Apex Rigging and Crane
Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors
Missed dates needing your explanation (0)
Nothing outstanding. Every missed date has an explanation on record.
Explanations on record
IN020 Install press rolls, suction roll and felt run
ACCEPTEDMissed 2026-08-26, now 2026-08-27 (+1 d) · Subcontractor performance
Follows delay D-005: New press frame sole plate shims re-cut.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Apex Rigging and Crane at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
Pay applications
Contract $1,110,400 (includes approved changes -$9,600) · certified to date $1,110,400 · retainage held $111,040 · paid $999,360
| No. | Period end | Claimed to date | Certified to date | Retainage | Back-charges off | Payment due | Status |
|---|---|---|---|---|---|---|---|
| 3 | 2026-09-21 | $1,110,400 | $1,110,400 | $111,040 | $423,360 | PAID | |
| 2 | 2026-08-19 | $640,000 | $640,000 | $64,000 | $387,000 | PAID | |
| 1 | 2026-07-25 | $210,000 | $210,000 | $21,000 | $189,000 | PAID |
Back-charges for errors on this scope
When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.
No back-charges on this scope.
Delays covering this scope
D-002 Press frame anchor bolts seized at removal Client · CLOSED
D-005 New press frame sole plate shims re-cut Subcontractor · CLOSED
Activities
| Activity | Trade | Planned | Actual finish | % |
|---|---|---|---|---|
EN050 Lift plans: press section, dryers, gears, rolls | RIG | 2025-12-14 → 2025-12-26 | 2025-12-26 | 100 |
PR050 Machine room crane inspection and load test | RIG | 2026-07-14 → 2026-07-15 | 2026-07-15 | 100 |
RM010 Remove the old press section: rolls and felt run | RIG | 2026-08-06 → 2026-08-08 | 2026-08-08 | 100 |
RM020 Remove press section frames and sole plates | RIG | 2026-08-09 → 2026-08-11 | 2026-08-11 | 100 |
IN010 Set new press frames and sole plates | RIG | 2026-08-17 → 2026-08-20 | 2026-08-20 | 100 |
IN020 Install press rolls, suction roll and felt run | RIG | 2026-08-24 → 2026-08-27 | 2026-08-27 | 100 |