Safety control center
Safety comes first on this project. Every pre-task plan, permit, inspection, corrective action, incident, stop-work and toolbox talk is recorded here with who entered it. Anyone may stop work. Safety reports stay open to every field supervisor at all times.
Plans for today
0
Source: safety_pretask
Not yet reviewed
0
Source: safety_pretask
Pre-task plans (JHA)
Each crew plans the task before starting: the steps, the hazards and the control for each. A plan that needs a permit with none open for that trade today is flagged.
| Ref | Date | Trade | Task | Hazards | Controls | Permits | Crew | Reviewed |
|---|---|---|---|---|---|---|---|---|
| JHA-262 | 2026-09-21 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-21 |
| JHA-261 | 2026-09-21 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-21 | |
| JHA-260 | 2026-09-21 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-21 | |
| JHA-259 | 2026-09-20 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-20 |
| JHA-258 | 2026-09-20 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-20 | |
| JHA-257 | 2026-09-20 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-20 | |
| JHA-256 | 2026-09-19 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-19 |
| JHA-255 | 2026-09-19 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-19 | |
| JHA-254 | 2026-09-19 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-19 | |
| JHA-253 | 2026-09-18 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-18 |
| JHA-252 | 2026-09-18 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-18 | |
| JHA-251 | 2026-09-18 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-18 | |
| JHA-250 | 2026-09-17 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-17 |
| JHA-249 | 2026-09-17 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-17 | |
| JHA-248 | 2026-09-17 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-17 | |
| JHA-247 | 2026-09-16 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-16 |
| JHA-246 | 2026-09-16 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-16 | |
| JHA-245 | 2026-09-16 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-16 | |
| JHA-244 | 2026-09-15 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-15 |
| JHA-243 | 2026-09-15 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-15 | |
| JHA-242 | 2026-09-15 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-15 | |
| JHA-241 | 2026-09-14 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-14 |
| JHA-240 | 2026-09-14 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-14 | |
| JHA-239 | 2026-09-14 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-14 | |
| JHA-238 | 2026-09-13 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-13 |
| JHA-237 | 2026-09-13 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-13 | |
| JHA-236 | 2026-09-13 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-13 | |
| JHA-235 | 2026-09-12 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-12 |
| JHA-234 | 2026-09-12 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-12 | |
| JHA-233 | 2026-09-12 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 3 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-12 | |
| JHA-232 | 2026-09-11 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-11 |
| JHA-231 | 2026-09-11 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-11 | |
| JHA-230 | 2026-09-11 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-11 | |
| JHA-229 | 2026-09-10 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-10 |
| JHA-228 | 2026-09-10 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-10 | |
| JHA-227 | 2026-09-10 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-10 | |
| JHA-226 | 2026-09-09 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-09 |
| JHA-225 | 2026-09-09 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-09 | |
| JHA-224 | 2026-09-09 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-09 | |
| JHA-223 | 2026-09-08 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-08 |
| JHA-222 | 2026-09-08 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-08 | |
| JHA-221 | 2026-09-08 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-08 | |
| JHA-220 | 2026-09-07 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-07 |
| JHA-219 | 2026-09-07 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-07 | |
| JHA-218 | 2026-09-07 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-07 | |
| JHA-217 | 2026-09-06 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-06 |
| JHA-216 | 2026-09-06 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-06 | |
| JHA-215 | 2026-09-06 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-06 | |
| JHA-214 | 2026-09-05 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-05 |
| JHA-213 | 2026-09-05 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-05 | |
| JHA-212 | 2026-09-05 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-05 | |
| JHA-211 | 2026-09-04 | EI | Punch list: labels, glands and as-built mark-ups Drive side and MCC room | Live equipment nearby | Operations work permit; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-04 |
| JHA-210 | 2026-09-04 | PIPE | Punch list: supports and insulation repairs Basement, drive side | Hot surfaces with the machine running | Work permits from operations; gloves | Marcus Lee · 3 Marcus Lee |
Carl Mendez, Superintendent 2026-09-04 | |
