Rigging and Heavy Lift: foreman view
The next two shifts, lifts, drawings and open items, plus turnover, field log and safety entries. Full board
Next shifts
Nothing planned in the next two shifts.
Source: activity
Lifts
No lifts in the next 7 days.
Source: activity
Drawings to check
Every drawing held is current.
Source: drawing
Overdue items
Nothing overdue.
Source: watch_item
Shift turnover
2026-08-27 DAYS AGREE
Lead: Press rolls in; crane released after IN020
Contractor: Press install complete
2026-08-22 DAYS AGREE
Lead: Press frames set; crane re-rigged for rolls
Contractor: Press frames complete