XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Lifecycle

Preconstruction to closeout. Tick a gate item when it is done; the name you enter is recorded with the date.

Preconstruction 2025-11-26 → 2025-12-28 5 / 5 gates Engineering and Procurement 2025-12-28 → 2026-07-13 4 / 4 gates Construction 2026-07-13 → 2026-09-03 5 / 5 gates Commissioning and Startup 2026-09-03 → 2026-09-15 4 / 4 gates Turnover and Closeout 2026-09-15 → 2026-10-23 5 / 5 gates

Preconstruction COMPLETE

2025-11-26 → 2025-12-28 · 5 of 5 done

  • Contract and scope of work signedDone 2025-12-26 by Jordan Pike, PM
  • Baseline schedule approvedDone 2025-12-26 by Jordan Pike, PM
  • Budget and cost codes set upDone 2025-12-26 by Jordan Pike, PM
  • Site safety plan approvedDone 2025-12-26 by Jordan Pike, PM
  • Trade contractors awardedDone 2025-12-26 by Jordan Pike, PM
Source: gate_item

Engineering and Procurement COMPLETE

2025-12-28 → 2026-07-13 · 4 of 4 done

  • Issued for construction drawings receivedDone 2026-01-27 by Jordan Pike, PM
  • Long-lead equipment orderedDone 2026-01-27 by Jordan Pike, PM
  • Material delivery schedule agreedDone 2026-01-27 by Jordan Pike, PM
  • Inspection and test plans approvedDone 2026-01-27 by Jordan Pike, PM
Source: gate_item

Construction COMPLETE

2026-07-13 → 2026-09-03 · 5 of 5 done

  • Mobilization completeDone 2026-07-22 by Jordan Pike, PM
  • Foundations completeDone 2026-07-22 by Jordan Pike, PM
  • Equipment setDone 2026-08-28 by Jordan Pike, PM
  • Piping and E&I installedDone 2026-09-01 by Jordan Pike, PM
  • Mechanical completion walkdownDone 2026-09-03 by Jordan Pike, PM
Source: gate_item

Commissioning and Startup COMPLETE

2026-09-03 → 2026-09-15 · 4 of 4 done

  • Pre-commissioning checks completeDone 2026-09-03 by Jordan Pike, PM
  • Loop checks completeDone 2026-09-03 by Jordan Pike, PM
  • Systems energizedDone 2026-09-04 by Jordan Pike, PM
  • Performance tests passedDone 2026-09-11 by Jordan Pike, PM
Source: gate_item

Turnover and Closeout CURRENT

2026-09-15 → 2026-10-23 · 5 of 5 done

  • Punch list closedDone 2026-09-21 by Jordan Pike, PM
  • Turnover packages acceptedDone 2026-09-21 by Jordan Pike, PM
  • As-built drawings deliveredDone 2026-09-27 by Jordan Pike, PM
  • Final cost report issuedDone 2026-10-07 by Jordan Pike, PM
  • Lessons learned recordedDone 2026-10-05 by Jordan Pike, PM