| Activity | Orig dur | Rem dur | % comp | Start | Finish | BL start | BL finish | Total float calc | Free float | vs BL |
Dec 2025Jan 2026Feb 2026Mar 2026Apr 2026May 2026Jun 2026Jul 2026Aug 2026Sep 2026Oct 2026 |
| A10 Press section 6 activities · 6 complete |
| | 100% |
06-Aug-26 | 29-Aug-26 |
06-Aug-26 | 28-Aug-26 | | |
-1 |
|
RM010 COMPLETE Remove the old press section: rolls and felt runRIG · Apex Rigging and Crane · 5 lift plans · after OT020
Edit
Predecessors
OT020 FS
Successors
RM020 FS
Progress to the data date
Change the activity
Early 2026-08-06 to 2026-08-08 · late 2026-08-06 to 2026-08-08 · free float · baseline 2026-08-06 to 2026-08-08
|
3 |
0 |
100% |
06-Aug-26 A |
08-Aug-26 A |
06-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RM020 COMPLETE Remove press section frames and sole platesRIG · Apex Rigging and Crane · 2 lift plans · after RM010
Edit
Predecessors
RM010 FS
Successors
SV010 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-11 · late 2026-08-09 to 2026-08-11 · free float · baseline 2026-08-09 to 2026-08-10
|
2 |
0 |
100% |
09-Aug-26 A |
11-Aug-26 A |
09-Aug-26 |
10-Aug-26 |
done |
|
-1 |
|
IN010 COMPLETE Set new press frames and sole platesRIG · Apex Rigging and Crane · 2 lift plans · after SV010
Edit
Predecessors
SV010 FS
Successors
IN015 FS
Progress to the data date
Change the activity
Early 2026-08-17 to 2026-08-20 · late 2026-08-17 to 2026-08-20 · free float · baseline 2026-08-17 to 2026-08-19
|
3 |
0 |
100% |
17-Aug-26 A |
20-Aug-26 A |
17-Aug-26 |
19-Aug-26 |
done |
|
-1 |
|
IN015 COMPLETE Grout press sole plates and cureCONC · Granite Grout and Concrete · after IN010
Edit
Predecessors
IN010 FS
Successors
IN020 FS
Progress to the data date
Change the activity
Early 2026-08-21 to 2026-08-23 · late 2026-08-21 to 2026-08-23 · free float · baseline 2026-08-20 to 2026-08-22
|
3 |
0 |
100% |
21-Aug-26 A |
23-Aug-26 A |
20-Aug-26 |
22-Aug-26 |
done |
|
-1 |
|
IN020 COMPLETE Install press rolls, suction roll and felt runRIG · Apex Rigging and Crane · 5 lift plans · after IN015
Edit
Predecessors
IN015 FS
Successors
IN030 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-27 · late 2026-08-24 to 2026-08-27 · free float · baseline 2026-08-23 to 2026-08-26
|
4 |
0 |
100% |
24-Aug-26 A |
27-Aug-26 A |
23-Aug-26 |
26-Aug-26 |
done |
|
-1 |
|
IN030 COMPLETE Align the press sectionSURV · Benchmark Alignment Survey · after IN020
Edit
Predecessors
IN020 FS
Successors
SY060 FS
Progress to the data date
Change the activity
Early 2026-08-28 to 2026-08-29 · late 2026-08-28 to 2026-08-29 · free float · baseline 2026-08-27 to 2026-08-28
|
2 |
0 |
100% |
28-Aug-26 A |
29-Aug-26 A |
27-Aug-26 |
28-Aug-26 |
done |
|
-1 |
|
| A20 Dryer section 83 activities · 83 complete |
| | 100% |
09-Dec-25 | 11-Sep-26 |
09-Dec-25 | 11-Sep-26 | | |
0 |
|
EN020 COMPLETE Laser scan and survey of the existing dryer sectionSURV · Benchmark Alignment Survey · after PC010
Edit
Predecessors
PC010 FS +10d
Successors
EN060 SS FB040 FS FB080 FS FB090 FS PR060 FS
Progress to the data date
Change the activity
Early 2025-12-09 to 2025-12-12 · late 2025-12-09 to 2025-12-12 · free float · baseline 2025-12-09 to 2025-12-12
|
4 |
0 |
100% |
09-Dec-25 A |
12-Dec-25 A |
09-Dec-25 |
12-Dec-25 |
done |
|
0 |
|
PR060 COMPLETE Set survey control network and baselinesSURV · Benchmark Alignment Survey · after EN020
Edit
Predecessors
EN020 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2025-12-13 to 2025-12-15 · late 2025-12-13 to 2025-12-15 · free float · baseline 2025-12-13 to 2025-12-15
|
3 |
0 |
100% |
13-Dec-25 A |
15-Dec-25 A |
13-Dec-25 |
15-Dec-25 |
done |
|
0 |
|
PR050 COMPLETE Machine room crane inspection and load testRIG · Apex Rigging and Crane · Start on or after 2026-07-14 · after EN050
Edit
Predecessors
EN050 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2026-07-14 to 2026-07-15 · late 2026-07-14 to 2026-07-15 · free float · baseline 2026-07-14 to 2026-07-15
|
2 |
0 |
100% |
14-Jul-26 A |
15-Jul-26 A |
14-Jul-26 |
15-Jul-26 |
done |
|
0 |
|
OT000 COMPLETE Machine down: last paper off the reelPMGT · Must start on 2026-08-04 · after PR080
Edit
Predecessors
PR080 FS
Successors
OT010 FS
Progress to the data date
Change the activity
Early 2026-08-04 to 2026-08-04 · late 2026-08-04 to 2026-08-04 · free float · baseline 2026-08-04 to 2026-08-04
|
MS |
0 |
100% |
04-Aug-26 A |
04-Aug-26 A |
04-Aug-26 |
04-Aug-26 |
done |
|
0 |
Machine down: last paper off the reel
|
OT010 COMPLETE Shut down, cool down, lockout and tryoutMILL · Northfield Millwright Services · after OT000
Edit
Predecessors
OT000 FS
Successors
OT020 FS OT040 FS OT050 FS
Progress to the data date
Change the activity
Early 2026-08-04 to 2026-08-04 · late 2026-08-04 to 2026-08-04 · free float · baseline 2026-08-04 to 2026-08-04
|
1 |
0 |
100% |
04-Aug-26 A |
04-Aug-26 A |
04-Aug-26 |
04-Aug-26 |
done |
|
0 |
|
OT020 COMPLETE Remove press and dryer feltsMILL · Northfield Millwright Services · after OT010
Edit
Predecessors
OT010 FS
Successors
OT030 FS RM010 FS
Progress to the data date
Change the activity
Early 2026-08-05 to 2026-08-05 · late 2026-08-05 to 2026-08-05 · free float · baseline 2026-08-05 to 2026-08-05
|
1 |
0 |
100% |
05-Aug-26 A |
05-Aug-26 A |
05-Aug-26 |
05-Aug-26 |
done |
|
0 |
|
OT030 COMPLETE Erect outage scaffolding, tending and drive sidesSCAF · Summit Scaffold · after OT020
Edit
Predecessors
OT020 FS
Successors
RB01 FS RB02 FS RB03 FS RB04 FS RB05 FS RB06 FS RF01 FS RF02 FS RF03 FS RF04 FS RF05 FS RF06 FS RF07 FS RF08 FS RF09 FS RF10 FS RF11 FS RF12 FS RF13 FS
Progress to the data date
Change the activity
Early 2026-08-06 to 2026-08-07 · late 2026-08-06 to 2026-08-07 · free float · baseline 2026-08-06 to 2026-08-07
|
2 |
0 |
100% |
06-Aug-26 A |
07-Aug-26 A |
06-Aug-26 |
07-Aug-26 |
done |
|
0 |
|
RB01 COMPLETE Remove blow box BB-1MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD01 FS RD02 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RB02 COMPLETE Remove blow box BB-2MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD03 FS RD04 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RB03 COMPLETE Remove blow box BB-3MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD05 FS RD06 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RB04 COMPLETE Remove blow box BB-4MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD07 FS RD08 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RB05 COMPLETE Remove blow box BB-5MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD09 FS RD10 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RB06 COMPLETE Remove blow box BB-6MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD11 FS RD12 FS RD13 FS RD14 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF01 COMPLETE Remove felt roll FR-01 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD01 FS RD02 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF02 COMPLETE Remove felt roll FR-02 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD02 FS RD03 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF03 COMPLETE Remove felt roll FR-03 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD03 FS RD04 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF04 COMPLETE Remove felt roll FR-04 