Weekly Outage Coordination, day 11
2026-08-15 · Jordan Pike (PM), Elena Varga (CM), Carl Mendez (Superintendent), client outage manager, Dale Whitaker, R. Okafor, Wes Turner, Marcus Lee, Priya Raman, Tony Alvarez, Hannah Price · All meetings
Items pulled from this meeting
Each item links to the line it was read from. Accepting an action or date puts it on that trade's watch list; accepting a decision adds it to the decision register. Your name is recorded with it.
Line Boring and Machining runs IB-3 to IB-5 on nights so the idler gears keep their dates.
Accepted by Wes Turner on 2026-08-15 · MECH · decision register
Log as a schedule delay
The machine room crane sets the blow boxes; no second mobile crane day (change order CO-004).
Accepted by R. Okafor on 2026-08-15 · RIG · decision register
Log as a schedule delay
[R. Okafor] Issue the critical lift review for the press rolls IN020 by 2026-08-20.
Accepted by R. Okafor on 2026-08-15 · RIG · owner R. Okafor · due 2026-08-20 · watch item MTG-2-13
Log as a schedule delay
Marcus Lee to confirm the condensate header replacement spool dimensions for SY010 by 2026-08-17.
Accepted by Marcus Lee on 2026-08-15 · PIPE · owner Marcus Lee · due 2026-08-17 · watch item MTG-2-14
Log as a schedule delay
[Hannah Price] Survey and Layout to book the final alignment survey window by 2026-08-21.
Accepted by Hannah Price on 2026-08-15 · SURV · owner Hannah Price · due 2026-08-21 · watch item MTG-2-15
Log as a schedule delay
Priya Raman to confirm the drive firmware version for SY040 with the client by 2026-08-22.
Accepted by Jordan Pike, PM on 2026-10-05 · EI · owner Priya Raman · due 2026-08-22 · watch item MTG-2-16
Log as a schedule delay
All 14 dryers set by 2026-08-23 (ID14).
Accepted by Jordan Pike, PM on 2026-10-05 · MILL · due 2026-08-23 · watch item MTG-2-17
Log as a schedule delay
Paper on the reel holds 2026-09-08 (SU050).
Accepted by Jordan Pike, PM on 2026-10-05 · COMM · due 2026-09-08 · watch item MTG-2-18
Log as a schedule delay
Meeting text
- # Weekly Outage Coordination, day 11
- Date: 2026-08-15
- Attendees: Jordan Pike (PM), Elena Varga (CM), Carl Mendez (Superintendent), client outage manager, Dale Whitaker, R. Okafor, Wes Turner, Marcus Lee, Priya Raman, Tony Alvarez, Hannah Price
- ## Summary
- The team walked the removal and install sequence for the dryer section and the press section.
- Removal finished on the critical path. Line boring is one day behind on IB-2 with float to spare.
- The 250 t crane goes back to the north pad for the press rolls after the frames are grouted.
- ## Decisions
- - Line Boring and Machining runs IB-3 to IB-5 on nights so the idler gears keep their dates.
- - The machine room crane sets the blow boxes; no second mobile crane day (change order CO-004).
- ## Action Items
- - [R. Okafor] Issue the critical lift review for the press rolls IN020 by 2026-08-20.
- - Marcus Lee to confirm the condensate header replacement spool dimensions for SY010 by 2026-08-17.
- - [Hannah Price] Survey and Layout to book the final alignment survey window by 2026-08-21.
- - Priya Raman to confirm the drive firmware version for SY040 with the client by 2026-08-22.
- ## Key Dates
- - All 14 dryers set by 2026-08-23 (ID14).
- - Paper on the reel holds 2026-09-08 (SU050).