| JHA-209 | 2026-09-04 | MILL | Punch list and demob Dryer section, tending side | Manual handling; forklift traffic | Spotter for every forklift move | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-04 | |
| JHA-208 | 2026-09-03 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-03 |
| JHA-207 | 2026-09-03 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-09-03 |
| JHA-206 | 2026-09-03 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-03 |
| JHA-205 | 2026-09-02 | INSUL | Insulate steam and condensate piping Basement, steam and condensate | Fibres; hot surfaces near the run | Gloves and sleeves; lines confirmed cold | Beth Carver · 3 Beth Carver |
Carl Mendez, Superintendent 2026-09-02 | |
| JHA-204 | 2026-09-02 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-02 |
| JHA-203 | 2026-09-02 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 7 Tony Alvarez |
Carl Mendez, Superintendent 2026-09-02 |
| JHA-202 | 2026-09-02 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-09-02 |
| JHA-201 | 2026-09-02 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-02 |
| JHA-200 | 2026-09-01 | INSUL | Insulate steam and condensate piping Basement, steam and condensate | Fibres; hot surfaces near the run | Gloves and sleeves; lines confirmed cold | Beth Carver · 3 Beth Carver |
Carl Mendez, Superintendent 2026-09-01 | |
| JHA-199 | 2026-09-01 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-09-01 |
| JHA-198 | 2026-09-01 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 7 Tony Alvarez |
Carl Mendez, Superintendent 2026-09-01 |
| JHA-197 | 2026-09-01 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-09-01 |
| JHA-196 | 2026-09-01 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-09-01 |
| JHA-195 | 2026-08-31 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-31 |
| JHA-194 | 2026-08-31 | INSUL | Insulate steam and condensate piping Basement, steam and condensate | Fibres; hot surfaces near the run | Gloves and sleeves; lines confirmed cold | Beth Carver · 3 Beth Carver |
Carl Mendez, Superintendent 2026-08-31 | |
| JHA-193 | 2026-08-31 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-31 |
| JHA-192 | 2026-08-31 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-31 |
| JHA-191 | 2026-08-31 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-31 |
| JHA-190 | 2026-08-31 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-31 |
| JHA-189 | 2026-08-30 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-30 |
| JHA-188 | 2026-08-30 | INSUL | Insulate steam and condensate piping Basement, steam and condensate | Fibres; hot surfaces near the run | Gloves and sleeves; lines confirmed cold | Beth Carver · 3 Beth Carver |
Carl Mendez, Superintendent 2026-08-30 | |
| JHA-187 | 2026-08-30 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-30 |
| JHA-186 | 2026-08-30 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-30 |
| JHA-185 | 2026-08-30 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-30 |
| JHA-184 | 2026-08-30 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-30 |
| JHA-183 | 2026-08-29 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-182 | 2026-08-29 | INSUL | Insulate steam and condensate piping Basement, steam and condensate | Fibres; hot surfaces near the run | Gloves and sleeves; lines confirmed cold | Beth Carver · 3 Beth Carver |
Carl Mendez, Superintendent 2026-08-29 | |
| JHA-181 | 2026-08-29 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-180 | 2026-08-29 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-179 | 2026-08-29 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-178 | 2026-08-29 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 3 R. Okafor |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-177 | 2026-08-29 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-29 |
| JHA-176 | 2026-08-28 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-175 | 2026-08-28 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-174 | 2026-08-28 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-173 | 2026-08-28 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-172 | 2026-08-28 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 3 R. Okafor |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-171 | 2026-08-28 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-28 |
| JHA-170 | 2026-08-27 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-169 | 2026-08-27 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-168 | 2026-08-27 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-167 | 2026-08-27 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-166 | 2026-08-27 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 4 R. Okafor |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-165 | 2026-08-27 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-27 |
| JHA-164 | 2026-08-26 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-163 | 2026-08-26 | MECH | Machine journal seats in place (CO-008) Gear case, drive side | Rotating cutter; chips; noise | Cutter guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 3 Wes Turner |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-162 | 2026-08-26 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-161 | 2026-08-26 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-160 | 2026-08-26 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-159 | 2026-08-26 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 4 R. Okafor |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-158 | 2026-08-26 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-26 |