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD04 FS RD05 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF05 COMPLETE Remove felt roll FR-05 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD05 FS RD06 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF06 COMPLETE Remove felt roll FR-06 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD06 FS RD07 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF07 COMPLETE Remove felt roll FR-07 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD07 FS RD08 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF08 COMPLETE Remove felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD08 FS RD09 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF09 COMPLETE Remove felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD09 FS RD10 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF10 COMPLETE Remove felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD10 FS RD11 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF11 COMPLETE Remove felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD11 FS RD12 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF12 COMPLETE Remove felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD12 FS RD13 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RF13 COMPLETE Remove felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after OT030
Edit
Predecessors
OT030 FS
Successors
RD13 FS RD14 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RD01 COMPLETE Remove dryer D-01 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB01, RF01, RG01
Edit
Predecessors
RB01 FS
RF01 FS
RG01 FS
Successors
RD03 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09
|
1 |
0 |
100% |
09-Aug-26 A |
09-Aug-26 A |
09-Aug-26 |
09-Aug-26 |
done |
|
0 |
|
RD02 COMPLETE Remove dryer D-02 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB01, RF01, RF02, RG02
Edit
Predecessors
RB01 FS
RF01 FS
RF02 FS
RG02 FS
Successors
RD04 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09
|
1 |
0 |
100% |
09-Aug-26 A |
09-Aug-26 A |
09-Aug-26 |
09-Aug-26 |
done |
|
0 |
|
RD03 COMPLETE Remove dryer D-03 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB02, RD01, RF02, RF03, RG03
Edit
Predecessors
RB02 FS
RD01 FS
RF02 FS
RF03 FS
RG03 FS
Successors
RD05 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10
|
1 |
0 |
100% |
10-Aug-26 A |
10-Aug-26 A |
10-Aug-26 |
10-Aug-26 |
done |
|
0 |
|
RD04 COMPLETE Remove dryer D-04 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB02, RD02, RF03, RF04, RG04
Edit
Predecessors
RB02 FS
RD02 FS
RF03 FS
RF04 FS
RG04 FS
Successors
RD06 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10
|
1 |
0 |
100% |
10-Aug-26 A |
10-Aug-26 A |
10-Aug-26 |
10-Aug-26 |
done |
|
0 |
|
RD05 COMPLETE Remove dryer D-05 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB03, RD03, RF04, RF05, RG05
Edit
Predecessors
RB03 FS
RD03 FS
RF04 FS
RF05 FS
RG05 FS
Successors
RD07 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11
|
1 |
0 |
100% |
11-Aug-26 A |
11-Aug-26 A |
11-Aug-26 |
11-Aug-26 |
done |
|
0 |
|
RD06 COMPLETE Remove dryer D-06 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB03, RD04, RF05, RF06, RG06
Edit
Predecessors
RB03 FS
RD04 FS
RF05 FS
RF06 FS
RG06 FS
Successors
RD08 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11
|
1 |
0 |
100% |
11-Aug-26 A |
11-Aug-26 A |
11-Aug-26 |
11-Aug-26 |
done |
|
0 |
|
RD07 COMPLETE Remove dryer D-07 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB04, RD05, RF06, RF07, RG07
Edit
Predecessors
RB04 FS
RD05 FS
RF06 FS
RF07 FS
RG07 FS
Successors
RD09 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12
|
1 |
0 |
100% |
12-Aug-26 A |
12-Aug-26 A |
12-Aug-26 |
12-Aug-26 |
done |
|
0 |
|
RD08 COMPLETE Remove dryer D-08 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB04, RD06, RF07, RF08, RG08
Edit
Predecessors
RB04 FS
RD06 FS
RF07 FS
RF08 FS
RG08 FS
Successors
RD10 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12
|
1 |
0 |
100% |
12-Aug-26 A |
12-Aug-26 A |
12-Aug-26 |
12-Aug-26 |
done |
|
0 |
|
RD09 COMPLETE Remove dryer D-09 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB05, RD07, RF08, RF09, RG09
Edit
Predecessors
RB05 FS
RD07 FS
RF08 FS
RF09 FS
RG09 FS
Successors
RD11 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13
|
1 |
0 |
100% |
13-Aug-26 A |
13-Aug-26 A |
13-Aug-26 |
13-Aug-26 |
done |
|
0 |
|
RD10 COMPLETE Remove dryer D-10 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB05, RD08, RF09, RF10, RG10
Edit
Predecessors
RB05 FS
RD08 FS
RF09 FS
RF10 FS
RG10 FS
Successors
RD12 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13
|
1 |
0 |
100% |
13-Aug-26 A |
13-Aug-26 A |
13-Aug-26 |
13-Aug-26 |
done |
|
0 |
|
RD11 COMPLETE Remove dryer D-11 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB06, RD09, RF10, RF11, RG11
Edit
Predecessors
RB06 FS
RD09 FS
RF10 FS
RF11 FS
RG11 FS
Successors
RD13 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-14 to 2026-08-14 · late 2026-08-14 to 2026-08-14 · free float · baseline 2026-08-14 to 2026-08-14
|
1 |
0 |
100% |
14-Aug-26 A |
14-Aug-26 A |
14-Aug-26 |
14-Aug-26 |
done |
|
0 |
|
RD12 COMPLETE Remove dryer D-12 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB06, RD10, RF11, RF12, RG12
Edit
Predecessors
RB06 FS
RD10 FS
RF11 FS
RF12 FS
RG12 FS
Successors
RD14 FS SV010 FS
Progress to the data date
Change the activity
Early 2026-08-14 to 2026-08-14 · late 2026-08-14 to 2026-08-14 · free float · baseline 2026-08-14 to 2026-08-14
|
1 |
0 |
100% |
14-Aug-26 A |
14-Aug-26 A |
14-Aug-26 |
14-Aug-26 |
done |
|
0 |
|
RD13 COMPLETE Remove dryer D-13 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after RB06, RD11, RF12, RF13, RG13
Edit
Predecessors
RB06 FS
RD11 FS
RF12 FS
RF13 FS
RG13 FS
Successors
SV010 FS
Progress to the data date
Change the activity
Early 2026-08-15 to 2026-08-15 · late 2026-08-15 to 2026-08-15 · free float · baseline 2026-08-15 to 2026-08-15
|
1 |
0 |
100% |
15-Aug-26 A |
15-Aug-26 A |
15-Aug-26 |
15-Aug-26 |
done |
|
0 |
|
RD14 COMPLETE Remove dryer D-14 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after RB06, RD12, RF13, RG14
Edit
Predecessors
RB06 FS
RD12 FS
RF13 FS
RG14 FS
Successors
SV010 FS
Progress to the data date
Change the activity
Early 2026-08-15 to 2026-08-15 · late 2026-08-15 to 2026-08-15 · free float · baseline 2026-08-15 to 2026-08-15
|
1 |
0 |
100% |
15-Aug-26 A |
15-Aug-26 A |
15-Aug-26 |
15-Aug-26 |
done |
|
0 |
|
SV010 COMPLETE Survey the frames after removalSURV · Benchmark Alignment Survey · after RD01, RD02, RD03, RD04, RD05, RD06, RD07, RD08, RD09, RD10, RD11, RD12, RD13, RD14, RM020
Edit
Predecessors
RD01 FS
RD02 FS
RD03 FS
RD04 FS
RD05 FS
RD06 FS
RD07 FS
RD08 FS
RD09 FS
RD10 FS
RD11 FS
RD12 FS
RD13 FS
RD14 FS
RM020 FS
Successors
ID01 FS ID02 FS ID03 FS ID04 FS ID05 FS ID06 FS ID07 FS ID08 FS ID09 FS ID10 FS ID11 FS ID12 FS ID13 FS ID14 FS IN010 FS
Progress to the data date
Change the activity
Early 2026-08-16 to 2026-08-16 · late 2026-08-16 to 2026-08-16 · free float · baseline 2026-08-16 to 2026-08-16
|
1 |
0 |
100% |
16-Aug-26 A |
16-Aug-26 A |
16-Aug-26 |
16-Aug-26 |
done |
|
0 |
|
ID01 COMPLETE Set new dryer D-01 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after SV010
Edit
Predecessors
SV010 FS
Successors
