SAMPLE PROJECT · Invented data, read-only · Back to xpcspine.com
XPC Spine PM3-REBUILDPaper Machine 3 Press and Dryer Section Rebuild
Help

Help ›

Client master board

The client never sees the live boards, only the frozen updates the PM or CM approves on the client master board.

Client master board Latest report

Approve a release

  1. Open Client master board. Give it a title and tick the sections: progress by trade, milestones, delay register, and cost only if the contract shares cost.
  2. Add a note to the client if you want, then Approve and release under your name.
  3. Later changes reach the client only in a new release. Delays still OPEN are not released.

Read your report

  1. When you sign in you open the latest update the PM or CM released to your master board.
  2. Press Print or save as PDF to keep a copy.

Ask the guide

Shows the help topics that match your question.

Other topics

Getting started on a new project · Signing in, two-step and work accounts · Setting up a new project · Trade boards and trade leads · P6 schedule, Gantt and the scheduler · Working over each other · Safety control center · Safety training and OSHA cards · Rigging and lift plans · Meetings · Delay log · Client delay report · Change orders, back-charges and pay apps · Drawings, revisions and board photos · Procurement and document control · Client NDA · Live connectors · Live boards · Your scope page (contractors)