| JHA-157 | 2026-08-25 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-156 | 2026-08-25 | MECH | Machine journal seats in place (CO-008) Gear case, drive side | Rotating cutter; chips; noise | Cutter guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 3 Wes Turner |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-155 | 2026-08-25 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-154 | 2026-08-25 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-153 | 2026-08-25 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-152 | 2026-08-25 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 4 R. Okafor |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-151 | 2026-08-25 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-25 |
| JHA-150 | 2026-08-24 | SURV | Final alignment survey Press and dryer section | Work near open edges | Harness tied off above 6 ft | Work at height | Hannah Price · 3 Hannah Price |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-149 | 2026-08-24 | EI | Reconnect drives and instruments; loop checks Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 3 Priya Raman |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-148 | 2026-08-24 | SCAF | Strike outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-147 | 2026-08-24 | PIPE | Reconnect steam joints and syphons; hydro test Basement, drive side | Stored pressure; hot work | Hydro boundary barricaded; hot work permit; fire watch 60 min | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-146 | 2026-08-24 | RIG | Rig the press rolls with the 250 t crane Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 4 R. Okafor |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-145 | 2026-08-24 | MILL | Install felt rolls and blow boxes; gear mesh checks Dryer section, tending side | Suspended loads; pinch points; jogging drives | Approved lift plans; tag lines; guards on before jog | Lockout / tagout (energy isolation) | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-24 |
| JHA-144 | 2026-08-23 | CONC | Mix and pour epoxy grout under the press sole plates Press section sole plates | Chemical exposure; skin contact | SDS reviewed; gloves, face shields; spill kit at the pour | Luis Ortega · 8 Luis Ortega |
Carl Mendez, Superintendent 2026-08-23 | |
| JHA-143 | 2026-08-23 | RIG | Set press frames and rig the press rolls Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-23 |
| JHA-142 | 2026-08-23 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 10 Priya Raman |
Carl Mendez, Superintendent 2026-08-23 |
| JHA-141 | 2026-08-23 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 8 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-23 |
| JHA-140 | 2026-08-23 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-23 |
| JHA-139 | 2026-08-23 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-23 |
| JHA-138 | 2026-08-22 | CONC | Mix and pour epoxy grout under the press sole plates Press section sole plates | Chemical exposure; skin contact | SDS reviewed; gloves, face shields; spill kit at the pour | Luis Ortega · 8 Luis Ortega |
Carl Mendez, Superintendent 2026-08-22 | |
| JHA-137 | 2026-08-22 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 6 Priya Raman |
Carl Mendez, Superintendent 2026-08-22 |
| JHA-136 | 2026-08-22 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-22 |
| JHA-135 | 2026-08-22 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-22 |
| JHA-134 | 2026-08-22 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 5 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-22 |
| JHA-133 | 2026-08-21 | CONC | Mix and pour epoxy grout under the press sole plates Press section sole plates | Chemical exposure; skin contact | SDS reviewed; gloves, face shields; spill kit at the pour | Luis Ortega · 6 Luis Ortega |
Carl Mendez, Superintendent 2026-08-21 | |
| JHA-132 | 2026-08-21 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 8 Priya Raman |
Carl Mendez, Superintendent 2026-08-21 |
| JHA-131 | 2026-08-21 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-21 |
| JHA-130 | 2026-08-21 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 8 Marcus Lee |
Carl Mendez, Superintendent 2026-08-21 |
| JHA-129 | 2026-08-21 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 11 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-21 |
| JHA-128 | 2026-08-20 | CONC | Mix and pour epoxy grout under the press sole plates Press section sole plates | Chemical exposure; skin contact | SDS reviewed; gloves, face shields; spill kit at the pour | Luis Ortega · 12 Luis Ortega |
Carl Mendez, Superintendent 2026-08-20 | |
| JHA-127 | 2026-08-20 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 11 Wes Turner |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-126 | 2026-08-20 | RIG | Set press frames and rig the press rolls Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-125 | 2026-08-20 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 10 Priya Raman |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-124 | 2026-08-20 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-123 | 2026-08-20 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 11 Marcus Lee |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-122 | 2026-08-20 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-20 |
