Northfield Millwright Services
Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors
Missed dates needing your explanation (0)
Nothing outstanding. Every missed date has an explanation on record.
Explanations on record
IF07 Install felt roll FR-07 (top felt)
ACCEPTEDMissed 2026-08-27, now 2026-08-30 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IF07 Install felt roll FR-07 (top felt)
ACCEPTEDMissed 2026-08-24, now 2026-08-27 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IB06 Install blow box BB-6
ACCEPTEDMissed 2026-08-23, now 2026-08-26 (+3 d) · Design, drawing or RFI
Follows delay D-004: Blow box BB-2 supply duct flange does not match.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
IF06 Install felt roll FR-06 (top felt)
ACCEPTEDMissed 2026-08-23, now 2026-08-26 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IB02 Install blow box BB-2
ACCEPTEDMissed 2026-08-22 · Design, drawing or RFI
BB-2 cannot be bolted to the existing supply duct: the flange bolt circle does not match.
Recovery: Set BB-2 on its supports now; bolt up when the adapter flange arrives. BB-3 to BB-6 continue in order. by 2026-08-25
Submitted by General Foreman, Northfield Millwright Services at 2026-08-23T13:35:00 · accepted by Elena Varga, CM on 2026-08-30
IB05 Install blow box BB-5
ACCEPTEDMissed 2026-08-22, now 2026-08-25 (+3 d) · Design, drawing or RFI
Follows delay D-004: Blow box BB-2 supply duct flange does not match.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
IF02 Install felt roll FR-02 (top felt)
ACCEPTEDMissed 2026-08-22 · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IF05 Install felt roll FR-05 (top felt)
ACCEPTEDMissed 2026-08-22, now 2026-08-25 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IB04 Install blow box BB-4
ACCEPTEDMissed 2026-08-21, now 2026-08-24 (+3 d) · Design, drawing or RFI
Follows delay D-004: Blow box BB-2 supply duct flange does not match.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
IF04 Install felt roll FR-04 (top felt)
ACCEPTEDMissed 2026-08-21, now 2026-08-24 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IB03 Install blow box BB-3
ACCEPTEDMissed 2026-08-20, now 2026-08-23 (+3 d) · Design, drawing or RFI
Follows delay D-004: Blow box BB-2 supply duct flange does not match.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
IF03 Install felt roll FR-03 (top felt)
ACCEPTEDMissed 2026-08-20, now 2026-08-23 (+3 d) · Other
Finish moved inside the activity's float; no successor was held.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
IB02 Install blow box BB-2
ACCEPTEDMissed 2026-08-19, now 2026-08-22 (+3 d) · Design, drawing or RFI
Follows delay D-004: Blow box BB-2 supply duct flange does not match.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-23T13:36:00 · accepted by Elena Varga, CM on 2026-08-23
IF02 Install felt roll FR-02 (top felt)
ACCEPTEDMissed 2026-08-19, now 2026-08-22 (+3 d) · Material delivery
Follows delay D-006: Felt roll FR-02 bearing housing bore undersize at receipt.
Recovery: Work follows on as soon as the predecessor is done; crews held on site.
Submitted by Site Manager, Northfield Millwright Services at 2026-08-30T09:00:00 · accepted by Elena Varga, CM on 2026-08-30
Pay applications
Contract $3,229,900 (includes approved changes $79,900) · certified to date $3,229,900 · retainage held $322,990 · paid $2,906,910
| No. | Period end | Claimed to date | Certified to date | Retainage | Back-charges off | Payment due | Status |
|---|---|---|---|---|---|---|---|
| 4 | 2026-09-21 | $3,229,900 | $3,229,900 | $322,990 | $1,574,910 | PAID | |
| 3 | 2026-08-19 | $1,480,000 | $1,480,000 | $148,000 | $864,000 | PAID | |
| 2 | 2026-07-25 | $520,000 | $520,000 | $52,000 | $252,000 | PAID | |
| 1 | 2026-06-25 | $240,000 | $240,000 | $24,000 | $216,000 | PAID |
Back-charges for errors on this scope
When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.
No back-charges on this scope.
