Survey and Layout
Trade lead: Hannah Price, Benchmark Alignment Survey · Everything saved here shows live on the PM and CM screens.
Owner: Survey Lead · Readers: Construction Manager, Project Manager · Trades: SURV · Foreman view · Enter on this board
Is this page current? All feeds OK
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $124,900 · approved changes $0 · revised $124,900 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
ACTION [Hannah Price] Survey and Layout to book the final alignment survey window by 2026-08-21. watch item MTG-2-15 · Weekly Outage Coordination, day 11 2026-08-15, line 17
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|---|---|---|---|
SV-3800-01 | Machine centerline and survey control | AB | AB | CURRENT |
SV-3800-02 | Frame survey after removal | AB | AB | CURRENT |
SV-RPT-01 | Final alignment survey report, press and dryers | 0 | 0 | CURRENT |
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
SV-3800-01 | Machine centerline and survey control | AB | SURV | 2026-09-27 | Open |
SV-3800-02 | Frame survey after removal | AB | SURV | 2026-09-22 | Open |
SV-RPT-01 | Final alignment survey report, press and dryers | 0 | SURV | 2026-09-23 | Open |
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
No milestones for this trade.
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| SURV-2.1-A20 | 2.1 · A20 | $41,700 | $41,700 | $40,000 | $40,000 |
| SURV-4.3-A20 | 4.3 · A20 | $31,200 | $31,200 | $30,000 | $30,000 |
| SURV-6.1-A20 | 6.1 · A20 | $10,400 | $10,400 | $10,000 | $10,000 |
| SURV-7.1-A10 | 7.1 · A10 | $20,800 | $20,800 | $20,000 | $20,000 |
| SURV-8.3-A20 | 8.3 · A20 | $20,800 | $20,800 | $20,000 | $20,000 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|---|---|---|---|
| 2026-10-22 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-21 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-20 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-19 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-18 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-17 | Benchmark Alignment Survey | read | 0 | 0.0 |
| 2026-10-16 | Benchmark Alignment Survey | read | 0 | 0.0 |
Shift turnover
No turnovers.
Field log
No entries.
Safety observations
2026-08-20 Survey crew wore harnesses tied off at 132 ft on the top-tier dryers. Referred to Site Safety Lead
2026-08-12 Survey crew wore harnesses tied off at 132 ft on the top-tier dryers. Referred to Site Safety Lead
2026-08-04 Survey crew wore harnesses tied off at 132 ft on the top-tier dryers. Referred to Site Safety Lead
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.
Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation
Forms and sign-off cards
- Layout check record
- As-built survey