SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Concrete ?

Trade lead: Luis Ortega, Granite Grout and Concrete · Everything saved here shows live on the PM and CM screens.

Owner: Concrete Lead · Readers: Construction Manager, Project Manager · Trades: CONC · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
0.99
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
1 / 1
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $150,000 · approved changes $0 · revised $150,000 · pending $0 · back-charges open $0 · value returned $0

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

ACTION [Luis Ortega] Concrete cure check on the press sole plates by 2026-08-23. watch item MTG-3-22 · Daily Outage Coordination, day 18 2026-08-22, line 15

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
C-3700-01Press sole plate grout detail ABAB CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
C-3700-01Press sole plate grout detailAB CONC2026-09-26Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

No milestones for this trade.

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
CONC-7.1-A107.1 · A10$150,000$150,000$151,500$151,500
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
2026-10-22Granite Grout and Concrete read 00.0
2026-10-21Granite Grout and Concrete read 00.0
2026-10-20Granite Grout and Concrete read 00.0
2026-10-19Granite Grout and Concrete read 00.0
2026-10-18Granite Grout and Concrete read 00.0
2026-10-17Granite Grout and Concrete read 00.0
2026-10-16Granite Grout and Concrete read 00.0
Hours per task are MISSING: contractor logs do not carry them
Source: daily_log

Shift turnover

2026-08-22 DAYS HOLD
Lead: Grout pour complete, curing
Contractor: Sole plates ready for rolls
Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-08-21 Epoxy grout mixing with face shields and gloves per the SDS; good. Referred to Site Safety Lead

2026-08-13 Epoxy grout mixing with face shields and gloves per the SDS; good. Referred to Site Safety Lead

2026-08-05 Epoxy grout mixing with face shields and gloves per the SDS; good. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • Pre-pour checklist
  • Rebar inspection
  • Cylinder test log
Source: board settings