Procurement
Every PO line the job is waiting on, checked against the date the work needs it. Need-by comes from the planned start of the activity that uses the item unless someone enters one. Status is worked out from the dates.
Is this page current? All feeds OK
Procurement register
OK
26 h ago · expected every 7 d
Schedule (P6 export)
OK
41 min ago · expected every 24 h
Late
0
Source: material_item, activity
At Risk
0
Source: material_item, activity
No Promise
0
Source: material_item, activity
On Track
0
Source: material_item, activity
Delivered
14
Source: material_item, activity
Material register
| PO line | Item | Trade | Supplier | Needed for | Need-by | Promised | Delivered | Margin calc | Status | |
|---|---|---|---|---|---|---|---|---|---|---|
| PO-7715-01 | Idler bearing bore sleeves IB-1 to IB-5 | PMGT | Midstate Bearing Supply | LB01 Line bore and sleeve idler bearing bore IB-1 |
2026-08-09 activity planned start |
2026-05-20 | 2026-05-20 | 81 d | DELIVERED | |
| PO-7710-01 | New press section, complete (OEM) Shipped late from the OEM; inside float (D-001) |
PMGT | Demo Press OEM | IN010 Set new press frames and sole plates |
2026-08-17 activity planned start |
2026-07-22 | 2026-07-28 | 20 d | DELIVERED | |
| PO-7711-01 | Dryer cans D-01 to D-14 | PMGT | Lakeshore Dryer Works | ID01 Set new dryer D-01 (top tier) |
2026-08-17 activity planned start |
2026-07-08 | 2026-07-08 | 40 d | DELIVERED | |
| PO-7715-02 | Dryer and gear bearings, housings and seals | PMGT | Midstate Bearing Supply | ID01 Set new dryer D-01 (top tier) |
2026-08-17 activity planned start |
2026-05-27 | 2026-05-27 | 82 d | DELIVERED | |
| PO-7712-01 | Bull gears BG-01 to BG-14 | PMGT | Ridgeline Gear Co | IG01 Install bull gear BG-01 and idler gears IG-01, IG-02 |
2026-08-18 activity planned start |
2026-06-24 | 2026-06-24 | 55 d | DELIVERED | |
| PO-7712-02 | Idler gears IG-01 to IG-27 | PMGT | Ridgeline Gear Co | IG01 Install bull gear BG-01 and idler gears IG-01, IG-02 |
2026-08-18 activity planned start |
2026-06-17 | 2026-06-17 | 62 d | DELIVERED | |
| PO-7713-01 | Felt rolls FR-01 to FR-13, balanced | PMGT | Crestview Roll Co | IF01 Install felt roll FR-01 (top felt) |
2026-08-18 activity planned start |
2026-06-10 | 2026-06-10 | 69 d | DELIVERED | |
| PO-7714-01 | Blow boxes BB-1 to BB-6 | PMGT | AirFlow Process Equipment | IB01 Install blow box BB-1 |
2026-08-18 activity planned start |
2026-06-03 | 2026-06-03 | 76 d | DELIVERED | |
| PO-7730-01 | Adapter flange for blow box BB-2 supply duct Raised after BB-2 would not bolt up (D-004) |
MILL | AirFlow Process Equipment | IB02 Install blow box BB-2 |
2026-08-19 entered |
2026-08-25 | 2026-08-26 | -7 d | DELIVERED | |
| PO-7740-01 | Epoxy grout, press sole plates | CONC | Granite Grout and Concrete | IN015 Grout press sole plates and cure |
2026-08-19 entered |
2026-08-17 | 2026-08-17 | 2 d | DELIVERED | |
| PO-7720-01 | Steam joint rebuild kits, 14 dryers 9 of 14 received; balance promised |
PIPE | Keystone Steam Specialties | SY010 Reconnect steam joints, syphons and condensate |
2026-08-24 entered |
2026-08-24 | 2026-08-24 | 0 d | DELIVERED | |
| PO-7720-02 | Stationary syphon assemblies, 14 | PIPE | Keystone Steam Specialties | SY010 Reconnect steam joints, syphons and condensate |
2026-08-24 entered |
2026-07-27 | 2026-07-27 | 28 d | DELIVERED | |
| PO-7750-01 | Drive couplings and guards, 14 sections | EI | Delta Electric and Controls | SY040 Reconnect drives and instruments, loop check |
2026-08-24 entered |
2026-08-01 | 2026-08-02 | 22 d | DELIVERED | |
| PO-7760-01 | Condensate header replacement pipe and fittings (CO-001) | PIPE | Ironwood Piping | SY010 Reconnect steam joints, syphons and condensate |
2026-08-24 entered |
2026-08-21 | 2026-08-21 | 3 d | DELIVERED |
Source: material_item, activity · margin = need-by minus promised (or delivered) date; negative means it arrives after the work needs it; a passed promise counts from today