SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Procurement Document control Current revisions Safety center

Procurement ?

Every PO line the job is waiting on, checked against the date the work needs it. Need-by comes from the planned start of the activity that uses the item unless someone enters one. Status is worked out from the dates.

Is this page current? All feeds OK

Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Late
0
Source: material_item, activity
At Risk
0
Source: material_item, activity
No Promise
0
Source: material_item, activity
On Track
0
Source: material_item, activity
Delivered
14
Source: material_item, activity

Material register

PO lineItemTradeSupplierNeeded forNeed-byPromisedDeliveredMargin calcStatus
PO-7715-01 Idler bearing bore sleeves IB-1 to IB-5 PMGT Midstate Bearing Supply LB01
Line bore and sleeve idler bearing bore IB-1
2026-08-09
activity planned start
2026-05-20 2026-05-20 81 d DELIVERED
PO-7710-01 New press section, complete (OEM)
Shipped late from the OEM; inside float (D-001)
PMGT Demo Press OEM IN010
Set new press frames and sole plates
2026-08-17
activity planned start
2026-07-22 2026-07-28 20 d DELIVERED
PO-7711-01 Dryer cans D-01 to D-14 PMGT Lakeshore Dryer Works ID01
Set new dryer D-01 (top tier)
2026-08-17
activity planned start
2026-07-08 2026-07-08 40 d DELIVERED
PO-7715-02 Dryer and gear bearings, housings and seals PMGT Midstate Bearing Supply ID01
Set new dryer D-01 (top tier)
2026-08-17
activity planned start
2026-05-27 2026-05-27 82 d DELIVERED
PO-7712-01 Bull gears BG-01 to BG-14 PMGT Ridgeline Gear Co IG01
Install bull gear BG-01 and idler gears IG-01, IG-02
2026-08-18
activity planned start
2026-06-24 2026-06-24 55 d DELIVERED
PO-7712-02 Idler gears IG-01 to IG-27 PMGT Ridgeline Gear Co IG01
Install bull gear BG-01 and idler gears IG-01, IG-02
2026-08-18
activity planned start
2026-06-17 2026-06-17 62 d DELIVERED
PO-7713-01 Felt rolls FR-01 to FR-13, balanced PMGT Crestview Roll Co IF01
Install felt roll FR-01 (top felt)
2026-08-18
activity planned start
2026-06-10 2026-06-10 69 d DELIVERED
PO-7714-01 Blow boxes BB-1 to BB-6 PMGT AirFlow Process Equipment IB01
Install blow box BB-1
2026-08-18
activity planned start
2026-06-03 2026-06-03 76 d DELIVERED
PO-7730-01 Adapter flange for blow box BB-2 supply duct
Raised after BB-2 would not bolt up (D-004)
MILL AirFlow Process Equipment IB02
Install blow box BB-2
2026-08-19
entered
2026-08-25 2026-08-26 -7 d DELIVERED
PO-7740-01 Epoxy grout, press sole plates CONC Granite Grout and Concrete IN015
Grout press sole plates and cure
2026-08-19
entered
2026-08-17 2026-08-17 2 d DELIVERED
PO-7720-01 Steam joint rebuild kits, 14 dryers
9 of 14 received; balance promised
PIPE Keystone Steam Specialties SY010
Reconnect steam joints, syphons and condensate
2026-08-24
entered
2026-08-24 2026-08-24 0 d DELIVERED
PO-7720-02 Stationary syphon assemblies, 14 PIPE Keystone Steam Specialties SY010
Reconnect steam joints, syphons and condensate
2026-08-24
entered
2026-07-27 2026-07-27 28 d DELIVERED
PO-7750-01 Drive couplings and guards, 14 sections EI Delta Electric and Controls SY040
Reconnect drives and instruments, loop check
2026-08-24
entered
2026-08-01 2026-08-02 22 d DELIVERED
PO-7760-01 Condensate header replacement pipe and fittings (CO-001) PIPE Ironwood Piping SY010
Reconnect steam joints, syphons and condensate
2026-08-24
entered
2026-08-21 2026-08-21 3 d DELIVERED
Source: material_item, activity · margin = need-by minus promised (or delivered) date; negative means it arrives after the work needs it; a passed promise counts from today

Add a material line