Summit Scaffold
Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors
Missed dates needing your explanation (0)
Nothing outstanding. Every missed date has an explanation on record.
Explanations on record
None yet.
Pay applications
Contract $600,000 · certified to date $600,000 · retainage held $60,000 · paid $538,150 · back-charges deducted $1,850
| No. | Period end | Claimed to date | Certified to date | Retainage | Back-charges off | Payment due | Status |
|---|---|---|---|---|---|---|---|
| 3 | 2026-09-21 | $600,000 | $600,000 | $60,000 | $171,000 | PAID | |
| 2 | 2026-08-19 | $410,000 | $410,000 | $41,000 | $153,000 | PAID | |
| 1 | 2026-07-25 | $240,000 | $240,000 | $24,000 | $1,850 | $214,150 | PAID |
Back-charges for errors on this scope
When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.
BC-001 Tending-side scaffold bay 6 handrail left off after a modification; re-fitted by the millwrights DEDUCTED
Basis: Scaffold inspection INS-001 fail on outage day 9; photos on file · OT030 · found 2026-08-13 by Tony Alvarez · Fixed by others, cost recovered · $1,850
Your answer: Agreed; our crew did not re-fit it. Site Super, Summit Scaffold
Delays covering this scope
No delays logged on these activities.
Activities
| Activity | Trade | Planned | Actual finish | % |
|---|---|---|---|---|
PR020 Scaffold design and pre-build of outage scaffolds | SCAF | 2026-07-05 → 2026-07-14 | 2026-07-14 | 100 |
OT030 Erect outage scaffolding, tending and drive sides | SCAF | 2026-08-06 → 2026-08-07 | 2026-08-07 | 100 |
SY080 Strike outage scaffolding | SCAF | 2026-09-01 → 2026-09-02 | 2026-09-02 | 100 |
Until sign-in by role is built, anyone with the link can submit here; every submission records the name given and the time.