Lifecycle
Preconstruction to closeout. Tick a gate item when it is done; the name you enter is recorded with the date.
Preconstruction COMPLETE
2025-11-26 → 2025-12-28 · 5 of 5 done
- Contract and scope of work signedDone 2025-12-26 by Jordan Pike, PM
- Baseline schedule approvedDone 2025-12-26 by Jordan Pike, PM
- Budget and cost codes set upDone 2025-12-26 by Jordan Pike, PM
- Site safety plan approvedDone 2025-12-26 by Jordan Pike, PM
- Trade contractors awardedDone 2025-12-26 by Jordan Pike, PM
Source: gate_item
Engineering and Procurement COMPLETE
2025-12-28 → 2026-07-13 · 4 of 4 done
- Issued for construction drawings receivedDone 2026-01-27 by Jordan Pike, PM
- Long-lead equipment orderedDone 2026-01-27 by Jordan Pike, PM
- Material delivery schedule agreedDone 2026-01-27 by Jordan Pike, PM
- Inspection and test plans approvedDone 2026-01-27 by Jordan Pike, PM
Source: gate_item
Construction COMPLETE
2026-07-13 → 2026-09-03 · 5 of 5 done
- Mobilization completeDone 2026-07-22 by Jordan Pike, PM
- Foundations completeDone 2026-07-22 by Jordan Pike, PM
- Equipment setDone 2026-08-28 by Jordan Pike, PM
- Piping and E&I installedDone 2026-09-01 by Jordan Pike, PM
- Mechanical completion walkdownDone 2026-09-03 by Jordan Pike, PM
Source: gate_item
Commissioning and Startup COMPLETE
2026-09-03 → 2026-09-15 · 4 of 4 done
- Pre-commissioning checks completeDone 2026-09-03 by Jordan Pike, PM
- Loop checks completeDone 2026-09-03 by Jordan Pike, PM
- Systems energizedDone 2026-09-04 by Jordan Pike, PM
- Performance tests passedDone 2026-09-11 by Jordan Pike, PM
Source: gate_item
Turnover and Closeout CURRENT
2026-09-15 → 2026-10-23 · 5 of 5 done
- Punch list closedDone 2026-09-21 by Jordan Pike, PM
- Turnover packages acceptedDone 2026-09-21 by Jordan Pike, PM
- As-built drawings deliveredDone 2026-09-27 by Jordan Pike, PM
- Final cost report issuedDone 2026-10-07 by Jordan Pike, PM
- Lessons learned recordedDone 2026-10-05 by Jordan Pike, PM
Source: gate_item