ID03 FS IG01 FS
Progress to the data date
Change the activity
Early 2026-08-17 to 2026-08-17 · late 2026-08-17 to 2026-08-17 · free float · baseline 2026-08-17 to 2026-08-17
|
1 |
0 |
100% |
17-Aug-26 A |
17-Aug-26 A |
17-Aug-26 |
17-Aug-26 |
done |
|
0 |
|
ID02 COMPLETE Set new dryer D-02 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after SV010
Edit
Predecessors
SV010 FS
Successors
IB01 FS ID04 FS IF01 FS IG02 FS
Progress to the data date
Change the activity
Early 2026-08-17 to 2026-08-17 · late 2026-08-17 to 2026-08-17 · free float · baseline 2026-08-17 to 2026-08-17
|
1 |
0 |
100% |
17-Aug-26 A |
17-Aug-26 A |
17-Aug-26 |
17-Aug-26 |
done |
|
0 |
|
IB01 COMPLETE Install blow box BB-1MILL · Northfield Millwright Services · 1 lift plan · after ID02
Edit
Predecessors
ID02 FS
Successors
IB02 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
ID03 COMPLETE Set new dryer D-03 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID01, SV010
Edit
Predecessors
ID01 FS
SV010 FS
Successors
ID05 FS IF02 FS IG03 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
ID04 COMPLETE Set new dryer D-04 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID02, SV010
Edit
Predecessors
ID02 FS
SV010 FS
Successors
IB02 FS ID06 FS IF03 FS IG04 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
IF01 COMPLETE Install felt roll FR-01 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID02
Edit
Predecessors
ID02 FS
Successors
IF02 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
ID05 COMPLETE Set new dryer D-05 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID03, SV010
Edit
Predecessors
ID03 FS
SV010 FS
Successors
ID07 FS IF04 FS IG05 FS
Progress to the data date
Change the activity
Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
19-Aug-26 A |
19-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
0 |
|
ID06 COMPLETE Set new dryer D-06 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID04, SV010
Edit
Predecessors
ID04 FS
SV010 FS
Successors
IB03 FS ID08 FS IF05 FS IG06 FS
Progress to the data date
Change the activity
Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
19-Aug-26 A |
19-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
0 |
|
ID07 COMPLETE Set new dryer D-07 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID05, SV010
Edit
Predecessors
ID05 FS
SV010 FS
Successors
ID09 FS IF06 FS IG07 FS
Progress to the data date
Change the activity
Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
20-Aug-26 A |
20-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
0 |
|
ID08 COMPLETE Set new dryer D-08 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID06, SV010
Edit
Predecessors
ID06 FS
SV010 FS
Successors
IB04 FS ID10 FS IF07 FS IG08 FS
Progress to the data date
Change the activity
Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
20-Aug-26 A |
20-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
0 |
|
ID09 COMPLETE Set new dryer D-09 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID07, SV010
Edit
Predecessors
ID07 FS
SV010 FS
Successors
ID11 FS IF08 FS IG09 FS
Progress to the data date
Change the activity
Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
21-Aug-26 A |
21-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
0 |
|
ID10 COMPLETE Set new dryer D-10 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID08, SV010
Edit
Predecessors
ID08 FS
SV010 FS
Successors
IB05 FS ID12 FS IF09 FS IG10 FS
Progress to the data date
Change the activity
Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
21-Aug-26 A |
21-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
0 |
|
ID11 COMPLETE Set new dryer D-11 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID09, SV010
Edit
Predecessors
ID09 FS
SV010 FS
Successors
ID13 FS IF10 FS IG11 FS
Progress to the data date
Change the activity
Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
22-Aug-26 A |
22-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
0 |
|
ID12 COMPLETE Set new dryer D-12 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID10, SV010
Edit
Predecessors
ID10 FS
SV010 FS
Successors
IB06 FS ID14 FS IF11 FS IG12 FS
Progress to the data date
Change the activity
Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
22-Aug-26 A |
22-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
0 |
|
IF08 COMPLETE Install felt roll FR-08 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID09
Edit
Predecessors
ID09 FS
Successors
IF09 FS
Progress to the data date
Change the activity
Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
22-Aug-26 A |
22-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
0 |
|
ID13 COMPLETE Set new dryer D-13 (top tier)MILL · Northfield Millwright Services · 1 lift plan · after ID11, SV010
Edit
Predecessors
ID11 FS
SV010 FS
Successors
IF12 FS IG13 FS SY010 FS
Progress to the data date
Change the activity
Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
23-Aug-26 A |
23-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
0 |
|
ID14 COMPLETE Set new dryer D-14 (bottom tier)MILL · Northfield Millwright Services · 1 lift plan · after ID12, SV010
Edit
Predecessors
ID12 FS
SV010 FS
Successors
IF13 FS IG14 FS SY010 FS
Progress to the data date
Change the activity
Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
23-Aug-26 A |
23-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
0 |
|
IF09 COMPLETE Install felt roll FR-09 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID10, IF08
Edit
Predecessors
ID10 FS
IF08 FS
Successors
IF10 FS
Progress to the data date
Change the activity
Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
23-Aug-26 A |
23-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
0 |
|
IB02 COMPLETE Install blow box BB-2MILL · Northfield Millwright Services · 1 lift plan · after IB01, ID04
Edit
Predecessors
IB01 FS
ID04 FS
Successors
IB03 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
24-Aug-26 A |
24-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
-5 |
|
IF02 COMPLETE Install felt roll FR-02 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID03, IF01
Edit
Predecessors
ID03 FS
IF01 FS
Successors
IF03 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
24-Aug-26 A |
24-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
-5 |
|
IF10 COMPLETE Install felt roll FR-10 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID11, IF09
Edit
Predecessors
ID11 FS
IF09 FS
Successors
IF11 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24
|
1 |
0 |
100% |
24-Aug-26 A |
24-Aug-26 A |
24-Aug-26 |
24-Aug-26 |
done |
|
0 |
|
IB03 COMPLETE Install blow box BB-3MILL · Northfield Millwright Services · 1 lift plan · after IB02, ID06
Edit
Predecessors
IB02 FS
ID06 FS
Successors
IB04 FS
Progress to the data date
Change the activity
Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
25-Aug-26 A |
25-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
-5 |
|
IF03 COMPLETE Install felt roll FR-03 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID04, IF02
Edit
Predecessors
ID04 FS
IF02 FS
Successors
IF04 FS
Progress to the data date
Change the activity
Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
25-Aug-26 A |
25-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
-5 |
|