| JHA-121 | 2026-08-19 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 11 Wes Turner |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-120 | 2026-08-19 | RIG | Set press frames and rig the press rolls Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 6 R. Okafor |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-119 | 2026-08-19 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 10 Priya Raman |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-118 | 2026-08-19 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 11 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-117 | 2026-08-19 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-116 | 2026-08-19 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-19 |
| JHA-115 | 2026-08-18 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 9 Wes Turner |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-114 | 2026-08-18 | RIG | Set press frames and rig the press rolls Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 6 R. Okafor |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-113 | 2026-08-18 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 7 Priya Raman |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-112 | 2026-08-18 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 8 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-111 | 2026-08-18 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 5 Marcus Lee |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-110 | 2026-08-18 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-18 |
| JHA-109 | 2026-08-17 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 11 Wes Turner |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-108 | 2026-08-17 | RIG | Set press frames and rig the press rolls Press section and north pad | Suspended loads; crane on the north pad | Critical lift plan; exclusion zone; outrigger mats checked | Critical lift | R. Okafor · 6 R. Okafor |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-107 | 2026-08-17 | EI | Recouple drive motors and land instrument cables Drive side and MCC room | Stored electrical energy; rotating equipment | Group lockout; test before touch; guards on before jog | Lockout / tagout (energy isolation) | Priya Raman · 11 Priya Raman |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-106 | 2026-08-17 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 12 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-105 | 2026-08-17 | PIPE | Fit and weld condensate header section Basement, drive side | Hot work; burns; fumes | Hot work permit; fire watch 60 min; fume extraction | Hot work | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-104 | 2026-08-17 | MILL | Set new dryers and install gears Dryer section, tending side | Suspended loads; pinch points; gear mesh hand injuries | Approved lift plans; tag lines; hands off the mesh while jogging | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 8 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-17 |
| JHA-103 | 2026-08-16 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 10 Wes Turner |
Carl Mendez, Superintendent 2026-08-16 |
| JHA-102 | 2026-08-16 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 9 Priya Raman |
Carl Mendez, Superintendent 2026-08-16 |
| JHA-101 | 2026-08-16 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 5 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-16 |
| JHA-100 | 2026-08-16 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-16 |
| JHA-099 | 2026-08-16 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 6 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-16 |
| JHA-098 | 2026-08-15 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 8 Wes Turner |
Carl Mendez, Superintendent 2026-08-15 |
| JHA-097 | 2026-08-15 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 9 Priya Raman |
Carl Mendez, Superintendent 2026-08-15 |
| JHA-096 | 2026-08-15 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 8 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-15 |
| JHA-095 | 2026-08-15 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 10 Marcus Lee |
Carl Mendez, Superintendent 2026-08-15 |
| JHA-094 | 2026-08-15 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-15 |
| JHA-093 | 2026-08-14 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 5 Wes Turner |
Carl Mendez, Superintendent 2026-08-14 |
| JHA-092 | 2026-08-14 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 10 Priya Raman |
Carl Mendez, Superintendent 2026-08-14 |
| JHA-091 | 2026-08-14 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 9 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-14 |
| JHA-090 | 2026-08-14 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 8 Marcus Lee |
Carl Mendez, Superintendent 2026-08-14 |
| JHA-089 | 2026-08-14 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 11 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-14 |
| JHA-088 | 2026-08-13 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 7 Wes Turner |
Carl Mendez, Superintendent 2026-08-13 |
| JHA-087 | 2026-08-13 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 10 Priya Raman |
Carl Mendez, Superintendent 2026-08-13 |
| JHA-086 | 2026-08-13 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 12 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-13 |
| JHA-085 | 2026-08-13 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-13 |
| JHA-084 | 2026-08-13 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-13 |
