Delay log
Every schedule delay with its cause, who is responsible, the days lost and the evidence behind it. Slips are found by comparing each P6 upload with the one before.
Slips found in the schedule
No new slips. The next P6 upload is compared with the last one automatically.
Delays
D-001 New press section fabrication late at the OEM Third party CLOSED 9 d
- Trade
- PMGT
- Activities
- FB010
- Cause
- Material delivery
- Dates
- 2026-06-05 to 2026-06-14
- Days lost
- 9 · Entered by Jordan Pike, PM
- Entered
- Jordan Pike, PM on 2026-08-08 · entered on the delay log
Fabrication of the new press section finished 9 workdays late. The press section shipped inside its float; machine down held on its date.
Evidence
No evidence attached. A delay goes to the client with its evidence.
D-002 Press frame anchor bolts seized at removal Client CLOSED 1 d
- Trade
- RIG
- Activities
- RM020
- Cause
- Site condition
- Dates
- 2026-08-09 to 2026-08-10
- Days lost
- 1 · Entered by R. Okafor
- Entered
- R. Okafor on 2026-08-16 · entered on the delay log
Six anchor bolts on the drive-side press frame were seized in their sleeves and had to be burned out. Existing condition of the client's equipment.
Evidence
- Daily log Apex Rigging and Crane 2026-08-09 · Anchor bolts burned out, frame lifted next shift added by R. Okafor 2026-08-16
- Photo IMG_press_frame_anchor_bolts.jpg · Seized bolts after burn-out added by R. Okafor 2026-08-16
D-003 Idler bore IB-2 out of round deeper than surveyed Client CLOSED 1 d
- Trade
- MECH
- Activities
- LB02, LB04, LB05
- Cause
- Site condition
- Dates
- 2026-08-11 to 2026-08-12
- Days lost
- 1 · Entered by Wes Turner
- Entered
- Wes Turner on 2026-08-16 · entered on the delay log
Bore IB-2 needed a third boring pass before the sleeve fit. Line boring shifted a day; idler gear install keeps its float.
Contractor explanation
LB04: Follows delay D-003: Idler bore IB-2 out of round deeper than surveyed. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Precision Line Boring Co, 2026-08-23T13:36:00 · ACCEPTEDLB05: Follows delay D-003: Idler bore IB-2 out of round deeper than surveyed. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Precision Line Boring Co, 2026-08-23T13:36:00 · ACCEPTEDEvidence
- Other Line bore report IB-2, pass 3 · Bore 0.18 mm out of round before the third pass added by Wes Turner 2026-08-16
D-005 New press frame sole plate shims re-cut Subcontractor CLOSED 1 d calculated
- Trade
- RIG
- Activities
- IN010, IN015, IN020, IN030, SY060
- Cause
- Subcontractor performance
- Dates
- 2026-08-19 to 2026-08-20
- Days lost
- 1 · Calculated: IN015 finish moved 2026-08-22 to 2026-08-23 between P6 uploads
- Entered
- R. Okafor on 2026-08-23 · schedule_slip (P6 comparison)
Shim packs under the new press frames were cut to the old sole plate heights and had to be re-cut. Grout, roll install and press alignment each moved a day; the press chain is now on the critical path with no float left.
Contractor explanation
IN015: Follows delay D-005: New press frame sole plate shims re-cut. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Granite Grout and Concrete, 2026-08-23T13:36:00 · ACCEPTEDIN020: Follows delay D-005: New press frame sole plate shims re-cut. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Apex Rigging and Crane, 2026-08-23T13:36:00 · ACCEPTEDIN030: Follows delay D-005: New press frame sole plate shims re-cut. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Benchmark Alignment Survey, 2026-08-23T13:36:00 · ACCEPTEDSY060: Follows delay D-005: New press frame sole plate shims re-cut. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Benchmark Alignment Survey, 2026-08-23T13:36:00 · ACCEPTEDEvidence
- Daily log Apex Rigging and Crane 2026-08-19 · Shims re-cut on site, frames re-set added by R. Okafor 2026-08-23
D-004 Blow box BB-2 supply duct flange does not match Third party CLOSED 3 d calculated
- Trade
- MILL
- Activities
- IB02, IB03, IB04, IB05, IB06
- Cause
- Design, drawing or RFI
- Dates
- 2026-08-20 to 2026-08-26
- Days lost
- 3 · Calculated: IB02 finish moved 2026-08-19 to 2026-08-22 between P6 uploads
- Entered
- Dale Whitaker on 2026-08-23 · schedule_slip (P6 comparison)
The new BB-2 supply flange is drilled to a different bolt circle than the existing duct. AirFlow is sending an adapter flange; BB-3 to BB-6 follow BB-2.
Contractor explanation
IB02: Follows delay D-004: Blow box BB-2 supply duct flange does not match. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-23T13:36:00 · ACCEPTEDIB03: Follows delay D-004: Blow box BB-2 supply duct flange does not match. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-23T13:36:00 · ACCEPTEDIB04: Follows delay D-004: Blow box BB-2 supply duct flange does not match. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-23T13:36:00 · ACCEPTEDIB02: BB-2 cannot be bolted to the existing supply duct: the flange bolt circle does not match. Recovery: Set BB-2 on its supports now; bolt up when the adapter flange arrives. BB-3 to BB-6 continue in order. by 2026-08-25 · General Foreman, Northfield Millwright Services, 2026-08-23T13:35:00 · ACCEPTEDIB05: Follows delay D-004: Blow box BB-2 supply duct flange does not match. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-23T13:36:00 · ACCEPTEDIB06: Follows delay D-004: Blow box BB-2 supply duct flange does not match. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-23T13:36:00 · ACCEPTEDEvidence
- Drawing M-3140-02 rev B · Bolt circle on the drawing vs. as found added by Dale Whitaker 2026-08-23
- Other PO-7730-01 delivery ticket · Adapter flange on site, BB-2 bolted up the same shift added by Dale Whitaker 2026-08-26
D-006 Felt roll FR-02 bearing housing bore undersize at receipt Third party CLOSED 0 d
- Trade
- MILL
- Activities
- IF02
- Cause
- Material delivery
- Dates
- 2026-08-22 to 2026-08-24
- Days lost
- 0 · Entered by Dale Whitaker
- Entered
- Dale Whitaker on 2026-08-24 · entered on the delay log
The FR-02 housing bore measured undersize at receipt. Re-bored on site by the line boring crew at the roll supplier's cost; the roll went in inside its float.
Contractor explanation
IF02: Follows delay D-006: Felt roll FR-02 bearing housing bore undersize at receipt. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-30T09:00:00 · ACCEPTEDIF02: Finish moved inside the activity's float; no successor was held. Recovery: Work follows on as soon as the predecessor is done; crews held on site. · Site Manager, Northfield Millwright Services, 2026-08-30T09:00:00 · ACCEPTEDEvidence
- Other Receiving inspection FR-02 · Bore 0.06 mm under the drawing added by Dale Whitaker 2026-08-24
D-007 As-built alignment reports waited on the final line bore report Subcontractor CLOSED 1 d
- Trade
- PMGT
- Activities
- CL040
- Cause
- Subcontractor performance
- Dates
- 2026-09-26 to 2026-09-27
- Days lost
- 1 · Entered by Jordan Pike, PM
- Entered
- Jordan Pike, PM on 2026-09-26 · entered on the delay log
The line bore report IB-1 to IB-5 came a day late, so the as-built alignment package went to the mill a day after plan. Turnover moved one day; no cost to the mill.
Evidence
No evidence attached. A delay goes to the client with its evidence.