IF11 COMPLETE Install felt roll FR-11 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID12, IF10
Edit
Predecessors
ID12 FS
IF10 FS
Successors
IF12 FS
Progress to the data date
Change the activity
Early 2026-08-25 to 2026-08-25 · late 2026-08-25 to 2026-08-25 · free float · baseline 2026-08-25 to 2026-08-25
|
1 |
0 |
100% |
25-Aug-26 A |
25-Aug-26 A |
25-Aug-26 |
25-Aug-26 |
done |
|
0 |
|
IB04 COMPLETE Install blow box BB-4MILL · Northfield Millwright Services · 1 lift plan · after IB03, ID08
Edit
Predecessors
IB03 FS
ID08 FS
Successors
IB05 FS
Progress to the data date
Change the activity
Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
26-Aug-26 A |
26-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
-5 |
|
IF04 COMPLETE Install felt roll FR-04 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID05, IF03
Edit
Predecessors
ID05 FS
IF03 FS
Successors
IF05 FS
Progress to the data date
Change the activity
Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
26-Aug-26 A |
26-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
-5 |
|
IF12 COMPLETE Install felt roll FR-12 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID13, IF11
Edit
Predecessors
ID13 FS
IF11 FS
Successors
IF13 FS
Progress to the data date
Change the activity
Early 2026-08-26 to 2026-08-26 · late 2026-08-26 to 2026-08-26 · free float · baseline 2026-08-26 to 2026-08-26
|
1 |
0 |
100% |
26-Aug-26 A |
26-Aug-26 A |
26-Aug-26 |
26-Aug-26 |
done |
|
0 |
|
IB05 COMPLETE Install blow box BB-5MILL · Northfield Millwright Services · 1 lift plan · after IB04, ID10
Edit
Predecessors
IB04 FS
ID10 FS
Successors
IB06 FS
Progress to the data date
Change the activity
Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
27-Aug-26 A |
27-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
-5 |
|
IF05 COMPLETE Install felt roll FR-05 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID06, IF04
Edit
Predecessors
ID06 FS
IF04 FS
Successors
IF06 FS
Progress to the data date
Change the activity
Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
27-Aug-26 A |
27-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
-5 |
|
IF13 COMPLETE Install felt roll FR-13 (bottom felt)MILL · Northfield Millwright Services · 1 lift plan · after ID14, IF12
Edit
Predecessors
ID14 FS
IF12 FS
Successors
SY080 FS
Progress to the data date
Change the activity
Early 2026-08-27 to 2026-08-27 · late 2026-08-27 to 2026-08-27 · free float · baseline 2026-08-27 to 2026-08-27
|
1 |
0 |
100% |
27-Aug-26 A |
27-Aug-26 A |
27-Aug-26 |
27-Aug-26 |
done |
|
0 |
|
IB06 COMPLETE Install blow box BB-6MILL · Northfield Millwright Services · 1 lift plan · after IB05, ID12
Edit
Predecessors
IB05 FS
ID12 FS
Successors
SY080 FS
Progress to the data date
Change the activity
Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
28-Aug-26 A |
28-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
-5 |
|
IF06 COMPLETE Install felt roll FR-06 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID07, IF05
Edit
Predecessors
ID07 FS
IF05 FS
Successors
IF07 FS
Progress to the data date
Change the activity
Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
28-Aug-26 A |
28-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
-5 |
|
IF07 COMPLETE Install felt roll FR-07 (top felt)MILL · Northfield Millwright Services · 1 lift plan · after ID08, IF06
Edit
Predecessors
ID08 FS
IF06 FS
Successors
SY080 FS
Progress to the data date
Change the activity
Early 2026-08-29 to 2026-08-30 · late 2026-08-29 to 2026-08-30 · free float · baseline 2026-08-24 to 2026-08-24
|
1 |
0 |
100% |
29-Aug-26 A |
30-Aug-26 A |
24-Aug-26 |
24-Aug-26 |
done |
|
-6 |
|
SY060 COMPLETE Final alignment survey: press and dryersSURV · Benchmark Alignment Survey · after IN030, SY050
Edit
Predecessors
IN030 FS
SY050 FS
Successors
SY080 FS
Progress to the data date
Change the activity
Early 2026-08-30 to 2026-08-31 · late 2026-08-30 to 2026-08-31 · free float · baseline 2026-08-29 to 2026-08-30
|
2 |
0 |
100% |
30-Aug-26 A |
31-Aug-26 A |
29-Aug-26 |
30-Aug-26 |
done |
|
-1 |
|
SY080 COMPLETE Strike outage scaffoldingSCAF · Summit Scaffold · after IB06, IF07, IF13, SY060, SY070
Edit
Predecessors
IB06 FS
IF07 FS
IF13 FS
SY060 FS
SY070 FS
Successors
SY090 FS
Progress to the data date
Change the activity
Early 2026-09-01 to 2026-09-02 · late 2026-09-01 to 2026-09-02 · free float · baseline 2026-09-01 to 2026-09-02
|
2 |
0 |
100% |
01-Sep-26 A |
02-Sep-26 A |
01-Sep-26 |
02-Sep-26 |
done |
|
0 |
|
SY090 COMPLETE Punch walk and pre-startup safety reviewQAQC · after SY030, SY040, SY080
Edit
Predecessors
SY030 FS
SY040 FS
SY080 FS
Successors
SU010 FS
Progress to the data date
Change the activity
Early 2026-09-03 to 2026-09-03 · late 2026-09-03 to 2026-09-03 · free float · baseline 2026-09-03 to 2026-09-03
|
1 |
0 |
100% |
03-Sep-26 A |
03-Sep-26 A |
03-Sep-26 |
03-Sep-26 |
done |
|
0 |
|
SU010 COMPLETE Remove locks and hand the machine back to operationsCOMM · after SY090
Edit
Predecessors
SY090 FS
Successors
SU020 FS
Progress to the data date
Change the activity
Early 2026-09-04 to 2026-09-04 · late 2026-09-04 to 2026-09-04 · free float · baseline 2026-09-04 to 2026-09-04
|
1 |
0 |
100% |
04-Sep-26 A |
04-Sep-26 A |
04-Sep-26 |
04-Sep-26 |
done |
|
0 |
|
SU020 COMPLETE Dry run and jog the drivesCOMM · after SU010
Edit
Predecessors
SU010 FS
Successors
SU030 FS
Progress to the data date
Change the activity
Early 2026-09-05 to 2026-09-06 · late 2026-09-05 to 2026-09-06 · free float · baseline 2026-09-05 to 2026-09-06
|
2 |
0 |
100% |
05-Sep-26 A |
06-Sep-26 A |
05-Sep-26 |
06-Sep-26 |
done |
|
0 |
|
SU030 COMPLETE Hang new press and dryer feltsMILL · Northfield Millwright Services · after SU020
Edit
Predecessors
SU020 FS
Successors
SU040 FS
Progress to the data date
Change the activity
Early 2026-09-07 to 2026-09-07 · late 2026-09-07 to 2026-09-07 · free float · baseline 2026-09-07 to 2026-09-07
|
1 |
0 |
100% |
07-Sep-26 A |
07-Sep-26 A |
07-Sep-26 |
07-Sep-26 |
done |
|
0 |
|
SU040 COMPLETE Steam up and warm the dryersCOMM · after SU030
Edit
Predecessors
SU030 FS
Successors
SU050 FS
Progress to the data date
Change the activity
Early 2026-09-08 to 2026-09-08 · late 2026-09-08 to 2026-09-08 · free float · baseline 2026-09-08 to 2026-09-08
|
1 |
0 |
100% |
08-Sep-26 A |
08-Sep-26 A |
08-Sep-26 |
08-Sep-26 |
done |
|
0 |
|
SU050 COMPLETE Paper on the reelCOMM · Finish on or before 2026-09-08 · after SU040
Edit
Predecessors
SU040 FS
Successors
CL010 FS
Progress to the data date
Change the activity
Early 2026-09-08 to 2026-09-08 · late 2026-09-08 to 2026-09-08 · free float · baseline 2026-09-08 to 2026-09-08
|
MS |
0 |
100% |
08-Sep-26 A |
08-Sep-26 A |
08-Sep-26 |
08-Sep-26 |
done |
|
0 |
|
CL010 COMPLETE 72-hour performance runCOMM · after SU050
Edit
Predecessors
SU050 FS
Successors
CL020 FS CL030 FS CL040 FS
Progress to the data date
Change the activity
Early 2026-09-09 to 2026-09-11 · late 2026-09-09 to 2026-09-11 · free float · baseline 2026-09-09 to 2026-09-11
|
3 |
0 |
100% |
09-Sep-26 A |
11-Sep-26 A |
09-Sep-26 |
11-Sep-26 |
done |
|
0 |
|
| A30 Drive side, gear case and basement 42 activities · 42 complete |
| | 100% |
24-Dec-25 | 31-Aug-26 |
24-Dec-25 | 31-Aug-26 | | |
0 |
|
PR040 COMPLETE Pull new drive and instrument cables to the MCCEI · Delta Electric and Controls · after EN070
