Millwrights
Trade lead: Dale Whitaker, Northfield Millwright Services · Everything saved here shows live on the PM and CM screens.
Owner: Millwright Lead · Readers: Construction Manager, Project Manager · Trades: MILL · Foreman view · Enter on this board
Is this page current? All feeds OK
Exceptions requiring attention
Nothing past its needed-by date.
Watch list profile
Delays on this trade
No open delays on this trade.
Changes and back-charges
Budget $3,250,200 · approved changes $79,900 · revised $3,330,100 · pending $0 · back-charges open $0 · value returned $0
No pending change orders or open back-charges.
From front-end loading
No open front-end findings on this trade.
From meetings
DECISION Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives. in decision register · Daily Outage Coordination, day 18 2026-08-22, line 10
ACTION Dale Whitaker to chase the BB-2 adapter flange with the blow box supplier by 2026-08-23. watch item MTG-3-21 · Daily Outage Coordination, day 18 2026-08-22, line 14
DATE All 14 dryers set by 2026-08-23 (ID14). watch item MTG-2-17 · Weekly Outage Coordination, day 11 2026-08-15, line 21
Next shifts
| Activity | Area | Contractor | Planned | % |
|---|
Crane sequence
No lifts in the next 7 days.
Drawings
| Number | Title | Held | Doc control | Status |
|---|---|---|---|---|
M-3100-01 | Dryer section general arrangement | AB | AB | CURRENT |
M-3110-01 | Dryer bearing housing and journal details | AB | AB | CURRENT |
M-3120-01 | Gear train layout, bull and idler gears | AB | AB | CURRENT |
M-3130-01 | Felt run layout, top and bottom felts | AB | AB | CURRENT |
M-3140-02 | Blow box arrangement and supply ducts | AB | AB | CURRENT |
Prints for this trade
Current revisions only, filed by trade as they are received. Older revisions are kept by the PM.
| Number | Title | Rev | Trade | Received | |
|---|---|---|---|---|---|
M-3100-01 | Dryer section general arrangement | AB | MILL | 2026-09-22 | Open |
M-3110-01 | Dryer bearing housing and journal details | AB | MILL | 2026-09-23 | Open |
M-3120-01 | Gear train layout, bull and idler gears | AB | MILL | 2026-09-24 | Open |
M-3130-01 | Felt run layout, top and bottom felts | AB | MILL | 2026-09-25 | Open |
M-3140-02 | Blow box arrangement and supply ducts | AB | MILL | 2026-09-26 | Open |
Photos: progress and evidence
No photos yet. Use Take a photo on a phone or tablet to open the camera.
Milestones
No milestones for this trade.
Budget and earned value calculated
| Account | WBS | Budget | Earned | Actual | Forecast |
|---|---|---|---|---|---|
| MILL-2.1-A90 | 2.1 · A90 | $383,900 | $383,900 | $387,000 | $387,000 |
| MILL-3.5-A80 | 3.5 · A80 | $204,700 | $204,700 | $206,300 | $206,300 |
| MILL-4.1-A80 | 4.1 · A80 | $128,000 | $128,000 | $129,000 | $129,000 |
| MILL-5.1-A20 | 5.1 · A20 | $51,200 | $51,200 | $51,600 | $51,600 |
| MILL-5.3-A20 | 5.3 · A20 | $332,700 | $332,700 | $335,400 | $335,400 |
| MILL-5.4-A20 | 5.4 · A20 | $153,500 | $153,500 | $154,700 | $154,700 |
| MILL-5.5-A30 | 5.5 · A30 | $358,300 | $358,300 | $361,200 | $361,200 |
| MILL-5.6-A20 | 5.6 · A20 | $358,300 | $358,300 | $361,200 | $361,200 |
| MILL-7.2-A20 | 7.2 · A20 | $358,300 | $358,300 | $361,200 | $361,200 |
| MILL-7.3-A30 | 7.3 · A30 | $358,300 | $358,300 | $361,200 | $361,200 |
| MILL-7.4-A20 | 7.4 · A20 | $370,900 | $370,900 | $373,900 | $373,900 |
| MILL-7.5-A20 | 7.5 · A20 | $195,200 | $195,200 | $196,800 | $196,800 |
| MILL-8.3-A30 | 8.3 · A30 | $51,200 | $51,200 | $51,600 | $51,600 |
| MILL-9-A20 | 9 · A20 | $25,600 | $25,600 | $25,800 | $25,800 |
Manpower and daily logs
| Date | Contractor | Log | Headcount | Crew hours |
|---|---|---|---|---|
| 2026-10-22 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-21 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-20 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-19 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-18 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-17 | Northfield Millwright Services | read | 0 | 0.0 |
| 2026-10-16 | Northfield Millwright Services | read | 0 | 0.0 |
Shift turnover
Field log
No entries.
Safety observations
2026-09-21 Final walk with operations: laydown and trailers cleared, no open permits, no recordable injuries on the job. Referred to Site Safety Lead
2026-09-20 Felt hanging crew briefed on nip points before the rolls turned. Referred to Site Safety Lead
2026-09-15 Gear guard left off after the backlash check; refitted before the jog. Referred to Site Safety Lead
2026-09-13 Housekeeping on the operating floor after demob; good. Referred to Site Safety Lead
2026-09-11 Felt hanging crew briefed on nip points before the rolls turned. Referred to Site Safety Lead
Enter on this board
Each entry records your name. Changes show on this board, the CM roll-up and the master board straight away.
Watch list: add or change an item
Record a decision
Add a shift turnover
Add a field log entry
Record a safety observation
Forms and sign-off cards
- Shaft alignment record
- Bearing installation record
- Run-in sheet