packages accepted by the millPMGT · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL050 FS

Progress to the data date

Change the activity

Early 2026-09-12 to 2026-09-21 · late 2026-09-12 to 2026-09-21 · free float · baseline 2026-09-12 to 2026-09-21

10 0 100% 12-Sep-26 A 21-Sep-26 A 12-Sep-26 21-Sep-26 done 0
CL040 COMPLETE As-built drawings and alignment reportsPMGT · Office and engineering · after CL010
Edit

Predecessors

CL010 FS

Successors

CL050 FS

Progress to the data date

Change the activity

Early 2026-09-12 to 2026-09-27 · late 2026-09-12 to 2026-09-27 · free float · baseline 2026-09-12 to 2026-09-26

15 0 100% 12-Sep-26 A 27-Sep-26 A 12-Sep-26 26-Sep-26 done -1
CL050 COMPLETE Final cost report and lessons learnedPMGT · Office and engineering · after CL030, CL040
Edit

Predecessors

CL030 FS
CL040 FS

Successors

CL900 FS

Progress to the data date

Change the activity

Early 2026-09-28 to 2026-10-07 · late 2026-09-28 to 2026-10-07 · free float · baseline 2026-09-27 to 2026-10-06

10 0 100% 28-Sep-26 A 07-Oct-26 A 27-Sep-26 06-Oct-26 done -1
CL900 COMPLETE Project turned overPMGT · Office and engineering · after CL020, CL050
Edit

Predecessors

CL020 FS
CL050 FS

Successors

None

Progress to the data date

Change the activity

Early 2026-10-07 to 2026-10-07 · late 2026-10-07 to 2026-10-07 · free float · baseline 2026-10-06 to 2026-10-06

MS 0 100% 07-Oct-26 A 07-Oct-26 A 06-Oct-26 06-Oct-26 done -1
Project turned over
Source: activity, activity_rel, baseline_activity, work_calendar, holiday

Add an activity

Run, baseline and publish

Keeps a snapshot. Unfinished activities whose finish moved since the last update go to the delay log for review, and contractors are asked about missed dates.

Work calendar

Non-work days

2025-11-27 Thanksgiving
2025-12-25 Christmas
2026-01-01 New Year's Day