Edit
Predecessors
EN070 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2025-12-24 to 2026-01-06 · late 2025-12-24 to 2026-01-06 · free float · baseline 2025-12-24 to 2026-01-06
|
12 |
0 |
100% |
24-Dec-25 A |
06-Jan-26 A |
24-Dec-25 |
06-Jan-26 |
done |
|
0 |
|
OT040 COMPLETE Disconnect steam, condensate and lube oilPIPE · Ironwood Piping · after OT010
Edit
Predecessors
OT010 FS
Successors
RG01 FS RG02 FS RG03 FS RG04 FS RG05 FS RG06 FS RG07 FS RG08 FS RG09 FS RG10 FS RG11 FS RG12 FS RG13 FS RG14 FS
Progress to the data date
Change the activity
Early 2026-08-05 to 2026-08-06 · late 2026-08-05 to 2026-08-06 · free float · baseline 2026-08-05 to 2026-08-06
|
2 |
0 |
100% |
05-Aug-26 A |
06-Aug-26 A |
05-Aug-26 |
06-Aug-26 |
done |
|
0 |
|
OT050 COMPLETE Disconnect drives and instrumentsEI · Delta Electric and Controls · after OT010
Edit
Predecessors
OT010 FS
Successors
None
Progress to the data date
Change the activity
Early 2026-08-05 to 2026-08-05 · late 2026-08-05 to 2026-08-05 · free float · baseline 2026-08-05 to 2026-08-05
|
1 |
0 |
100% |
05-Aug-26 A |
05-Aug-26 A |
05-Aug-26 |
05-Aug-26 |
done |
|
0 |
|
RG01 COMPLETE Remove bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · 3 lift plans · after OT040
Edit
Predecessors
OT040 FS
Successors
RD01 FS RG03 FS
Progress to the data date
Change the activity
Early 2026-08-07 to 2026-08-07 · late 2026-08-07 to 2026-08-07 · free float · baseline 2026-08-07 to 2026-08-07
|
1 |
0 |
100% |
07-Aug-26 A |
07-Aug-26 A |
07-Aug-26 |
07-Aug-26 |
done |
|
0 |
|
RG02 COMPLETE Remove bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · 3 lift plans · after OT040
Edit
Predecessors
OT040 FS
Successors
RD02 FS RG04 FS
Progress to the data date
Change the activity
Early 2026-08-07 to 2026-08-07 · late 2026-08-07 to 2026-08-07 · free float · baseline 2026-08-07 to 2026-08-07
|
1 |
0 |
100% |
07-Aug-26 A |
07-Aug-26 A |
07-Aug-26 |
07-Aug-26 |
done |
|
0 |
|
RG03 COMPLETE Remove bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG01
Edit
Predecessors
OT040 FS
RG01 FS
Successors
LB01 FS RD03 FS RG05 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
RG04 COMPLETE Remove bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG02
Edit
Predecessors
OT040 FS
RG02 FS
Successors
RD04 FS RG06 FS
Progress to the data date
Change the activity
Early 2026-08-08 to 2026-08-08 · late 2026-08-08 to 2026-08-08 · free float · baseline 2026-08-08 to 2026-08-08
|
1 |
0 |
100% |
08-Aug-26 A |
08-Aug-26 A |
08-Aug-26 |
08-Aug-26 |
done |
|
0 |
|
LB01 COMPLETE Line bore and sleeve idler bearing bore IB-1MECH · Precision Line Boring Co · after RG03
Edit
Predecessors
RG03 FS
Successors
IG03 FS LB02 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-10 · late 2026-08-09 to 2026-08-10 · free float · baseline 2026-08-09 to 2026-08-10
|
2 |
0 |
100% |
09-Aug-26 A |
10-Aug-26 A |
09-Aug-26 |
10-Aug-26 |
done |
|
0 |
|
RG05 COMPLETE Remove bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG03
Edit
Predecessors
OT040 FS
RG03 FS
Successors
RD05 FS RG07 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09
|
1 |
0 |
100% |
09-Aug-26 A |
09-Aug-26 A |
09-Aug-26 |
09-Aug-26 |
done |
|
0 |
|
RG06 COMPLETE Remove bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG04
Edit
Predecessors
OT040 FS
RG04 FS
Successors
LB02 FS RD06 FS RG08 FS
Progress to the data date
Change the activity
Early 2026-08-09 to 2026-08-09 · late 2026-08-09 to 2026-08-09 · free float · baseline 2026-08-09 to 2026-08-09
|
1 |
0 |
100% |
09-Aug-26 A |
09-Aug-26 A |
09-Aug-26 |
09-Aug-26 |
done |
|
0 |
|
RG07 COMPLETE Remove bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG05
Edit
Predecessors
OT040 FS
RG05 FS
Successors
RD07 FS RG09 FS
Progress to the data date
Change the activity
Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10
|
1 |
0 |
100% |
10-Aug-26 A |
10-Aug-26 A |
10-Aug-26 |
10-Aug-26 |
done |
|
0 |
|
RG08 COMPLETE Remove bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG06
Edit
Predecessors
OT040 FS
RG06 FS
Successors
RD08 FS RG10 FS
Progress to the data date
Change the activity
Early 2026-08-10 to 2026-08-10 · late 2026-08-10 to 2026-08-10 · free float · baseline 2026-08-10 to 2026-08-10
|
1 |
0 |
100% |
10-Aug-26 A |
10-Aug-26 A |
10-Aug-26 |
10-Aug-26 |
done |
|
0 |
|
LB02 COMPLETE Line bore and sleeve idler bearing bore IB-2MECH · Precision Line Boring Co · after LB01, RG06
Edit
Predecessors
LB01 FS
RG06 FS
Successors
IG06 FS LB03 FS
Progress to the data date
Change the activity
Early 2026-08-11 to 2026-08-13 · late 2026-08-11 to 2026-08-13 · free float · baseline 2026-08-11 to 2026-08-12
|
2 |
0 |
100% |
11-Aug-26 A |
13-Aug-26 A |
11-Aug-26 |
12-Aug-26 |
done |
|
-1 |
|
RG09 COMPLETE Remove bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG07
Edit
Predecessors
OT040 FS
RG07 FS
Successors
LB03 FS RD09 FS RG11 FS
Progress to the data date
Change the activity
Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11
|
1 |
0 |
100% |
11-Aug-26 A |
11-Aug-26 A |
11-Aug-26 |
11-Aug-26 |
done |
|
0 |
|
RG10 COMPLETE Remove bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG08
Edit
Predecessors
OT040 FS
RG08 FS
Successors
RD10 FS RG12 FS
Progress to the data date
Change the activity
Early 2026-08-11 to 2026-08-11 · late 2026-08-11 to 2026-08-11 · free float · baseline 2026-08-11 to 2026-08-11
|
1 |
0 |
100% |
11-Aug-26 A |
11-Aug-26 A |
11-Aug-26 |
11-Aug-26 |
done |
|
0 |
|
RG11 COMPLETE Remove bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG09
Edit
Predecessors
OT040 FS
RG09 FS
Successors
RD11 FS RG13 FS
Progress to the data date
Change the activity
Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12
|
1 |
0 |
100% |
12-Aug-26 A |
12-Aug-26 A |
12-Aug-26 |
12-Aug-26 |
done |
|
0 |
|
RG12 COMPLETE Remove bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG10
Edit
Predecessors
OT040 FS
RG10 FS
Successors
LB04 FS RD12 FS RG14 FS
Progress to the data date
Change the activity
Early 2026-08-12 to 2026-08-12 · late 2026-08-12 to 2026-08-12 · free float · baseline 2026-08-12 to 2026-08-12
|
1 |
0 |
100% |
12-Aug-26 A |
12-Aug-26 A |
12-Aug-26 |
12-Aug-26 |
done |
|
0 |
|
RG13 COMPLETE Remove bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · 3 lift plans · after OT040, RG11
Edit
Predecessors
OT040 FS
RG11 FS
Successors
RD13 FS
Progress to the data date
Change the activity
Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13
|
1 |
0 |
100% |
13-Aug-26 A |
13-Aug-26 A |
13-Aug-26 |
13-Aug-26 |
done |
|
0 |
|
RG14 COMPLETE Remove bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · 2 lift plans · after OT040, RG12
Edit
Predecessors
OT040 FS
RG12 FS
Successors
LB05 FS RD14 FS
Progress to the data date
Change the activity
Early 2026-08-13 to 2026-08-13 · late 2026-08-13 to 2026-08-13 · free float · baseline 2026-08-13 to 2026-08-13
|
1 |
0 |
100% |
13-Aug-26 A |
13-Aug-26 A |
13-Aug-26 |
13-Aug-26 |
done |
|
0 |
|
LB03 COMPLETE Line bore and sleeve idler bearing bore IB-3MECH · Precision Line Boring Co · after LB02, RG09
Edit
Predecessors
LB02 FS
RG09 FS
Successors
IG09 FS LB04 FS
Progress to the data date
Change the activity
Early 2026-08-14 to 2026-08-15 · late 2026-08-14 to 2026-08-15 · free float · baseline 2026-08-13 to 2026-08-14
|