| JHA-083 | 2026-08-12 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 9 Wes Turner |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-082 | 2026-08-12 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 8 R. Okafor |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-081 | 2026-08-12 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 12 Priya Raman |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-080 | 2026-08-12 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 11 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-079 | 2026-08-12 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 11 Marcus Lee |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-078 | 2026-08-12 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 5 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-12 |
| JHA-077 | 2026-08-11 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 10 Wes Turner |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-076 | 2026-08-11 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-075 | 2026-08-11 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 6 Priya Raman |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-074 | 2026-08-11 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 9 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-073 | 2026-08-11 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-072 | 2026-08-11 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 6 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-11 |
| JHA-071 | 2026-08-10 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 8 Wes Turner |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-070 | 2026-08-10 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 6 R. Okafor |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-069 | 2026-08-10 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 9 Priya Raman |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-068 | 2026-08-10 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-067 | 2026-08-10 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 11 Marcus Lee |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-066 | 2026-08-10 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-10 |
| JHA-065 | 2026-08-09 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 8 Wes Turner |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-064 | 2026-08-09 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 6 R. Okafor |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-063 | 2026-08-09 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 6 Priya Raman |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-062 | 2026-08-09 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-061 | 2026-08-09 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 10 Marcus Lee |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-060 | 2026-08-09 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 6 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-09 |
| JHA-059 | 2026-08-08 | MECH | Line bore and sleeve idler bores Gear case, drive side | Rotating boring bar; chips; noise | Bar guarded; area roped off; hearing protection | Lockout / tagout (energy isolation) | Wes Turner · 6 Wes Turner |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-058 | 2026-08-08 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-057 | 2026-08-08 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 6 Priya Raman |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-056 | 2026-08-08 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 11 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-055 | 2026-08-08 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-054 | 2026-08-08 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-08 |
| JHA-053 | 2026-08-07 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 9 R. Okafor |
Carl Mendez, Superintendent 2026-08-07 |
| JHA-052 | 2026-08-07 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 8 Priya Raman |
Carl Mendez, Superintendent 2026-08-07 |
| JHA-051 | 2026-08-07 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 7 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-07 |
| JHA-050 | 2026-08-07 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-08-07 |
| JHA-049 | 2026-08-07 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-07 |
| JHA-048 | 2026-08-06 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-06 |
| JHA-047 | 2026-08-06 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 9 Priya Raman |
Carl Mendez, Superintendent 2026-08-06 |
| JHA-046 | 2026-08-06 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 5 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-06 |
| JHA-045 | 2026-08-06 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 11 Marcus Lee |
Carl Mendez, Superintendent 2026-08-06 |
| JHA-044 | 2026-08-06 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 8 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-06 |
| JHA-043 | 2026-08-05 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 7 R. Okafor |
Carl Mendez, Superintendent 2026-08-05 |
| JHA-042 | 2026-08-05 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 8 Priya Raman |
Carl Mendez, Superintendent 2026-08-05 |
| JHA-041 | 2026-08-05 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-05 |
| JHA-040 | 2026-08-05 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-05 |
| JHA-039 | 2026-08-05 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-05 |
| JHA-038 | 2026-08-04 | RIG | Remove press rolls and frames with the 250 t crane Press section and north pad | Suspended loads over the press pit; wind | Critical lift plan reviewed; exclusion zone; wind limit 20 mph; signal person | Critical lift | R. Okafor · 10 R. Okafor |
Carl Mendez, Superintendent 2026-08-04 |