Delays covering this scope
D-004 Blow box BB-2 supply duct flange does not match Third party · CLOSED
D-006 Felt roll FR-02 bearing housing bore undersize at receipt Third party · CLOSED
Activities
| Activity | Trade | Planned | Actual finish | % |
|---|---|---|---|---|
EN030 Gear train review: 14 bull gears and 27 idler gears | MILL | 2025-11-29 → 2025-12-13 | 2025-12-13 | 100 |
PR010 Set up laydown, staging and outage trailers | MILL | 2026-06-20 → 2026-06-24 | 2026-06-24 | 100 |
FB110 Receive, inspect and stage all equipment at the laydown | MILL | 2026-07-01 → 2026-07-08 | 2026-07-08 | 100 |
OT010 Shut down, cool down, lockout and tryout | MILL | 2026-08-04 → 2026-08-04 | 2026-08-04 | 100 |
OT020 Remove press and dryer felts | MILL | 2026-08-05 → 2026-08-05 | 2026-08-05 | 100 |
RG01 Remove bull gear BG-01 and idler gears IG-01, IG-02 | MILL | 2026-08-07 → 2026-08-07 | 2026-08-07 | 100 |
RG02 Remove bull gear BG-02 and idler gears IG-03, IG-04 | MILL | 2026-08-07 → 2026-08-07 | 2026-08-07 | 100 |
RB01 Remove blow box BB-1 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RB02 Remove blow box BB-2 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RB03 Remove blow box BB-3 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RB04 Remove blow box BB-4 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RB05 Remove blow box BB-5 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RB06 Remove blow box BB-6 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF01 Remove felt roll FR-01 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF02 Remove felt roll FR-02 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF03 Remove felt roll FR-03 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF04 Remove felt roll FR-04 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF05 Remove felt roll FR-05 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF06 Remove felt roll FR-06 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF07 Remove felt roll FR-07 (top felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF08 Remove felt roll FR-08 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF09 Remove felt roll FR-09 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF10 Remove felt roll FR-10 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF11 Remove felt roll FR-11 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF12 Remove felt roll FR-12 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RF13 Remove felt roll FR-13 (bottom felt) | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RG03 Remove bull gear BG-03 and idler gears IG-05, IG-06 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RG04 Remove bull gear BG-04 and idler gears IG-07, IG-08 | MILL | 2026-08-08 → 2026-08-08 | 2026-08-08 | 100 |
RD01 Remove dryer D-01 (top tier) | MILL | 2026-08-09 → 2026-08-09 | 2026-08-09 | 100 |
RD02 Remove dryer D-02 (bottom tier) | MILL | 2026-08-09 → 2026-08-09 | 2026-08-09 | 100 |
RG05 Remove bull gear BG-05 and idler gears IG-09, IG-10 | MILL | 2026-08-09 → 2026-08-09 | 2026-08-09 | 100 |
RG06 Remove bull gear BG-06 and idler gears IG-11, IG-12 | MILL | 2026-08-09 → 2026-08-09 | 2026-08-09 | 100 |
RD03 Remove dryer D-03 (top tier) | MILL | 2026-08-10 → 2026-08-10 | 2026-08-10 | 100 |