2 |
0 |
100% |
14-Aug-26 A |
15-Aug-26 A |
13-Aug-26 |
14-Aug-26 |
done |
|
-1 |
|
LB04 COMPLETE Line bore and sleeve idler bearing bore IB-4MECH · Precision Line Boring Co · after LB03, RG12
Edit
Predecessors
LB03 FS
RG12 FS
Successors
IG12 FS LB05 FS
Progress to the data date
Change the activity
Early 2026-08-16 to 2026-08-17 · late 2026-08-16 to 2026-08-17 · free float · baseline 2026-08-15 to 2026-08-16
|
2 |
0 |
100% |
16-Aug-26 A |
17-Aug-26 A |
15-Aug-26 |
16-Aug-26 |
done |
|
-1 |
|
IG01 COMPLETE Install bull gear BG-01 and idler gears IG-01, IG-02MILL · Northfield Millwright Services · 3 lift plans · after ID01
Edit
Predecessors
ID01 FS
Successors
IG03 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
IG02 COMPLETE Install bull gear BG-02 and idler gears IG-03, IG-04MILL · Northfield Millwright Services · 3 lift plans · after ID02
Edit
Predecessors
ID02 FS
Successors
IG04 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-18 · late 2026-08-18 to 2026-08-18 · free float · baseline 2026-08-18 to 2026-08-18
|
1 |
0 |
100% |
18-Aug-26 A |
18-Aug-26 A |
18-Aug-26 |
18-Aug-26 |
done |
|
0 |
|
LB05 COMPLETE Line bore and sleeve idler bearing bore IB-5MECH · Precision Line Boring Co · after LB04, RG14
Edit
Predecessors
LB04 FS
RG14 FS
Successors
IG14 FS
Progress to the data date
Change the activity
Early 2026-08-18 to 2026-08-19 · late 2026-08-18 to 2026-08-19 · free float · baseline 2026-08-17 to 2026-08-18
|
2 |
0 |
100% |
18-Aug-26 A |
19-Aug-26 A |
17-Aug-26 |
18-Aug-26 |
done |
|
-1 |
|
IG03 COMPLETE Install bull gear BG-03 and idler gears IG-05, IG-06MILL · Northfield Millwright Services · 3 lift plans · after ID03, IG01, LB01
Edit
Predecessors
ID03 FS
IG01 FS
LB01 FS
Successors
IG05 FS
Progress to the data date
Change the activity
Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
19-Aug-26 A |
19-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
0 |
|
IG04 COMPLETE Install bull gear BG-04 and idler gears IG-07, IG-08MILL · Northfield Millwright Services · 3 lift plans · after ID04, IG02
Edit
Predecessors
ID04 FS
IG02 FS
Successors
IG06 FS
Progress to the data date
Change the activity
Early 2026-08-19 to 2026-08-19 · late 2026-08-19 to 2026-08-19 · free float · baseline 2026-08-19 to 2026-08-19
|
1 |
0 |
100% |
19-Aug-26 A |
19-Aug-26 A |
19-Aug-26 |
19-Aug-26 |
done |
|
0 |
|
IG05 COMPLETE Install bull gear BG-05 and idler gears IG-09, IG-10MILL · Northfield Millwright Services · 3 lift plans · after ID05, IG03
Edit
Predecessors
ID05 FS
IG03 FS
Successors
IG07 FS
Progress to the data date
Change the activity
Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
20-Aug-26 A |
20-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
0 |
|
IG06 COMPLETE Install bull gear BG-06 and idler gears IG-11, IG-12MILL · Northfield Millwright Services · 3 lift plans · after ID06, IG04, LB02
Edit
Predecessors
ID06 FS
IG04 FS
LB02 FS
Successors
IG08 FS
Progress to the data date
Change the activity
Early 2026-08-20 to 2026-08-20 · late 2026-08-20 to 2026-08-20 · free float · baseline 2026-08-20 to 2026-08-20
|
1 |
0 |
100% |
20-Aug-26 A |
20-Aug-26 A |
20-Aug-26 |
20-Aug-26 |
done |
|
0 |
|
IG07 COMPLETE Install bull gear BG-07 and idler gears IG-13, IG-14MILL · Northfield Millwright Services · 3 lift plans · after ID07, IG05
Edit
Predecessors
ID07 FS
IG05 FS
Successors
IG09 FS
Progress to the data date
Change the activity
Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
21-Aug-26 A |
21-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
0 |
|
IG08 COMPLETE Install bull gear BG-08 and idler gears IG-15, IG-16MILL · Northfield Millwright Services · 3 lift plans · after ID08, IG06
Edit
Predecessors
ID08 FS
IG06 FS
Successors
IG10 FS
Progress to the data date
Change the activity
Early 2026-08-21 to 2026-08-21 · late 2026-08-21 to 2026-08-21 · free float · baseline 2026-08-21 to 2026-08-21
|
1 |
0 |
100% |
21-Aug-26 A |
21-Aug-26 A |
21-Aug-26 |
21-Aug-26 |
done |
|
0 |
|
IG09 COMPLETE Install bull gear BG-09 and idler gears IG-17, IG-18MILL · Northfield Millwright Services · 3 lift plans · after ID09, IG07, LB03
Edit
Predecessors
ID09 FS
IG07 FS
LB03 FS
Successors
IG11 FS
Progress to the data date
Change the activity
Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
22-Aug-26 A |
22-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
0 |
|
IG10 COMPLETE Install bull gear BG-10 and idler gears IG-19, IG-20MILL · Northfield Millwright Services · 3 lift plans · after ID10, IG08
Edit
Predecessors
ID10 FS
IG08 FS
Successors
IG12 FS
Progress to the data date
Change the activity
Early 2026-08-22 to 2026-08-22 · late 2026-08-22 to 2026-08-22 · free float · baseline 2026-08-22 to 2026-08-22
|
1 |
0 |
100% |
22-Aug-26 A |
22-Aug-26 A |
22-Aug-26 |
22-Aug-26 |
done |
|
0 |
|
IG11 COMPLETE Install bull gear BG-11 and idler gears IG-21, IG-22MILL · Northfield Millwright Services · 3 lift plans · after ID11, IG09
Edit
Predecessors
ID11 FS
IG09 FS
Successors
IG13 FS
Progress to the data date
Change the activity
Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
23-Aug-26 A |
23-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
0 |
|
IG12 COMPLETE Install bull gear BG-12 and idler gears IG-23, IG-24MILL · Northfield Millwright Services · 3 lift plans · after ID12, IG10, LB04
Edit
Predecessors
ID12 FS
IG10 FS
LB04 FS
Successors
IG14 FS
Progress to the data date
Change the activity
Early 2026-08-23 to 2026-08-23 · late 2026-08-23 to 2026-08-23 · free float · baseline 2026-08-23 to 2026-08-23
|
1 |
0 |
100% |
23-Aug-26 A |
23-Aug-26 A |
23-Aug-26 |
23-Aug-26 |
done |
|
0 |
|
IG13 COMPLETE Install bull gear BG-13 and idler gears IG-25, IG-26MILL · Northfield Millwright Services · 3 lift plans · after ID13, IG11
Edit
Predecessors
ID13 FS
IG11 FS
Successors
SY050 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24
|
1 |
0 |
100% |
24-Aug-26 A |
24-Aug-26 A |
24-Aug-26 |
24-Aug-26 |
done |
|
0 |
|
IG14 COMPLETE Install bull gear BG-14 and idler gear IG-27MILL · Northfield Millwright Services · 2 lift plans · after ID14, IG12, LB05
Edit
Predecessors
ID14 FS
IG12 FS
LB05 FS
Successors
SY040 SS SY050 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-24 · late 2026-08-24 to 2026-08-24 · free float · baseline 2026-08-24 to 2026-08-24
|
1 |
0 |
100% |
24-Aug-26 A |
24-Aug-26 A |
24-Aug-26 |
24-Aug-26 |
done |
|
0 |
|
SY010 COMPLETE Reconnect steam joints, syphons and condensatePIPE · Ironwood Piping · after ID13, ID14
Edit
Predecessors
ID13 FS
ID14 FS
Successors
SY020 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-27 · late 2026-08-24 to 2026-08-27 · free float · baseline 2026-08-24 to 2026-08-27
|
4 |
0 |
100% |
24-Aug-26 A |
27-Aug-26 A |
24-Aug-26 |
27-Aug-26 |
done |
|
0 |
|
SY040 COMPLETE Reconnect drives and instruments, loop checkEI · Delta Electric and Controls · after IG14
Edit
Predecessors
IG14 SS
Successors
SY090 FS
Progress to the data date
Change the activity
Early 2026-08-24 to 2026-08-26 · late 2026-08-24 to 2026-08-26 · free float · baseline 2026-08-24 to 2026-08-26
|
3 |
0 |
100% |
24-Aug-26 A |
26-Aug-26 A |
24-Aug-26 |
26-Aug-26 |
done |
|
0 |
|
SY050 COMPLETE Gear mesh, backlash and runout checksMILL · Northfield Millwright Services · after IG13, IG14
Edit
Predecessors
IG13 FS
