XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

ThermaCoat Insulation ?

Scope view: this contractor's activities, every missed schedule date and the explanation given for it. All contractors

Missed dates needing your explanation (0)

Nothing outstanding. Every missed date has an explanation on record.

Source: missed_date · asked when a planned finish passes unfinished or slips between P6 uploads

Explanations on record

None yet.

Source: missed_date, missed_date_doc

Pay applications

Contract $314,600 (includes approved changes $44,600) · certified to date $314,600 · retainage held $31,460 · paid $283,140

No.Period endClaimed to dateCertified to dateRetainageBack-charges offPayment dueStatus
22026-09-21$314,600 $314,600 $31,460 $247,140 PAID
12026-08-19$40,000 $40,000 $4,000 $36,000 PAID

Submit the next application

Agreed back-charges are taken off when the application is certified.

Source: subcontract, pay_app

Back-charges for errors on this scope

When work has to be fixed because of an error on this scope, the cost is charged back. Read the basis and evidence, then accept it or dispute it with your reasons and documents.

No back-charges on this scope.

Source: backcharge, backcharge_doc

Delays covering this scope

No delays logged on these activities.

Source: delay

Activities

ActivityTradePlannedActual finish%
SY070 Insulate steam and condensate pipingINSUL 2026-08-29 → 2026-08-312026-08-31 100