SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Paper Machine 3 Press and Dryer Section Rebuild ?

Demo Paper Mill · Pulp and paper outage rebuild · Demo Mill, PM3 · 2025-11-26 to 2026-10-23

Preconstruction 2025-11-26 → 2025-12-28 5 / 5 gates Engineering and Procurement 2025-12-28 → 2026-07-13 4 / 4 gates Construction 2026-07-13 → 2026-09-03 5 / 5 gates Commissioning and Startup 2026-09-03 → 2026-09-15 4 / 4 gates Turnover and Closeout 2026-09-15 → 2026-10-23 5 / 5 gates

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
0 recordables
TRIR 0.00 calc · supervision trained 100%
Source: safety_observation, safety_pretask, safety_toolbox, safety_inspection, safety_permit, safety_action, safety_stop_work, safety_incident, daily_log, training_attempt, safety_card
Activities complete
165 / 165
Source: activity
Late activities
0
Source: activity
Budget
$33,509,500
Source: cost_account
Forecast at completion
$33,553,000
Source: cost_account
Cost performance (CPI) calculated
1.00
Source: cost_account, activity · earned value / actual cost, trades with a cost source
$33,509,500
approved changes $1,144,200 · 0 pending ($0) · value returned $11,450
Source: cost_account, change_order, backcharge
0
of 14 PO lines · 0 with no promise date
Source: material_item, activity

Schedule and budget by trade

TradeTrade leadActivitiesCompleteLate% completeBudgetEarnedActualForecastCPI
Millwrights Dale Whitaker 101101 0 100% $3,330,100$3,330,100$3,356,900$3,356,900 0.99
Rigging and Heavy Lift R. Okafor 66 0 100% $1,140,500$1,140,500$1,174,700$1,174,700 0.97
Piping Marcus Lee 55 0 100% $1,552,600$1,552,600$1,583,700$1,583,700 0.98
Electrical and Instrumentation Priya Raman 44 0 100% $1,616,800$1,616,800$1,592,500$1,592,500 1.02
Scaffolding Tony Alvarez 33 0 100% $609,900$609,900$609,900$609,900 1.00
Insulation Beth Carver 11 0 100% $384,600$384,600$384,600$384,600 1.00
Concrete Luis Ortega 11 0 100% $150,000$150,000$151,500$151,500 0.99
Survey and Layout Hannah Price 55 0 100% $124,900$124,900$120,000$120,000 1.04
Welding and QA/QC Grant Fowler 66 0 100% $210,100$210,100$207,900$207,900 1.01
Commissioning Nina Brooks 55 0 100% $600,000$600,000$582,000$582,000 1.03
Line Boring and Machining Wes Turner 66 0 100% $608,000$608,000$595,800$595,800 1.02
Project Management and Procurement Jordan Pike 2222 0 100% $23,182,000$23,182,000$23,193,500$23,193,500 1.00
Source: activity, cost_account · schedule and cost join on WBS, area and trade · nothing is estimated

Live from the boards updates by itself

  • 16:00 · Elena Varga, CM released a client report
  • 11:00 · Elena Varga, CM updated the delay log
  • 15:00 · Jordan Pike, PM updated changes
  • 11:00 · Document Controller loaded a drawing revision
  • 16:00 · Jordan Pike, PM updated a meeting
  • 10:00 · Elena Varga, CM updated a pay app
  • 13:48 · Survey and Layout · Hannah Price added a field log entry
  • 13:30 · Dale Whitaker updated schedule progress
  • 13:15 · Line Boring and Machining · Wes Turner added a turnover
  • 12:58 · R. Okafor updated a lift plan
  • 12:40 · Rigging and Heavy Lift · R. Okafor added a watch item
  • 12:25 · Millwrights · Dale Whitaker added a field log entry
Source: live_event · every saved change on the project

Trades needing attention

BoardOverdue itemsBlockedNeeds a decision
Millwrights 0 0 None
Rigging and Heavy Lift 0 0 None
Piping 0 0 None
Electrical and Instrumentation 0 0 None
Scaffolding 0 0 None
Insulation 0 0 None
Concrete 0 0 None
Survey and Layout 0 0 None
Welding and QA/QC 0 0 None
Commissioning 0 0 None
Line Boring and Machining 0 0 None
Project Management and Procurement 0 0 None
Source: watch_item (same as the CM roll-up)

Next milestones

No open milestones in the schedule.

Source: activity

Schedule delays

7 delays logged.

ResponsibleDelaysDays lost
Third party312
Client22
Subcontractor22

Client delay report Contractors Delay log

Source: delay, schedule_slip · each delay counted once; overlapping delays are not added into one project delay

Meetings

2026-10-05 Closeout and Lessons Learned Review 4 items, 0 waiting

2026-08-22 Daily Outage Coordination, day 18 6 items, 0 waiting

2026-08-15 Weekly Outage Coordination, day 11 8 items, 0 waiting

Source: meeting, meeting_item