IG14 FS
Successors
SY060 FS
Progress to the data date
Change the activity
Early 2026-08-25 to 2026-08-26 · late 2026-08-25 to 2026-08-26 · free float · baseline 2026-08-25 to 2026-08-26
|
2 |
0 |
100% |
25-Aug-26 A |
26-Aug-26 A |
25-Aug-26 |
26-Aug-26 |
done |
|
0 |
|
SY020 COMPLETE Hydro test dryers and steam jointsQAQC · after SY010
Edit
Predecessors
SY010 FS
Successors
SY030 SS SY070 FS
Progress to the data date
Change the activity
Early 2026-08-28 to 2026-08-28 · late 2026-08-28 to 2026-08-28 · free float · baseline 2026-08-28 to 2026-08-28
|
1 |
0 |
100% |
28-Aug-26 A |
28-Aug-26 A |
28-Aug-26 |
28-Aug-26 |
done |
|
0 |
|
SY030 COMPLETE Flush the lube oil systemPIPE · Ironwood Piping · after SY020
Edit
Predecessors
SY020 SS
Successors
SY090 FS
Progress to the data date
Change the activity
Early 2026-08-28 to 2026-08-30 · late 2026-08-28 to 2026-08-30 · free float · baseline 2026-08-28 to 2026-08-30
|
3 |
0 |
100% |
28-Aug-26 A |
30-Aug-26 A |
28-Aug-26 |
30-Aug-26 |
done |
|
0 |
|
SY070 COMPLETE Insulate steam and condensate pipingINSUL · ThermaCoat Insulation · after SY020
Edit
Predecessors
SY020 FS
Successors
SY080 FS
Progress to the data date
Change the activity
Early 2026-08-29 to 2026-08-31 · late 2026-08-29 to 2026-08-31 · free float · baseline 2026-08-29 to 2026-08-31
|
3 |
0 |
100% |
29-Aug-26 A |
31-Aug-26 A |
29-Aug-26 |
31-Aug-26 |
done |
|
0 |
|
| A80 Shops, fabrication and laydown 15 activities · 15 complete |
| | 100% |
13-Dec-25 | 14-Jul-26 |
13-Dec-25 | 14-Jul-26 | | |
0 |
|
FB040 COMPLETE Fabricate 14 dryer cansPMGT · after EN020
Edit
Predecessors
EN020 FS
Successors
FB045 FS
Progress to the data date
Change the activity
Early 2025-12-13 to 2026-04-23 · late 2025-12-13 to 2026-04-23 · free float · baseline 2025-12-13 to 2026-04-23
|
130 |
0 |
100% |
13-Dec-25 A |
23-Apr-26 A |
13-Dec-25 |
23-Apr-26 |
done |
|
0 |
|
FB080 COMPLETE Fabricate and balance 13 felt rollsPMGT · after EN020
Edit
Predecessors
EN020 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2025-12-13 to 2026-03-04 · late 2025-12-13 to 2026-03-04 · free float · baseline 2025-12-13 to 2026-03-04
|
80 |
0 |
100% |
13-Dec-25 A |
04-Mar-26 A |
13-Dec-25 |
04-Mar-26 |
done |
|
0 |
|
FB090 COMPLETE Fabricate 6 blow boxesPMGT · after EN020
Edit
Predecessors
EN020 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2025-12-13 to 2026-02-22 · late 2025-12-13 to 2026-02-22 · free float · baseline 2025-12-13 to 2026-02-22
|
70 |
0 |
100% |
13-Dec-25 A |
22-Feb-26 A |
13-Dec-25 |
22-Feb-26 |
done |
|
0 |
|
FB060 COMPLETE Machine 14 bull gearsPMGT · after EN030
Edit
Predecessors
EN030 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2025-12-14 to 2026-03-25 · late 2025-12-14 to 2026-03-25 · free float · baseline 2025-12-14 to 2026-03-25
|
100 |
0 |
100% |
14-Dec-25 A |
25-Mar-26 A |
14-Dec-25 |
25-Mar-26 |
done |
|
0 |
|
FB070 COMPLETE Machine 27 idler gearsPMGT · after EN030
Edit
Predecessors
EN030 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2025-12-14 to 2026-03-15 · late 2025-12-14 to 2026-03-15 · free float · baseline 2025-12-14 to 2026-03-15
|
90 |
0 |
100% |
14-Dec-25 A |
15-Mar-26 A |
14-Dec-25 |
15-Mar-26 |
done |
|
0 |
|
FB100 COMPLETE Bearings, bore sleeves and housingsPMGT · after EN040
Edit
Predecessors
EN040 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2025-12-21 to 2026-02-20 · late 2025-12-21 to 2026-02-20 · free float · baseline 2025-12-21 to 2026-02-20
|
60 |
0 |
100% |
21-Dec-25 A |
20-Feb-26 A |
21-Dec-25 |
20-Feb-26 |
done |
|
0 |
|
PR030 COMPLETE Prefabricate steam, condensate and syphon spoolsPIPE · Ironwood Piping · after EN060
Edit
Predecessors
EN060 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2025-12-30 to 2026-01-27 · late 2025-12-30 to 2026-01-27 · free float · baseline 2025-12-30 to 2026-01-24
|
25 |
0 |
100% |
30-Dec-25 A |
27-Jan-26 A |
30-Dec-25 |
24-Jan-26 |
done |
|
-3 |
|
FB010 COMPLETE Fabricate new press section (OEM)PMGT · after EN010
Edit
Predecessors
EN010 FS
Successors
FB020 FS
Progress to the data date
Change the activity
Early 2026-01-15 to 2026-06-22 · late 2026-01-15 to 2026-06-22 · free float · baseline 2026-01-15 to 2026-06-13
|
150 |
0 |
100% |
15-Jan-26 A |
22-Jun-26 A |
15-Jan-26 |
13-Jun-26 |
done |
|
-9 |
|
FB045 COMPLETE Dryer pressure vessel inspection and code stampsQAQC · after FB040
Edit
Predecessors
FB040 FS
Successors
FB050 FS
Progress to the data date
Change the activity
Early 2026-04-24 to 2026-04-28 · late 2026-04-24 to 2026-04-28 · free float · baseline 2026-04-24 to 2026-04-28
|
5 |
0 |
100% |
24-Apr-26 A |
28-Apr-26 A |
24-Apr-26 |
28-Apr-26 |
done |
|
0 |
|
FB050 COMPLETE Ship 14 dryersPMGT · after FB045
Edit
Predecessors
FB045 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2026-04-29 to 2026-05-06 · late 2026-04-29 to 2026-05-06 · free float · baseline 2026-04-29 to 2026-05-06
|
8 |
0 |
100% |
29-Apr-26 A |
06-May-26 A |
29-Apr-26 |
06-May-26 |
done |
|
0 |
|
PR010 COMPLETE Set up laydown, staging and outage trailersMILL · Northfield Millwright Services · Start on or after 2026-06-20 · after PC040
Edit
Predecessors
PC040 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2026-06-20 to 2026-06-24 · late 2026-06-20 to 2026-06-24 · free float · baseline 2026-06-20 to 2026-06-24
|
5 |
0 |
100% |
20-Jun-26 A |
24-Jun-26 A |
20-Jun-26 |
24-Jun-26 |
done |
|
0 |
|
FB020 COMPLETE Press section factory acceptance testQAQC · after FB010
Edit
Predecessors
FB010 FS
Successors
FB030 FS
Progress to the data date
Change the activity
Early 2026-06-23 to 2026-06-26 · late 2026-06-23 to 2026-06-26 · free float · baseline 2026-06-14 to 2026-06-17
|
4 |
0 |
100% |
23-Jun-26 A |
26-Jun-26 A |
14-Jun-26 |
17-Jun-26 |
done |
|
-9 |
|
FB030 COMPLETE Ship press section to the millPMGT · after FB020
Edit
Predecessors
FB020 FS
Successors
FB110 FF
Progress to the data date
Change the activity
Early 2026-06-27 to 2026-07-08 · late 2026-06-27 to 2026-07-08 · free float · baseline 2026-06-18 to 2026-06-29
|
12 |
0 |
100% |
27-Jun-26 A |
08-Jul-26 A |
18-Jun-26 |
29-Jun-26 |
done |
|
-9 |
|
FB110 COMPLETE Receive, inspect and stage all equipment at the laydownMILL · Northfield Millwright Services · after FB030, FB050, FB060, FB070, FB080, FB090, FB100
Edit
Predecessors
FB030 FF
FB050 FF
FB060 FF
FB070 FF
FB080 FF
FB090 FF
FB100 FF
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2026-07-01 to 2026-07-08 · late 2026-07-01 to 2026-07-08 · free float · baseline 2026-06-22 to 2026-06-29
|
8 |
0 |
100% |
01-Jul-26 A |
08-Jul-26 A |
22-Jun-26 |
29-Jun-26 |
done |
|
-9 |
|
PR020 COMPLETE Scaffold design and pre-build of outage scaffoldsSCAF · Summit Scaffold · Start on or after 2026-07-05 · after EN050
Edit
Predecessors
EN050 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2026-07-05 to 2026-07-14 · late 2026-07-05 to 2026-07-14 · free float · baseline 2026-07-05 to 2026-07-14
|
10 |
0 |
100% |
05-Jul-26 A |
14-Jul-26 A |
05-Jul-26 |
14-Jul-26 |
done |
|
0 |
|
| A90 Office and engineering 19 activities · 19 complete |
| | 100% |
26-Nov-25 | 07-Oct-26 |
26-Nov-25 | 06-Oct-26 | | |
-1 |
|
PC010 COMPLETE Kickoff meeting and scope walk with the millPMGT · after PO000
Edit
Predecessors
PO000 FS
Successors
EN010 FS EN020 FS +10d PC020 FS PC030 FS
Progress to the data date
