Trade lead: Grant Fowler, Owner QA/QC · Everything saved here shows live on the PM and CM screens.
Owner: QA/QC Lead · Readers: Construction Manager, Project Manager · Trades: QAQC · Foreman view · Enter on this board
Is this page current? All feeds OK
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $210,100 · approved changes $0 · revised $210,100 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
ACTION Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28. watch item MTG-3-23 · Daily Outage Coordination, day 18 2026-08-22, line 16
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|---|---|---|---|
QA-ITP-01 | Inspection and test plan, mechanical install | 2 | 2 | CURRENT |
QA-ITP-02 | Hydro test procedure, dryers and steam joints | 1 | 1 | CURRENT |
QA-RPT-01 | Hydro test and inspection records, dryers and steam joints | 0 | 0 | CURRENT |
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
QA-ITP-01 | Inspection and test plan, mechanical install | 2 | QAQC | 2026-08-09 | Open |
QA-ITP-02 | Hydro test procedure, dryers and steam joints | 1 | QAQC | 2026-08-09 | Open |
QA-RPT-01 | Hydro test and inspection records, dryers and steam joints | 0 | QAQC | 2026-09-19 | Open |
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
No milestones for this trade.
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| QAQC-10.2-A90 | 10.2 · A90 | $77,800 | $77,800 | $77,000 | $77,000 |
| QAQC-2.3-A90 | 2.3 · A90 | $46,700 | $46,700 | $46,200 | $46,200 |
| QAQC-3.1-A80 | 3.1 · A80 | $31,100 | $31,100 | $30,800 | $30,800 |
| QAQC-3.2-A80 | 3.2 · A80 | $38,900 | $38,900 | $38,500 | $38,500 |
| QAQC-8.1-A30 | 8.1 · A30 | $7,800 | $7,800 | $7,700 | $7,700 |
| QAQC-8.4-A20 | 8.4 · A20 | $7,800 | $7,800 | $7,700 | $7,700 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|
Shift turnover
Field log
No entries.
Safety observations
2026-09-12 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead
2026-09-07 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead
2026-09-02 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead
2026-08-28 Punch walk party kept to the marked walkway with operations running. Referred to Site Safety Lead
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.
Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation
Forms and sign-off cards
- NDT request
- Weld log
- Non-conformance report