SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Rigging and Heavy Lift ?

Trade lead: R. Okafor, Apex Rigging and Crane · Everything saved here shows live on the PM and CM screens.

Owner: Lift Supervisor · Readers: Construction Manager, Project Manager · Trades: RIG · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
0.97
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
2 / 2
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $1,150,100 · approved changes -$9,600 · revised $1,140,500 · pending $0 · back-charges open $0 · value returned $9,600

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

DECISION Press roll install IN020 starts only after the grout cure check passes. in decision register · Daily Outage Coordination, day 18 2026-08-22, line 11

ACTION R. Okafor to set the 250 t crane on the north pad for the press roll picks by 2026-08-23. watch item MTG-3-24 · Daily Outage Coordination, day 18 2026-08-22, line 17

DECISION The machine room crane sets the blow boxes; no second mobile crane day (change order CO-004). in decision register · Weekly Outage Coordination, day 11 2026-08-15, line 12

ACTION [R. Okafor] Issue the critical lift review for the press rolls IN020 by 2026-08-20. watch item MTG-2-13 · Weekly Outage Coordination, day 11 2026-08-15, line 15

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
RIG-3200-01Mobile crane set-up, north pad and roof hatch ABAB CURRENT
RIG-3200-02Machine room crane rigging arrangement, dryers ABAB CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
RIG-3200-01Mobile crane set-up, north pad and roof hatchAB RIG2026-09-27Open
RIG-3200-02Machine room crane rigging arrangement, dryersAB RIG2026-09-22Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

No milestones for this trade.

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
RIG-2.1-A902.1 · A90$530,800$530,800$546,700$546,700
RIG-4.3-A204.3 · A20$88,500$88,500$91,200$91,200
RIG-5.2-A105.2 · A10$221,200$221,200$227,800$227,800
RIG-7.1-A107.1 · A10$300,000$300,000$309,000$309,000
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
2026-10-22Apex Rigging and Crane read 00.0
2026-10-21Apex Rigging and Crane read 00.0
2026-10-20Apex Rigging and Crane read 00.0
2026-10-19Apex Rigging and Crane read 00.0
2026-10-18Apex Rigging and Crane read 00.0
2026-10-17Apex Rigging and Crane read 00.0
2026-10-16Apex Rigging and Crane read 00.0
Hours per task are MISSING: contractor logs do not carry them
Source: daily_log

Shift turnover

2026-08-27 DAYS AGREE
Lead: Press rolls in; crane released after IN020
Contractor: Press install complete
2026-08-22 DAYS AGREE
Lead: Press frames set; crane re-rigged for rolls
Contractor: Press frames complete
Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-09-14 Outrigger mats re-checked after rain before the press roll picks; good. Referred to Site Safety Lead

2026-09-08 Outrigger mats re-checked after rain before the press roll picks; good. Referred to Site Safety Lead

2026-09-03 Outrigger mats re-checked after rain before the press roll picks; good. Referred to Site Safety Lead

2026-08-29 Outrigger mats re-checked after rain before the press roll picks; good. Referred to Site Safety Lead

2026-08-24 Outrigger mats re-checked after rain before the press roll picks; good. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • Critical lift plan
  • Crane inspection
  • Ground bearing check
Source: board settings