RD04 Remove dryer D-04 (bottom tier) | MILL | 2026-08-10 → 2026-08-10 | 2026-08-10 | 100 |
RG07 Remove bull gear BG-07 and idler gears IG-13, IG-14 | MILL | 2026-08-10 → 2026-08-10 | 2026-08-10 | 100 |
RG08 Remove bull gear BG-08 and idler gears IG-15, IG-16 | MILL | 2026-08-10 → 2026-08-10 | 2026-08-10 | 100 |
RD05 Remove dryer D-05 (top tier) | MILL | 2026-08-11 → 2026-08-11 | 2026-08-11 | 100 |
RD06 Remove dryer D-06 (bottom tier) | MILL | 2026-08-11 → 2026-08-11 | 2026-08-11 | 100 |
RG09 Remove bull gear BG-09 and idler gears IG-17, IG-18 | MILL | 2026-08-11 → 2026-08-11 | 2026-08-11 | 100 |
RG10 Remove bull gear BG-10 and idler gears IG-19, IG-20 | MILL | 2026-08-11 → 2026-08-11 | 2026-08-11 | 100 |
RD07 Remove dryer D-07 (top tier) | MILL | 2026-08-12 → 2026-08-12 | 2026-08-12 | 100 |
RD08 Remove dryer D-08 (bottom tier) | MILL | 2026-08-12 → 2026-08-12 | 2026-08-12 | 100 |
RG11 Remove bull gear BG-11 and idler gears IG-21, IG-22 | MILL | 2026-08-12 → 2026-08-12 | 2026-08-12 | 100 |
RG12 Remove bull gear BG-12 and idler gears IG-23, IG-24 | MILL | 2026-08-12 → 2026-08-12 | 2026-08-12 | 100 |
RD09 Remove dryer D-09 (top tier) | MILL | 2026-08-13 → 2026-08-13 | 2026-08-13 | 100 |
RD10 Remove dryer D-10 (bottom tier) | MILL | 2026-08-13 → 2026-08-13 | 2026-08-13 | 100 |
RG13 Remove bull gear BG-13 and idler gears IG-25, IG-26 | MILL | 2026-08-13 → 2026-08-13 | 2026-08-13 | 100 |
RG14 Remove bull gear BG-14 and idler gear IG-27 | MILL | 2026-08-13 → 2026-08-13 | 2026-08-13 | 100 |
RD11 Remove dryer D-11 (top tier) | MILL | 2026-08-14 → 2026-08-14 | 2026-08-14 | 100 |
RD12 Remove dryer D-12 (bottom tier) | MILL | 2026-08-14 → 2026-08-14 | 2026-08-14 | 100 |
RD13 Remove dryer D-13 (top tier) | MILL | 2026-08-15 → 2026-08-15 | 2026-08-15 | 100 |
RD14 Remove dryer D-14 (bottom tier) | MILL | 2026-08-15 → 2026-08-15 | 2026-08-15 | 100 |
ID01 Set new dryer D-01 (top tier) | MILL | 2026-08-17 → 2026-08-17 | 2026-08-17 | 100 |
ID02 Set new dryer D-02 (bottom tier) | MILL | 2026-08-17 → 2026-08-17 | 2026-08-17 | 100 |
IB01 Install blow box BB-1 | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
ID03 Set new dryer D-03 (top tier) | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
ID04 Set new dryer D-04 (bottom tier) | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
IF01 Install felt roll FR-01 (top felt) | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
IG01 Install bull gear BG-01 and idler gears IG-01, IG-02 | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
IG02 Install bull gear BG-02 and idler gears IG-03, IG-04 | MILL | 2026-08-18 → 2026-08-18 | 2026-08-18 | 100 |
ID05 Set new dryer D-05 (top tier) | MILL | 2026-08-19 → 2026-08-19 | 2026-08-19 | 100 |
ID06 Set new dryer D-06 (bottom tier) | MILL | 2026-08-19 → 2026-08-19 | 2026-08-19 | 100 |
IG03 Install bull gear BG-03 and idler gears IG-05, IG-06 | MILL | 2026-08-19 → 2026-08-19 | 2026-08-19 | 100 |
IG04 Install bull gear BG-04 and idler gears IG-07, IG-08 | MILL | 2026-08-19 → 2026-08-19 | 2026-08-19 | 100 |
ID07 Set new dryer D-07 (top tier) | MILL | 2026-08-20 → 2026-08-20 | 2026-08-20 | 100 |
ID08 Set new dryer D-08 (bottom tier) | MILL | 2026-08-20 → 2026-08-20 | 2026-08-20 | 100 |
IG05 Install bull gear BG-05 and idler gears IG-09, IG-10 | MILL | 2026-08-20 → 2026-08-20 | 2026-08-20 | 100 |
