Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

IN020 Install press rolls, suction roll and felt run ACCEPTED

Missed 2026-08-26, now 2026-08-27 (+1 d) · Subcontractor performance

Follows delay D-005: New press frame sole plate shims re-cut.

Recovery: Work follows on as soon as the predecessor is done; crews held on site.

Submitted by Site Manager, Apex Rigging and Crane at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23

Source: missed_date, missed_date_doc

Pay applications

Contract $1,110,400 (includes approved changes -$9,600) · certified to date $1,110,400 · retainage held $111,040 · paid $999,360

No.Period endClaimed to dateCertified to dateRetainageBack-charges offPayment dueStatus
32026-09-21$1,110,400 $1,110,400 $111,040 $423,360 PAID
22026-08-19$640,000 $640,000 $64,000 $387,000 PAID
12026-07-25$210,000 $210,000 $21,000 $189,000 PAID

Submit the next application

Agreed back-charges are taken off when the application is certified.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

D-002 Press frame anchor bolts seized at removal Client · CLOSED

D-005 New press frame sole plate shims re-cut Subcontractor · CLOSED

Source: delay

Activities

ActivityTradePlannedActual finish%
EN050 Lift plans: press section, dryers, gears, rollsRIG 2025-12-14 → 2025-12-262025-12-26 100
PR050 Machine room crane inspection and load testRIG 2026-07-14 → 2026-07-152026-07-15 100
RM010 Remove the old press section: rolls and felt runRIG 2026-08-06 → 2026-08-082026-08-08 100
RM020 Remove press section frames and sole platesRIG 2026-08-09 → 2026-08-112026-08-11 100
IN010 Set new press frames and sole platesRIG 2026-08-17 → 2026-08-202026-08-20 100
IN020 Install press rolls, suction roll and felt runRIG 2026-08-24 → 2026-08-272026-08-27 100