SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Granite Grout and Concrete ?

Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

IN015 Grout press sole plates and cure ACCEPTED

Missed 2026-08-22, now 2026-08-23 (+1 d) · Subcontractor performance

Follows delay D-005: New press frame sole plate shims re-cut.

Recovery: Work follows on as soon as the predecessor is done; crews held on site.

Submitted by Site Manager, Granite Grout and Concrete at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23

Source: missed_date, missed_date_doc

Pay applications

Contract $148,000 · certified to date $148,000 · retainage held $7,400 · paid $140,600

No.Period endClaimed to dateCertified to dateRetainageBack-charges offPayment dueStatus
12026-09-21$148,000 $148,000 $7,400 $140,600 PAID

Submit the next application

Agreed back-charges are taken off when the application is certified.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

D-005 New press frame sole plate shims re-cut Subcontractor · CLOSED

Source: delay

Activities

ActivityTradePlannedActual finish%
IN015 Grout press sole plates and cureCONC 2026-08-21 → 2026-08-232026-08-23 100
Source: activity

Until sign-in by role is built, anyone with the link can submit here; every submission records the name given and the time.