SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Piping ?

Trade lead: Marcus Lee, Ironwood Piping · Everything saved here shows live on the PM and CM screens.

Owner: Piping Lead · Readers: Construction Manager, Project Manager · Trades: PIPE · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
0.98
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
4 / 4
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $1,320,100 · approved changes $232,500 · revised $1,552,600 · pending $0 · back-charges open $0 · value returned $0

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

ACTION Marcus Lee to confirm the condensate header replacement spool dimensions for SY010 by 2026-08-17. watch item MTG-2-14 · Weekly Outage Coordination, day 11 2026-08-15, line 16

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
P-3300-ISO-01Steam joint and syphon isometric, D-01 to D-07 ABAB CURRENT
P-3300-ISO-02Steam joint and syphon isometric, D-08 to D-14 ABAB CURRENT
P-3300-ISO-05Condensate header replacement (CO-001) ABAB CURRENT
P-PID-330Dryer steam and condensate P&ID ABAB CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
P-3300-ISO-01Steam joint and syphon isometric, D-01 to D-07AB PIPE2026-09-23Open
P-3300-ISO-02Steam joint and syphon isometric, D-08 to D-14AB PIPE2026-09-24Open
P-3300-ISO-05Condensate header replacement (CO-001)AB PIPE2026-09-25Open
P-PID-330Dryer steam and condensate P&IDAB PIPE2026-09-26Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

No milestones for this trade.

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
PIPE-2.2-A902.2 · A90$404,100$404,100$412,200$412,200
PIPE-4.2-A804.2 · A80$673,500$673,500$687,000$687,000
PIPE-5.1-A305.1 · A30$53,900$53,900$55,000$55,000
PIPE-8.1-A308.1 · A30$421,100$421,100$429,500$429,500
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
2026-10-22Ironwood Piping read 00.0
2026-10-21Ironwood Piping read 00.0
2026-10-20Ironwood Piping read 00.0
2026-10-19Ironwood Piping read 00.0
2026-10-18Ironwood Piping read 00.0
2026-10-17Ironwood Piping read 00.0
2026-10-16Ironwood Piping read 00.0
Hours per task are MISSING: contractor logs do not carry them
Source: daily_log

Shift turnover

No turnovers.

Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-09-16 Hydro test boundary barricaded and signed; good. Referred to Site Safety Lead

2026-09-09 Hydro test boundary barricaded and signed; good. Referred to Site Safety Lead

2026-09-04 Hydro test boundary barricaded and signed; good. Referred to Site Safety Lead

2026-08-30 Hydro test boundary barricaded and signed; good. Referred to Site Safety Lead

2026-08-25 Hydro test boundary barricaded and signed; good. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • Hydro test package
  • Weld map sign-off
  • Line walkdown
Source: board settings