SAMPLE PROJECT · Completed job · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Daily Outage Coordination, day 18 ?

2026-08-22 · Elena Varga (CM), Carl Mendez (Superintendent), Dale Whitaker, R. Okafor, Luis Ortega, Marcus Lee, Priya Raman, Grant Fowler · All meetings

Items pulled from this meeting

Each item links to the line it was read from. Accepting an action or date puts it on that trade's watch list; accepting a decision adds it to the decision register. Your name is recorded with it.

DECISION ACCEPTED line 10

Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives.

Accepted by Dale Whitaker on 2026-08-23 · MILL · decision register

Log as a schedule delay
DECISION ACCEPTED line 11

Press roll install IN020 starts only after the grout cure check passes.

Accepted by R. Okafor on 2026-08-23 · RIG · decision register

Log as a schedule delay
ACTION ACCEPTED line 14

Dale Whitaker to chase the BB-2 adapter flange with the blow box supplier by 2026-08-23.

Accepted by Dale Whitaker on 2026-08-23 · MILL · owner Dale Whitaker · due 2026-08-23 · watch item MTG-3-21

Log as a schedule delay
ACTION ACCEPTED line 15

[Luis Ortega] Concrete cure check on the press sole plates by 2026-08-23.

Accepted by Jordan Pike, PM on 2026-10-05 · CONC · owner Luis Ortega · due 2026-08-23 · watch item MTG-3-22

Log as a schedule delay
ACTION ACCEPTED line 16

Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28.

Accepted by Jordan Pike, PM on 2026-10-05 · QAQC · owner Grant Fowler · due 2026-08-28 · watch item MTG-3-23

Log as a schedule delay
ACTION ACCEPTED line 17

R. Okafor to set the 250 t crane on the north pad for the press roll picks by 2026-08-23.

Accepted by R. Okafor on 2026-08-23 · RIG · owner R. Okafor · due 2026-08-23 · watch item MTG-3-24

Log as a schedule delay
Source: meeting: Daily outage coordination day 18 (Plaud).md

Meeting text

  1. # Daily Outage Coordination, day 18
  2. Date: 2026-08-22
  3. Attendees: Elena Varga (CM), Carl Mendez (Superintendent), Dale Whitaker, R. Okafor, Luis Ortega, Marcus Lee, Priya Raman, Grant Fowler
  4. ## Summary
  5. D-11 and D-12 set on the day shift. BB-2 will not bolt up to the existing supply duct; the box is set on its
  6. supports. The press sole plate grout was poured at 14:30 and cures overnight.
  7. ## Decisions
  8. - Millwrights set BB-2 on its supports and carry on with BB-3 to BB-6 (IB03); bolt-up when the adapter arrives.
  9. - Press roll install IN020 starts only after the grout cure check passes.
  10. ## Action Items
  11. - Dale Whitaker to chase the BB-2 adapter flange with the blow box supplier by 2026-08-23.
  12. - [Luis Ortega] Concrete cure check on the press sole plates by 2026-08-23.
  13. - Grant Fowler to witness the steam joint hydro test for Welding and QA/QC by 2026-08-28.
  14. - R. Okafor to set the 250 t crane on the north pad for the press roll picks by 2026-08-23.
Source: meeting: Daily outage coordination day 18 (Plaud).md · read 2026-08-23T00:00:00