SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Client master board ?

Only the PM and CM see the master board. The client sees this board instead: each update is a frozen copy of the sections you choose, approved under your name. Each one has its own link to send.

Releases

ReleaseApprovedIncludes
Closeout report: project turned over
Paper on the reel on the contract date (2026-09-08). Turnover packages, as-built drawings and alignment reports accepted; project turned over 2026-10-07, one day after the baseline (D-007). No recordable injuries. Final cost within half a percent of the revised budget.
Elena Varga, CM
2026-10-08T16:00:00
Progress by trade, Milestones, Delay register, Cost summary
Paper on the reel
Paper on the reel on outage day 35, the contract date. 72-hour performance run under way.
Elena Varga, CM
2026-09-09T16:00:00
Progress by trade, Milestones, Delay register
Weekly client report: outage day 33
Mechanically complete on day 30; machine handed back to operations on day 31. Dry run and drive jog done; new felts going on. Paper on the reel holds its date.
Elena Varga, CM
2026-09-06T16:00:00
Progress by trade, Milestones, Delay register
Weekly client report: outage day 26
Press section aligned; all 14 dryers, gears, felt rolls and blow boxes back in. BB-2 bolted up when the adapter flange arrived (D-004 agreed, 3 days on the blow boxes, inside float). Hydro test passed.
Elena Varga, CM
2026-08-30T16:00:00
Progress by trade, Milestones, Delay register
Weekly client report: outage day 19
Dryers D-01 to D-12 back in, press frames grouted. Paper on the reel holds its date; BB-2 adapter flange (D-004) is on the watch list.
Elena Varga, CM
2026-08-23T13:55:00
Progress by trade, Milestones, Delay register
Weekly client report: outage day 12
Press section and all 14 dryers out. Line boring one day behind on IB-2; delay D-003 agreed.
Elena Varga, CM
2026-08-16T16:00:00
Progress by trade, Milestones, Delay register
Weekly client report: outage day 5
Machine down on time. Felts out, scaffold up, press section removal under way.
Elena Varga, CM
2026-08-09T16:00:00
Progress by trade, Milestones, Delay register
Source: client_release