Setting up a new project
Five short steps on one page. Only the basics are needed; every other step can be skipped.
New project Advanced setup Finish setting up Upload data Settings Lifecycle
Start
- On Projects, press New project. A PM or an administrator creates projects; whoever creates one becomes its PM.
- The bar at the top shows the five steps. Next and Back move between them; Skip takes the default.
- Nothing is created until you press Create project on the last step.
1. Project basics
- Type the project name, the client and the site, and the start and finish dates.
- The project code is suggested from the name. Change it if your company uses its own codes.
2. Project type
- Pick the card closest to your job: paper or pulp mill rebuild, power plant or boiler outage, or one under More project types. Blank starts with nothing ticked.
- The card shows what it adds: trades, areas, lifecycle phases with their gate checklists, and the boards.
- Untick any area, phase or gate item you do not want. Add other areas as 'CODE, Name', one per line.
- Skipped: Blank, with the standard five phases.
3. Trades and contractors
- The project type's trades are ticked. Each trade gets its own board. Tick or untick, or add others as 'CODE, Name'.
- Type the contractor names next to each trade, separated by commas. You can add them later.
- Skipped with nothing ticked: civil, structural, mechanical, piping and E&I.
4. P6 schedule (optional)
- Choose your P6 export (.xer, or .csv with activity, name and trade columns) and press Read the file.
- The areas, trades and contractors in it are listed and ticked. Match each P6 trade code to a trade, make it a new trade, or leave it out.
- Area and trade codes then match the schedule, so every activity lands on its board.
- On Create the schedule loads and is set as the baseline.
5. Review and create
- Check the list. Anything wrong is shown in plain words on the step it belongs to.
- Press Create project. Everything is saved together, or nothing is.
- The project opens with its NDA first (every project is closed until it is signed), then Finish setting up: assign trade leads, publish the client's NDA, load the drawing list and cost report, invite people.
Advanced setup
- The older one-page form is still under Advanced setup on the New project page, with every field typed in. It is for administrators only.
Change it later
- Settings edits the project details, each board (title, owner, readers, contractors, tie-in words, doc control folders, forms) and phase dates and gate items.
- Add a trade board at the bottom of the Boards list.
- If one person runs two trades, give them both boards rather than merging the trades.
- Lifecycle shows the phases and their gate checklists. Tick gate items and set the current phase there.
Settings is for the PM only; the CM assigns trade leads and uses Lifecycle.
Load the data
- On Upload data pick what the file is, choose the file and press Upload.
- Load the P6 schedule first (if you did not in setup), then the cost report, then the doc control drawing list.
- Daily logs and the watch list go in as they come.
- Every board reads MISSING or NEVER until its data arrives. A file that cannot be read changes nothing and marks the feed FAILED.