SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Welding and QA/QC ?

Trade lead: Grant Fowler, Owner QA/QC · Everything saved here shows live on the PM and CM screens.

Owner: QA/QC Lead · Readers: Construction Manager, Project Manager · Trades: QAQC · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
1.01
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
3 / 3
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $210,100 · approved changes $0 · revised $210,100 · pending $0 · back-charges open $0 · value returned $0

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

ACTION Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28. watch item MTG-3-23 · Daily Outage Coordination, day 18 2026-08-22, line 16

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
QA-ITP-01Inspection and test plan, mechanical install 22 CURRENT
QA-ITP-02Hydro test procedure, dryers and steam joints 11 CURRENT
QA-RPT-01Hydro test and inspection records, dryers and steam joints 00 CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
QA-ITP-01Inspection and test plan, mechanical install2 QAQC2026-08-09Open
QA-ITP-02Hydro test procedure, dryers and steam joints1 QAQC2026-08-09Open
QA-RPT-01Hydro test and inspection records, dryers and steam joints0 QAQC2026-09-19Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

No milestones for this trade.

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
QAQC-10.2-A9010.2 · A90$77,800$77,800$77,000$77,000
QAQC-2.3-A902.3 · A90$46,700$46,700$46,200$46,200
QAQC-3.1-A803.1 · A80$31,100$31,100$30,800$30,800
QAQC-3.2-A803.2 · A80$38,900$38,900$38,500$38,500
QAQC-8.1-A308.1 · A30$7,800$7,800$7,700$7,700
QAQC-8.4-A208.4 · A20$7,800$7,800$7,700$7,700
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
Source: daily_log

Shift turnover

2026-09-03 DAYS AGREE
Lead: Punch walk done; 41 items, none holding startup
Contractor: Mechanically complete
Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-09-12 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead

2026-09-07 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead

2026-09-02 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead

2026-08-28 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • NDT request
  • Weld log
  • Non-conformance report