Daily Outage Coordination, day 18
2026-08-22 · Elena Varga (CM), Carl Mendez (Superintendent), Dale Whitaker, R. Okafor, Luis Ortega, Marcus Lee, Priya Raman, Grant Fowler · All meetings
Items pulled from this meeting
Each item links to the line it was read from. Accepting an action or date puts it on that trade's watch list; accepting a decision adds it to the decision register. Your name is recorded with it.
Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives.
Accepted by Dale Whitaker on 2026-08-23 · MILL · decision register
Log as a schedule delay
Press roll install IN020 starts only after the grout cure check passes.
Accepted by R. Okafor on 2026-08-23 · RIG · decision register
Log as a schedule delay
Dale Whitaker to chase the BB-2 adapter flange with the blow box supplier by 2026-08-23.
Accepted by Dale Whitaker on 2026-08-23 · MILL · owner Dale Whitaker · due 2026-08-23 · watch item MTG-3-21
Log as a schedule delay
[Luis Ortega] Concrete cure check on the press sole plates by 2026-08-23.
Accepted by Jordan Pike, PM on 2026-10-05 · CONC · owner Luis Ortega · due 2026-08-23 · watch item MTG-3-22
Log as a schedule delay
Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28.
Accepted by Jordan Pike, PM on 2026-10-05 · QAQC · owner Grant Fowler · due 2026-08-28 · watch item MTG-3-23
Log as a schedule delay
R. Okafor to set the 250 t crane on the north pad for the press roll picks by 2026-08-23.
Accepted by R. Okafor on 2026-08-23 · RIG · owner R. Okafor · due 2026-08-23 · watch item MTG-3-24
Log as a schedule delay
Meeting text
- # Daily Outage Coordination, day 18
- Date: 2026-08-22
- Attendees: Elena Varga (CM), Carl Mendez (Superintendent), Dale Whitaker, R. Okafor, Luis Ortega, Marcus Lee, Priya Raman, Grant Fowler
- ## Summary
- D-11 and D-12 set on the day shift. BB-2 will not bolt up to the existing supply duct; the box is set on its
- supports. The press sole plate grout was poured at 14:30 and cures overnight.
- ## Decisions
- - Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives.
- - Press roll install IN020 starts only after the grout cure check passes.
- ## Action Items
- - Dale Whitaker to chase the BB-2 adapter flange with the blow box supplier by 2026-08-23.
- - [Luis Ortega] Concrete cure check on the press sole plates by 2026-08-23.
- - Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28.
- - R. Okafor to set the 250 t crane on the north pad for the press roll picks by 2026-08-23.