SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Electrical and Instrumentation ?

Trade lead: Priya Raman, Delta Electric and Controls · Everything saved here shows live on the PM and CM screens.

Owner: E&I Lead · Readers: Construction Manager, Project Manager · Trades: EI · Foreman view · Enter on this board

Is this page current? All feeds OK

CM look-ahead OK 3 h ago · expected every 24 h
Contractor daily logs OK 71 min ago · expected every 24 h
Cost report OK 9 h ago · expected every 7 d
Doc control drawings OK 51 min ago · expected every 24 h
Meeting records OK 22 h ago · expected every 7 d
Procurement register OK 26 h ago · expected every 7 d
Schedule (P6 export) OK 41 min ago · expected every 24 h
Watch list register OK 21 min ago · expected every 24 h
Late activities
0
Planned finish before today, no actual finish
Source: activity
Due in 7 days
0
Planned finish in the next 7 days
Source: activity
Percent complete calculated
100%
Source: activity · inputs: activity.pct_complete (simple average)
Cost performance (CPI) calculated
1.02
Cost performance index: earned value / actual cost
Source: cost_account · inputs: cost_account.budget, cost_account.actual, activity.pct_complete
Drawings current
2 / 2
Sheets held at the revision doc control holds
Source: drawing

Exceptions requiring attention

Nothing past its needed-by date.

Source: watch_item

Watch list profile

Source: watch_item

Delays on this trade

No open delays on this trade.

Source: delay, schedule_slip

Changes and back-charges

Budget $1,380,000 · approved changes $236,800 · revised $1,616,800 · pending $0 · back-charges open $0 · value returned $0

No pending change orders or open back-charges.

Source: cost_account, change_order, backcharge

From front-end loading

No open front-end findings on this trade.

Source: fel_finding, activity, schedule_slip, delay, material_item, missed_date

From meetings

ACTION Priya Raman to confirm the drive firmware version for SY040 with the client by 2026-08-22. watch item MTG-2-16 · Weekly Outage Coordination, day 11 2026-08-15, line 18

Source: meeting, meeting_item

Next shifts

ActivityAreaContractorPlanned%
Source: activity

Crane sequence

No lifts in the next 7 days.

Source: activity

Drawings

NumberTitleHeldDoc controlStatus
E-3400-01Dryer section drive one-line ABAB CURRENT
E-3410-01Instrument loop diagrams, dryer section ABAB CURRENT
Source: drawing

Prints for this trade ?

Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.

NumberTitleRevTradeReceived
E-3400-01Dryer section drive one-lineAB EI2026-09-27Open
E-3410-01Instrument loop diagrams, dryer sectionAB EI2026-09-22Open
Source: doc_file (current revisions)

Photos: progress and evidence

No photo yet

No photos yet. Use Take a photo on a phone or tablet to open the camera.

Source: board_photo · each photo keeps who took it, when, and a SHA-256 fingerprint

Milestones

No milestones for this trade.

Source: activity

Budget and earned value calculated

AccountWBSBudgetEarnedActualForecast
EI-2.2-A902.2 · A90$766,700$766,700$755,200$755,200
EI-4.2-A304.2 · A30$460,000$460,000$453,100$453,100
EI-5.1-A305.1 · A30$38,300$38,300$37,700$37,700
EI-8.2-A308.2 · A30$351,800$351,800$346,500$346,500
Source: cost_account, activity · Earned = budget × average percent complete of activities on the same WBS, area and trade

Manpower and daily logs

DateContractorLogHeadcountCrew hours
2026-10-22Delta Electric and Controls read 00.0
2026-10-21Delta Electric and Controls read 00.0
2026-10-20Delta Electric and Controls read 00.0
2026-10-19Delta Electric and Controls read 00.0
2026-10-18Delta Electric and Controls read 00.0
2026-10-17Delta Electric and Controls read 00.0
2026-10-16Delta Electric and Controls read 00.0
Hours per task are MISSING: contractor logs do not carry them
Source: daily_log

Shift turnover

No turnovers.

Source: shift_turnover

Field log

No entries.

Source: field_entry

Safety observations

2026-09-17 Every drive locked and tried before the coupling work; good. Referred to Site Safety Lead

2026-09-09 Every drive locked and tried before the coupling work; good. Referred to Site Safety Lead

2026-09-04 Every drive locked and tried before the coupling work; good. Referred to Site Safety Lead

2026-08-30 Every drive locked and tried before the coupling work; good. Referred to Site Safety Lead

2026-08-25 Every drive locked and tried before the coupling work; good. Referred to Site Safety Lead

Observations only. Referred to the site safety lead.
Source: safety_observation

Enter on this board

Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.

Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation

Observations only. Incidents and injuries go through the site safety process, not this board.

Forms and sign-off cards

  • Cable pull record
  • Megger test record
  • Loop check sheet
Source: board settings