IG06 Install bull gear BG-06 and idler gears IG-11, IG-12 | MILL | 2026-08-20 → 2026-08-20 | 2026-08-20 | 100 |
ID09 Set new dryer D-09 (top tier) | MILL | 2026-08-21 → 2026-08-21 | 2026-08-21 | 100 |
ID10 Set new dryer D-10 (bottom tier) | MILL | 2026-08-21 → 2026-08-21 | 2026-08-21 | 100 |
IG07 Install bull gear BG-07 and idler gears IG-13, IG-14 | MILL | 2026-08-21 → 2026-08-21 | 2026-08-21 | 100 |
IG08 Install bull gear BG-08 and idler gears IG-15, IG-16 | MILL | 2026-08-21 → 2026-08-21 | 2026-08-21 | 100 |
ID11 Set new dryer D-11 (top tier) | MILL | 2026-08-22 → 2026-08-22 | 2026-08-22 | 100 |
ID12 Set new dryer D-12 (bottom tier) | MILL | 2026-08-22 → 2026-08-22 | 2026-08-22 | 100 |
IF08 Install felt roll FR-08 (bottom felt) | MILL | 2026-08-22 → 2026-08-22 | 2026-08-22 | 100 |
IG09 Install bull gear BG-09 and idler gears IG-17, IG-18 | MILL | 2026-08-22 → 2026-08-22 | 2026-08-22 | 100 |
IG10 Install bull gear BG-10 and idler gears IG-19, IG-20 | MILL | 2026-08-22 → 2026-08-22 | 2026-08-22 | 100 |
ID13 Set new dryer D-13 (top tier) | MILL | 2026-08-23 → 2026-08-23 | 2026-08-23 | 100 |
ID14 Set new dryer D-14 (bottom tier) | MILL | 2026-08-23 → 2026-08-23 | 2026-08-23 | 100 |
IF09 Install felt roll FR-09 (bottom felt) | MILL | 2026-08-23 → 2026-08-23 | 2026-08-23 | 100 |
IG11 Install bull gear BG-11 and idler gears IG-21, IG-22 | MILL | 2026-08-23 → 2026-08-23 | 2026-08-23 | 100 |
IG12 Install bull gear BG-12 and idler gears IG-23, IG-24 | MILL | 2026-08-23 → 2026-08-23 | 2026-08-23 | 100 |
IB02 Install blow box BB-2 | MILL | 2026-08-24 → 2026-08-24 | 2026-08-24 | 100 |
IF02 Install felt roll FR-02 (top felt) | MILL | 2026-08-24 → 2026-08-24 | 2026-08-24 | 100 |
IF10 Install felt roll FR-10 (bottom felt) | MILL | 2026-08-24 → 2026-08-24 | 2026-08-24 | 100 |
IG13 Install bull gear BG-13 and idler gears IG-25, IG-26 | MILL | 2026-08-24 → 2026-08-24 | 2026-08-24 | 100 |
IG14 Install bull gear BG-14 and idler gear IG-27 | MILL | 2026-08-24 → 2026-08-24 | 2026-08-24 | 100 |
IB03 Install blow box BB-3 | MILL | 2026-08-25 → 2026-08-25 | 2026-08-25 | 100 |
IF03 Install felt roll FR-03 (top felt) | MILL | 2026-08-25 → 2026-08-25 | 2026-08-25 | 100 |
IF11 Install felt roll FR-11 (bottom felt) | MILL | 2026-08-25 → 2026-08-25 | 2026-08-25 | 100 |
SY050 Gear mesh, backlash and runout checks | MILL | 2026-08-25 → 2026-08-26 | 2026-08-26 | 100 |
IB04 Install blow box BB-4 | MILL | 2026-08-26 → 2026-08-26 | 2026-08-26 | 100 |
IF04 Install felt roll FR-04 (top felt) | MILL | 2026-08-26 → 2026-08-26 | 2026-08-26 | 100 |
IF12 Install felt roll FR-12 (bottom felt) | MILL | 2026-08-26 → 2026-08-26 | 2026-08-26 | 100 |
IB05 Install blow box BB-5 | MILL | 2026-08-27 → 2026-08-27 | 2026-08-27 | 100 |
IF05 Install felt roll FR-05 (top felt) | MILL | 2026-08-27 → 2026-08-27 | 2026-08-27 | 100 |
IF13 Install felt roll FR-13 (bottom felt) | MILL | 2026-08-27 → 2026-08-27 | 2026-08-27 | 100 |
IB06 Install blow box BB-6 | MILL | 2026-08-28 → 2026-08-28 | 2026-08-28 | 100 |
IF06 Install felt roll FR-06 (top felt) | MILL | 2026-08-28 → 2026-08-28 | 2026-08-28 | 100 |
IF07 Install felt roll FR-07 (top felt) | MILL | 2026-08-29 → 2026-08-30 | 2026-08-30 | 100 |
SU030 Hang new press and dryer felts | MILL | 2026-09-07 → 2026-09-07 | 2026-09-07 | 100 |