Change the activity
Early 2025-11-26 to 2025-11-28 · late 2025-11-26 to 2025-11-28 · free float · baseline 2025-11-26 to 2025-11-28
|
2 |
0 |
100% |
26-Nov-25 A |
28-Nov-25 A |
26-Nov-25 |
28-Nov-25 |
done |
|
0 |
|
PO000 COMPLETE Purchase order receivedPMGT · Must start on 2025-11-26
Edit
Predecessors
None
Successors
PC010 FS
Progress to the data date
Change the activity
Early 2025-11-26 to 2025-11-26 · late 2025-11-26 to 2025-11-26 · free float · baseline 2025-11-26 to 2025-11-26
|
MS |
0 |
100% |
26-Nov-25 A |
26-Nov-25 A |
26-Nov-25 |
26-Nov-25 |
done |
|
0 |
|
EN010 COMPLETE Press section design and approval drawings (OEM)PMGT · after PC010
Edit
Predecessors
PC010 FS
Successors
EN080 SS +20d FB010 FS
Progress to the data date
Change the activity
Early 2025-11-29 to 2026-01-14 · late 2025-11-29 to 2026-01-14 · free float · baseline 2025-11-29 to 2026-01-14
|
45 |
0 |
100% |
29-Nov-25 A |
14-Jan-26 A |
29-Nov-25 |
14-Jan-26 |
done |
|
0 |
|
EN030 COMPLETE Gear train review: 14 bull gears and 27 idler gearsMILL · Northfield Millwright Services · after PC030
Edit
Predecessors
PC030 SS
Successors
FB060 FS FB070 FS
Progress to the data date
Change the activity
Early 2025-11-29 to 2025-12-13 · late 2025-11-29 to 2025-12-13 · free float · baseline 2025-11-29 to 2025-12-13
|
15 |
0 |
100% |
29-Nov-25 A |
13-Dec-25 A |
29-Nov-25 |
13-Dec-25 |
done |
|
0 |
|
PC020 COMPLETE Site safety plan, JHAs and outage lift plan approvedPMGT · after PC010
Edit
Predecessors
PC010 FS
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2025-11-29 to 2025-12-08 · late 2025-11-29 to 2025-12-08 · free float · baseline 2025-11-29 to 2025-12-08
|
10 |
0 |
100% |
29-Nov-25 A |
08-Dec-25 A |
29-Nov-25 |
08-Dec-25 |
done |
|
0 |
|
PC030 COMPLETE Award millwright, rigging, line boring, piping, E&I, scaffold and insulationPMGT · after PC010
Edit
Predecessors
PC010 FS
Successors
EN030 SS EN040 FS EN050 FS EN060 FS EN070 SS +5d PC040 FS
Progress to the data date
Change the activity
Early 2025-11-29 to 2025-12-13 · late 2025-11-29 to 2025-12-13 · free float · baseline 2025-11-29 to 2025-12-13
|
15 |
0 |
100% |
29-Nov-25 A |
13-Dec-25 A |
29-Nov-25 |
13-Dec-25 |
done |
|
0 |
|
EN070 COMPLETE Drive, controls and instrument designEI · Delta Electric and Controls · after PC030
Edit
Predecessors
PC030 SS +5d
Successors
PR040 FS
Progress to the data date
Change the activity
Early 2025-12-04 to 2025-12-23 · late 2025-12-04 to 2025-12-23 · free float · baseline 2025-12-04 to 2025-12-23
|
20 |
0 |
100% |
04-Dec-25 A |
23-Dec-25 A |
04-Dec-25 |
23-Dec-25 |
done |
|
0 |
|
EN040 COMPLETE Line bore and sleeve procedure for 5 idler bearing boresMECH · Precision Line Boring Co · after PC030
Edit
Predecessors
PC030 FS
Successors
FB100 FS
Progress to the data date
Change the activity
Early 2025-12-14 to 2025-12-20 · late 2025-12-14 to 2025-12-20 · free float · baseline 2025-12-14 to 2025-12-20
|
7 |
0 |
100% |
14-Dec-25 A |
20-Dec-25 A |
14-Dec-25 |
20-Dec-25 |
done |
|
0 |
|
EN050 COMPLETE Lift plans: press section, dryers, gears, rollsRIG · Apex Rigging and Crane · after PC030
Edit
Predecessors
PC030 FS
Successors
PR020 FS PR050 FS
Progress to the data date
Change the activity
Early 2025-12-14 to 2025-12-26 · late 2025-12-14 to 2025-12-26 · free float · baseline 2025-12-14 to 2025-12-26
|
12 |
0 |
100% |
14-Dec-25 A |
26-Dec-25 A |
14-Dec-25 |
26-Dec-25 |
done |
|
0 |
|
EN060 COMPLETE Steam joint, syphon and condensate piping isometricsPIPE · Ironwood Piping · after EN020, PC030
Edit
Predecessors
EN020 SS
PC030 FS
Successors
PR030 FS
Progress to the data date
Change the activity
Early 2025-12-14 to 2025-12-29 · late 2025-12-14 to 2025-12-29 · free float · baseline 2025-12-14 to 2025-12-29
|
15 |
0 |
100% |
14-Dec-25 A |
29-Dec-25 A |
14-Dec-25 |
29-Dec-25 |
done |
|
0 |
|
PC040 COMPLETE Baseline schedule and outage plan approved by the millPMGT · after PC030
Edit
Predecessors
PC030 FS
Successors
PR010 FS
Progress to the data date
Change the activity
Early 2025-12-14 to 2025-12-20 · late 2025-12-14 to 2025-12-20 · free float · baseline 2025-12-14 to 2025-12-20
|
7 |
0 |
100% |
14-Dec-25 A |
20-Dec-25 A |
14-Dec-25 |
20-Dec-25 |
done |
|
0 |
|
EN080 COMPLETE Inspection and test plans approvedQAQC · after EN010
Edit
Predecessors
EN010 SS +20d
Successors
PR080 FS
Progress to the data date
Change the activity
Early 2025-12-19 to 2025-12-24 · late 2025-12-19 to 2025-12-24 · free float · baseline 2025-12-19 to 2025-12-24
|
6 |
0 |
100% |
19-Dec-25 A |
24-Dec-25 A |
19-Dec-25 |
24-Dec-25 |
done |
|
0 |
|
PR070 COMPLETE Outage safety stand-down and site orientation, all crewsPMGT · Start on or after 2026-07-31
Edit
Predecessors
None
Successors
PR080 FF
Progress to the data date
Change the activity
Early 2026-07-31 to 2026-07-31 · late 2026-07-31 to 2026-07-31 · free float · baseline 2026-07-31 to 2026-07-31
|
1 |
0 |
100% |
31-Jul-26 A |
31-Jul-26 A |
31-Jul-26 |
31-Jul-26 |
done |
|
0 |
|
PR080 COMPLETE Outage readiness review with the millPMGT · after EN080, FB110, PC020, PR010, PR020, PR030, PR040, PR050, PR060, PR070
Edit
Predecessors
EN080 FS
FB110 FS
PC020 FS
PR010 FS
PR020 FS
PR030 FS
PR040 FS
PR050 FS
PR060 FS
PR070 FF
Successors
OT000 FS
Progress to the data date
Change the activity
Early 2026-07-31 to 2026-07-31 · late 2026-07-31 to 2026-07-31 · free float · baseline 2026-07-31 to 2026-07-31
|
1 |
0 |
100% |
31-Jul-26 A |
31-Jul-26 A |
31-Jul-26 |
31-Jul-26 |
done |
|
0 |
|
CL020 COMPLETE Close the punch listQAQC · after CL010
Edit
Predecessors
CL010 FS
Successors
CL900 FS
Progress to the data date
Change the activity
Early 2026-09-12 to 2026-09-21 · late 2026-09-12 to 2026-09-21 · free float · baseline 2026-09-12 to 2026-09-21
|
10 |
0 |
100% |
12-Sep-26 A |
21-Sep-26 A |
12-Sep-26 |
21-Sep-26 |
done |
|
0 |
|
CL030 COMPLETE Turnover packages accepted by the millPMGT · after CL010
Edit
Predecessors
CL010 FS
Successors
CL050 FS
Progress to the data date
Change the activity
Early 2026-09-12 to 2026-09-21 · late 2026-09-12 to 2026-09-21 · free float · baseline 2026-09-12 to 2026-09-21
|
10 |
0 |
100% |
12-Sep-26 A |
21-Sep-26 A |
12-Sep-26 |
21-Sep-26 |
done |
|
0 |
|
CL040 COMPLETE As-built drawings and alignment reportsPMGT · after CL010
Edit
Predecessors
CL010 FS
Successors
CL050 FS
Progress to the data date
Change the activity
Early 2026-09-12 to 2026-09-27 · late 2026-09-12 to 2026-09-27 · free float · baseline 2026-09-12 to 2026-09-26
|
15 |
0 |
100% |
12-Sep-26 A |
27-Sep-26 A |
12-Sep-26 |
26-Sep-26 |
done |
|
-1 |
|
CL050 COMPLETE Final cost report and lessons learnedPMGT · after CL030, CL040
Edit
Predecessors
CL030 FS
CL040 FS
Successors
CL900 FS
Progress to the data date
Change the activity
Early 2026-09-28 to 2026-10-07 · late 2026-09-28 to 2026-10-07 · free float · baseline 2026-09-27 to 2026-10-06
|
10 |
0 |
100% |
28-Sep-26 A |
07-Oct-26 A |
27-Sep-26 |
06-Oct-26 |
done |
|
-1 |
|
CL900 COMPLETE Project turned overPMGT · after CL020, CL050
Edit
Predecessors
CL020 FS
CL050 FS
Successors
None
Progress to the data date
Change the activity
Early 2026-10-07 to 2026-10-07 · late 2026-10-07 to 2026-10-07 · free float · baseline 2026-10-06 to 2026-10-06
|
MS |
0 |
100% |
07-Oct-26 A |
07-Oct-26 A |
06-Oct-26 |
06-Oct-26 |
done |
|
-1 |
|