| JHA-037 | 2026-08-04 | EI | Disconnect drive motors and instruments Drive side and MCC room | Stored electrical energy | Group lockout; test before touch | Lockout / tagout (energy isolation) | Priya Raman · 5 Priya Raman |
Carl Mendez, Superintendent 2026-08-04 |
| JHA-036 | 2026-08-04 | SCAF | Erect and modify outage scaffolds Dryer section, top tier | Falls; dropped objects | Harness 100% tie-off; tool lanyards; area below barricaded | Work at height | Tony Alvarez · 6 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-04 |
| JHA-035 | 2026-08-04 | PIPE | Disconnect and cap steam and condensate lines Basement, drive side | Residual pressure and hot condensate; burns | Line break permit; lines drained and verified at zero; face shields | Lockout / tagout (energy isolation) Line break / opening process equipment | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-08-04 |
| JHA-034 | 2026-08-04 | MILL | Remove dryers and gears with the machine room crane Dryer section, tending side | Suspended loads; pinch points at journals; work at height on the top tier | Approved lift plans; tag lines; barricaded aisle; harness tied off above 6 ft | Lockout / tagout (energy isolation) Work at height | Dale Whitaker · 8 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-04 |
| JHA-033 | 2026-08-03 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-03 |
| JHA-032 | 2026-08-03 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 9 Marcus Lee |
Carl Mendez, Superintendent 2026-08-03 |
| JHA-031 | 2026-08-03 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-03 | |
| JHA-030 | 2026-08-02 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-02 |
| JHA-029 | 2026-08-02 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-08-02 |
| JHA-028 | 2026-08-02 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 6 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-02 | |
| JHA-027 | 2026-08-01 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 12 Tony Alvarez |
Carl Mendez, Superintendent 2026-08-01 |
| JHA-026 | 2026-08-01 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-08-01 |
| JHA-025 | 2026-08-01 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-08-01 | |
| JHA-024 | 2026-07-31 | SCAF | Modify top-tier platforms for dryer install Dryer section, top tier | Falls; dropped objects | Harness tie-off; tool lanyards; barricade below | Work at height | Tony Alvarez · 11 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-31 |
| JHA-023 | 2026-07-31 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-07-31 |
| JHA-022 | 2026-07-31 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-31 | |
| JHA-021 | 2026-07-30 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-30 | |
| JHA-020 | 2026-07-30 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-07-30 |
| JHA-019 | 2026-07-30 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-30 | |
| JHA-018 | 2026-07-29 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-29 | |
| JHA-017 | 2026-07-29 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 10 Marcus Lee |
Carl Mendez, Superintendent 2026-07-29 |
| JHA-016 | 2026-07-29 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 7 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-29 | |
| JHA-015 | 2026-07-28 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 8 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-28 | |
| JHA-014 | 2026-07-28 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 6 Marcus Lee |
Carl Mendez, Superintendent 2026-07-28 |
| JHA-013 | 2026-07-28 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 9 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-28 | |
| JHA-012 | 2026-07-27 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-27 | |
| JHA-011 | 2026-07-27 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 12 Marcus Lee |
Carl Mendez, Superintendent 2026-07-27 |
| JHA-010 | 2026-07-27 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-27 | |
| JHA-009 | 2026-07-26 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 7 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-26 | |
| JHA-008 | 2026-07-26 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 11 Marcus Lee |
Carl Mendez, Superintendent 2026-07-26 |
| JHA-007 | 2026-07-26 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-26 | |
| JHA-006 | 2026-07-25 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-25 | |
| JHA-005 | 2026-07-25 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 7 Marcus Lee |
Carl Mendez, Superintendent 2026-07-25 |
| JHA-004 | 2026-07-25 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 10 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-25 | |
| JHA-003 | 2026-07-24 | SCAF | Pre-build outage scaffold sections at the laydown Dryer section, top tier | Manual handling; dropped objects | Two-person lifts; barricaded laydown | Tony Alvarez · 10 Tony Alvarez |
Carl Mendez, Superintendent 2026-07-24 | |
| JHA-002 | 2026-07-24 | PIPE | Prefabricate steam and condensate spools in the shop Basement, drive side | Hot work; grinding sparks | Hot work permit; fire watch; screens | Hot work | Marcus Lee · 8 Marcus Lee |
Carl Mendez, Superintendent 2026-07-24 |
| JHA-001 | 2026-07-24 | MILL | Receive and stage new dryers and gears at the laydown Dryer section, tending side | Suspended loads; forklift traffic | Spotter for every forklift move; laydown barricaded | Dale Whitaker · 12 Dale Whitaker |
Carl Mendez, Superintendent 2026-07-24 |
Source: safety_pretask, safety_permit