XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help
Gantt and activities Schedule check Working over each other

Schedule ?

The critical path schedule, built and run in the platform. Durations are workdays on the project calendar. Every change re-runs the schedule; publishing an update keeps a snapshot so any finish that moved goes to the delay log. P6 files still import on the upload page and export from here.

Data date
2026-10-21
Source: project
Project finish calc
2026-10-07
early finish of the last activity
Source: activity
Against baseline calc
1 d late
baseline 2026-10-06, set 2025-12-17 by Jordan Pike, PM
Source: baseline_activity
Critical activities
0
total float 0 or less
Source: activity
Working over each other calc
stacked crews or lifts over a crew
Source: activity, overhead_clearance
Last run
2026-10-22 13:35
by Jordan Pike, PM
Source: schedule_run
Critical path 0 Has float 0float bar to late finish In progress 0 Complete 0 Baseline 0 WBS summary Data date 2026-10-21
ActivityOrig durRem dur% compStartFinishBL startBL finishTotal float calcFree floatvs BL
No activities match this view.
Source: activity, activity_rel, baseline_activity, work_calendar, holiday

Add an activity

Run, baseline and publish

Keeps a snapshot. Unfinished activities whose finish moved since the last update go to the delay log for review, and contractors are asked about missed dates.

Work calendar

Non-work days

2025-11-27 Thanksgiving
2025-12-25 Christmas
2026-01-01 New Year's Day