Line Boring and Machining
Trade lead: Wes Turner, Precision Line Boring Co · Everything saved here shows live on the PM and CM screens.
Owner: Line Boring and Machining Lead · Readers: Construction Manager, Project Manager · Trades: MECH · Foreman view · Enter on this board
Is this page current? All feeds OK
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $460,000 · approved changes $148,000 · revised $608,000 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
DECISION Line Boring and Machining runs IB-3 to IB-5 on nights so the idler gears keep their dates. in decision register · Weekly Outage Coordination, day 11 2026-08-15, line 11
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|---|---|---|---|
MB-3900-01 | Line bore and sleeve procedure, IB-1 to IB-5 | C | C | CURRENT |
MB-3900-02 | Idler bore sleeve detail | AB | AB | CURRENT |
MB-RPT-01 | Line bore report, IB-1 to IB-5 | 0 | 0 | CURRENT |
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
MB-3900-01 | Line bore and sleeve procedure, IB-1 to IB-5 | C | MECH | 2026-08-09 | Open |
MB-3900-02 | Idler bore sleeve detail | AB | MECH | 2026-09-24 | Open |
MB-RPT-01 | Line bore report, IB-1 to IB-5 | 0 | MECH | 2026-09-26 | Open |
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
No milestones for this trade.
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| MECH-2.1-A90 | 2.1 · A90 | $189,400 | $189,400 | $185,600 | $185,600 |
| MECH-6.2-A30 | 6.2 · A30 | $418,600 | $418,600 | $410,200 | $410,200 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|---|---|---|---|
| 2026-10-22 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-21 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-20 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-19 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-18 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-17 | Precision Line Boring Co | read | 0 | 0.0 |
| 2026-10-16 | Precision Line Boring Co | read | 0 | 0.0 |
Shift turnover
Field log
No entries.
Safety observations
2026-08-17 Boring bar guard in place, area roped off, chips cleaned up at shift change. Referred to Site Safety Lead
2026-08-09 Boring bar guard in place, area roped off, chips cleaned up at shift change. Referred to Site Safety Lead
2026-07-30 Boring bar guard in place, area roped off, chips cleaned up at shift change. Referred to Site Safety Lead
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.